Print Statement | | | 9/25/2019 | | DONE |
|
|
|
|
Telephone call | | | 9/25/2019 | | DONE |
|
|
|
called Brandon to get final values on the plumbing-Mountain West is $56205.00 and SC Construction is $40000.00
|
FIRE-Final Inspection | 9/18/2019 | 9/18/2019 | 9/18/2019 | P | PASS |
Jim Page
|
|
|
Fire alarm issues have been resolved under FIR19-00588, final life fire safety inspwection for areas of work complete.
|
Print Occupancy Form | | | 9/6/2019 | | DONE |
|
|
|
|
Permanent Occupancy | | | 9/6/2019 | | DONE |
|
|
|
|
BLD-Final | 9/4/2019 | 9/5/2019 | 9/5/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Final | 8/8/2019 | 8/12/2019 | 8/9/2019 | A | PART |
Dave Hannah
|
|
|
Doug Phone #: ###-#### ok for 30 day temp occ needs to add handrails to ext stairs change door hardwear on ext door out of pre k rm
|
Temporary Occupancy | 8/9/2019 | 11/7/2019 | 8/9/2019 | | DONE |
Brittany Hill
|
|
|
|
Telephone call | | | 8/9/2019 | | DONE |
|
|
|
Spoke with Brandon informing him that fire and bld inspectors only gave a 30 day temp. emailed new one to him bgrote@beniton.com
|
FIRE-Final Inspection | 8/8/2019 | 8/8/2019 | 8/8/2019 | P | PART |
Jim Page
|
|
|
Partial final inspection for life fire safety inspection complete, final sign off is contingent upon FIR19-00588 being completed for the out of sync correction for fire alarm system. Scope of work for JCI on the fire alarms is complete, no fire sprinklers, fire extinguishers are placed with current inspection tags. 30 day TCO authorized per conversation with Romeo Gervais with Boise Fire for life fire safety.
Rescheduled by Doug for PM inspection when JCI can have a technician on site. 208.860.1445
|
FIRE-Final Inspection | 8/8/2019 | 8/9/2019 | 8/8/2019 | P | NR |
Mark Scharfen
|
|
|
JCI unable to be on site till 8/9/2019-Afternoon to sound off horn strobes to make sure audibility noticed on last inspection has been repaired. Rescheduled.
Doug Phone #: ###-####
|
BLD-Final | 8/7/2019 | 8/8/2019 | 8/8/2019 | P | DONE |
Dave Hannah
|
|
|
Please call when in route.
Thanks,
Doug S. Phone #: ###-#### >> Inspection requested via web by Brandon Grote
|
FIRE-Final Inspection | 8/7/2019 | 8/7/2019 | 8/8/2019 | P | DONE |
Mark Scharfen
|
|
|
Fire/life/safety inspection. Please call when in route.
Thanks,
Doug S. Phone #: ###-#### >> Inspection requested via web by Brandon Grote
|
FIRE-Final Inspection | 7/29/2019 | 8/2/2019 | 8/2/2019 | P | CANC |
Jim Page
|
|
|
Phone #: ###-#### >> Inspection requested via web by Doug Storey
|
FIRE-Conference | 7/18/2019 | 7/19/2019 | 7/18/2019 | A | CANC |
Jim Page
|
|
|
Room 102 (Front Office) Phone #: ###-#### >> Inspection requested via web by Doug Storey Inspection cancelled from web by: Doug Storey
|
BLD-Conference | 7/18/2019 | 7/18/2019 | 7/18/2019 | P | PASS |
Dave Hannah
|
|
|
Room 102 Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Ceiling Grid Inspection | 6/13/2019 | 6/14/2019 | 6/14/2019 | P | PASS |
Dave Hannah
|
|
|
Rooms 102, 132, 130 please. Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Framing/Rough-in | 5/15/2019 | 5/16/2019 | 5/16/2019 | A | PASS |
Dave Hannah
|
|
|
Room 100, 130 Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Framing/Rough-in | 5/9/2019 | 5/10/2019 | 5/10/2019 | A | PASS |
Jim Storey
|
|
|
Rooms 107A, 106A, 148, 131 Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Foundation | 5/8/2019 | 5/8/2019 | 5/8/2019 | A | PASS |
Dave Hannah
|
|
|
South Entry Stem Walls. Would like to pour about noon. Not sure if this has been looked at yet. Thank You. Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Foundation | 5/7/2019 | 5/7/2019 | 5/8/2019 | P | PASS |
Dave Hannah
|
|
|
South Entry Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Energy code compliance | 4/23/2019 | 4/24/2019 | 4/25/2019 | P | PASS |
Dave Hannah
|
|
|
Rooms 130, 131, and 132. Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Framing/Rough-in | 4/19/2019 | 4/22/2019 | 4/22/2019 | A | PART |
Jim Storey
|
|
|
Rooms 130, 131, 132. Phone #: ###-#### Inspection requested via web by Doug Storey ceilling ok to insulate// ok to cover all but corridor fur out wall need finsh gyp protection.
