Second Notice | | 7/20/2019 | 7/16/2019 | | DONE |
|
|
|
This permit finaled on the web by Michael McHargue
|
First Notice | | 6/9/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
Permanent Occupancy | | | 5/30/2019 | | DONE |
|
|
|
|
BLD-Final | 5/28/2019 | 5/28/2019 | 5/28/2019 | A | PASS |
Mike Jordan
|
|
|
All issues resolved. ok for perm occ.
|
BLD-Final | 5/22/2019 | 5/22/2019 | 5/22/2019 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Adam Joslin. Install remainder of carper and transitions. install base in restrooms. Mirror and sink mounted to high for ADA. remove exit sign in hall way.
|
FIRE-Final Inspection | 5/21/2019 | 5/21/2019 | 5/21/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Phone #: ###-#### Inspection requested via web by Michael McHargue
|
FIRE-Final Inspection | 5/20/2019 | 5/21/2019 | 5/21/2019 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Adam Joslin Inspection cancelled from web by: Michael McHargue
|
BLD-Ceiling Grid Inspection | 5/9/2019 | 5/9/2019 | 5/9/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Ceiling Grid Inspection | 5/7/2019 | 5/8/2019 | 5/8/2019 | A | NR |
Mike Jordan
|
|
|
early morning preference Phone #: ###-#### Inspection requested via web by Adam Joslin. Needs lelctrical and mech inspections first.
|
Print Occupancy Form | | | 4/2/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/2/2019 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 3/13/2019 | 3/13/2019 | 4/1/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod - Boise Image Enhancement - (routed to staff)
|
Plan Reviewer's activity | | | 4/1/2019 | | PASS |
|
|
|
The 1st plan mod was reviewed and approved. It could have been issued on 3-25-19 but wasn't because the Plans Examiner was on vacation. The issuance was delayed for a week until he got back on 4-1-19. Instructions were left to issue this permit when the review was completed but for some reason it wasn't.
|
Permit Ready to Issue | | | 4/1/2019 | | DONE |
|
|
|
Plan Mod Approved (fees due)
|
BLD-Energy code compliance | 3/26/2019 | 3/27/2019 | 3/27/2019 | A | PASS |
Mike Jordan
|
|
|
ADam Phone #: ###-####
|
BLD-Wall cover | 3/25/2019 | 3/26/2019 | 3/26/2019 | A | CANC |
Mike Jordan
|
|
|
Adam- wall cover -in Review status due to plan mod- adding appliances to kitchen Phone #: ###-####
|
BLD-Framing/Rough-in | 3/26/2019 | 3/26/2019 | 3/26/2019 | A | PASS |
Mike Jordan
|
|
|
Adam- wall cover -in Review status due to plan mod- adding appliances to kitchen Phone #: ###-####
|
Routing - PLUMBING | 3/21/2019 | | 3/25/2019 | | PASS |
Daryl Spivey
|
|
|
1) Install tempering device on lavs as required ISPC 407.3
|
BLD-Wall cover | 3/21/2019 | 3/22/2019 | 3/22/2019 | P | NR |
Mike Jordan
|
|
|
Permit had been issued but in Review status for Plan mod for adding kitchen appliances - please call Permit desk for any questions. Please call Adam for access Phone #: ###-####. Neeeds to complete airseal pack first.
|
Routing - PLAN CHECK | 3/22/2019 | | 3/22/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod approved
|
Routing PW Sewer Rating | 3/21/2019 | | 3/22/2019 | | PASS |
Angela Hardy
|
|
|
$336
|
Plan resubmittals received | | | 3/20/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 3/13/2019 | 3/16/2019 | 3/15/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Plan Reviewer's activity | | | 3/14/2019 | | FAIL |
|
|
|
The 1st plan mod plan intake failed because it was not compliant with accessibility issues. Called the Architect and explained the problem. Put a red line note on the drawings. Sent the workflow back to the applicant.
|
Plan resubmittals requested | | | 3/14/2019 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 3/13/2019 | | DONE |
|
|
|
plan mod accepted in e plan-changing the kitchen sink & addition of a dishwasher- sheets A-1.1, P-1, P-2, E-1 & E-3-assigned to CJW
|
Routing - PLAN CHECK | 3/20/2019 | | 2/21/2019 | | PASS |
Carl Westfall
|
|
|
1st plan mod approved
|
CHANGE ISSUED DATE | | | 2/19/2019 | | DONE |
|
|
|
permit was issued twice by mistake, corrected to original issued date.
|
Print Occupancy Form | | | 2/19/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/19/2019 | | DONE |
|
|
|
|
Meeting | | | 2/13/2019 | | DONE |
|
|
|
sent email to Adam Joslin informing him the rce number provided does not match the GC name on the revised value form
|
Routing - FIRE | 1/22/2019 | 1/22/2019 | 2/12/2019 | | PASS |
Mark Scharfen
|
|
|
IFC fire 02.12.2019.pdf. Complete.
|
Plan assigned to (CJW) | 1/22/2019 | 1/22/2019 | 2/12/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 02/07/19 (L3 - 15 days) (ePlan - 13 sheets) Boise Image Enhancement (L-3)
|
1st review completed | | | 2/12/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/12/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/12/2019 | | DONE |
|
|
|
NEED adam@prusikbuilt.com
met-ACHD
MET
REVISED VALUE
GC FORM
|
Routing - PLAN CHECK | 1/22/2019 | | 2/11/2019 | | PASS |
Carl Westfall
|
|
|
|
Routing - MECHANICAL | 1/22/2019 | | 1/25/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 1/22/2019 | | 1/25/2019 | | PASS |
David Moser
|
|
|
use allowed as per CUP08-00045 and CAR08-00009
|
Routing PW Solid Waste | 1/22/2019 | | 1/24/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Environmental | 1/22/2019 | | 1/23/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLUMBING | 1/22/2019 | | 1/23/2019 | | PASS |
Daryl Spivey
|
|
|
1) Install tempering device as required by ISPC 407.3 on lavs.
|
Routing - Addressing | 1/22/2019 | | 1/22/2019 | | PASS |
Doug Chausow
|
|
|
Ste 100
|
Routing - PUBLIC WORKS | 1/22/2019 | | 1/22/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 1/18/2019 | | PASS |
|
|
|
|
Application received | | | 1/8/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 8 2019 3:55PM
|