BLD-Final | 10/17/2019 | 10/21/2019 | 10/21/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 10/17/2019 | 10/21/2019 | 10/21/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.7
|
BLD-Energy code compliance | 8/13/2019 | 8/16/2019 | 8/16/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 8/13/2019 | 8/14/2019 | 8/14/2019 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate...
|
BLD-Wall Bracing | 7/30/2019 | 7/30/2019 | 7/30/2019 | P | PASS |
Brandon Shaw
|
|
|
& fascia - Jorge Phone #: ###-####
|
BLD-Foundation | 4/1/2019 | 4/1/2019 | 4/1/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 3/28/2019 | 3/29/2019 | 3/29/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
PubWorks Subgrade Approval | 3/27/2019 | 3/27/2019 | 3/27/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Inspection Record Card- Bld | | | 1/25/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/25/2019 | | DONE |
|
|
|
|
Meeting | | | 1/24/2019 | | DONE |
|
|
|
Emailed Josh to inform him the fire plan check fee was missed and once that is paid we can issue the permits.
|
OVERRIDE | | | 1/17/2019 | | |
|
|
|
|
Routing - FIRE | 1/16/2019 | 1/16/2019 | 1/17/2019 | | PASS |
Lee G Meredith
|
|
|
Fire sprinklers are not required.
|
Plan assigned to (RDP) | 1/15/2019 | 1/15/2019 | 1/17/2019 | | DONE |
Rob Patrick
|
|
|
Differed from Brian on 1/15. 1/16, review complete just need Fire to sign off.
|
Routing - PLAN CHECK | 1/15/2019 | | 1/17/2019 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 1/17/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/17/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 1/17/2019 | | DONE |
|
|
|
|
Routing - MECHANICAL | 1/14/2019 | | 1/16/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 1/14/2019 | 1/17/2019 | 1/15/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (BJM) | 1/14/2019 | 1/14/2019 | 1/15/2019 | | DEFR |
Brian McGowan
|
|
|
01/25 sfd ePlan L1
|
Plans ACCEPTED BY PLAN TECH | | | 1/14/2019 | | DONE |
|
|
|
|
Intake Approval | | | 1/14/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/14/2019 | | DONE |
|
|
|
|
Routing - PLANNING | 1/14/2019 | | 1/14/2019 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 1/14/2019 | | 1/14/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/14/2019 | | 1/14/2019 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 1/11/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 11 2019 10:09AM
|