|
BLD-Framing/Rough-in | 4/11/2019 | 4/12/2019 | 4/12/2019 | P | PASS |
Dave Hannah
|
|
|
Rooms 102 and 121 Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Footing | 3/27/2019 | 3/28/2019 | 3/28/2019 | A | PASS |
Dave Hannah
|
|
|
South Entry Footing, trying for a 12 pm noon pour. Thank you. Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Conference | 3/27/2019 | 3/28/2019 | 3/28/2019 | A | PASS |
Dave Hannah
|
|
|
Architect would like to meet with building Inspector regarding walls in room 130. Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Foundation | 3/26/2019 | 3/27/2019 | 3/27/2019 | A | DONE |
Tony Young
|
|
|
Stem wall inspection, north entry. Quality concrete is trying for a 9 am pour.. Thanks. Phone #: ###-#### Inspection requested via web by Doug Storey
|
BLD-Footing | 3/25/2019 | 3/26/2019 | 3/26/2019 | A | PART |
Tony Young
|
|
|
Footing Inspection on North side of building. Would it be possible for a 7:30 am inspection. Thank you. Phone #: ###-#### Inspection requested via web by Doug Storey,, entry footing
|
Issue PAID IN FULL permit | | | 3/12/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/12/2019 | | DONE |
|
|
|
|
Telephone call | | | 3/11/2019 | | DONE |
|
|
|
emailed fees due but let Bradon know we still need the RP
|
OVERRIDE | | | 3/1/2019 | | |
|
|
|
|
Plan assigned to (JAR) | 1/24/2019 | 1/24/2019 | 3/1/2019 | | DONE |
Julie Romig
|
|
|
02/25 - 1st Rev Comp - IBC 2nd Rev Comp - L2 Fort Boise School
|
Routing - ELECTRICAL | 2/19/2019 | | 3/1/2019 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/1/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/1/2019 | | DONE |
|
|
|
MET-GC Form
MET-Revised Value (use the states fees for plan check fees)
MET-RP
|
Routing - Erosion and Sediment | 2/26/2019 | | 2/27/2019 | | PASS |
Michael Zawacki
|
|
|
waiver request approved.
|
Routing - PLAN CHECK | 2/19/2019 | | 2/27/2019 | | PASS |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 2/19/2019 | | 2/20/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 2/19/2019 | | 2/19/2019 | | PASS |
Dan Ediger
|
|
|
Per plans and ISPC
|
Routing - PUBLIC WORKS | 2/19/2019 | | 2/19/2019 | | PASS |
Angela Hardy
|
|
|
|
Route to Impact Fee Review | 2/1/2019 | 2/4/2019 | 2/1/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 1/24/2019 | 1/24/2019 | 2/1/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 2/1/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing PW Environmental | 1/24/2019 | | 1/31/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLAN CHECK | 1/24/2019 | | 1/31/2019 | | FAIL |
Julie Romig
|
|
|
Plan review report emailed to architect.
|
Routing - MECHANICAL | 1/24/2019 | | 1/28/2019 | | FAIL |
Troy James
|
|
|
|
Routing - ELECTRICAL | 1/28/2019 | | 1/28/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLANNING | 1/24/2019 | | 1/25/2019 | | PASS |
David Moser
|
|
|
No expansion of school facility and ADA ramps outside of setbacks.
|
Routing - Addressing | 1/24/2019 | | 1/24/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/24/2019 | | 1/24/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - PLUMBING | 1/24/2019 | | 1/24/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 1/23/2019 | | PASS |
|
|
|
|
Intake Approval | | | 1/18/2019 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following:
1. Mechanical and Plumbing sheets are in the incorrect orientation.
2. Planning and Zoning approval letter is not uploaded to the documents folder.
|
Application received | | | 1/13/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 13 2019 4:08PM
|