Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-00165
StatusFinaled
Name STOCK CONSTRUCTION MANAGEMENT
Site Address 100 S 6TH ST
Project NameChina Blue Repair
Customer Number 
ePlanReviewNo
Description
(CHINA BLUE REPAIR) ""THIS IS AN EXPEDITED (MAX 10 DAYS) PERMIT PROCESS ASAP"" Permit to replace the existing failing roof system with work to include the removal of the existing roof on the front portion of the building and replacing it with a new roof truss system per the approved plans and the attached engineering. THERE ARE NO INTERIOR ALTERATIONS, NEW LIGHTING OR INTERIOR FINISHES APPROVED UNDER THIS PERMIT. This is a scope of work permit only with a certificate of completion to be issued upon completion and approval of the repair. All work per the approved plans. This building is fully fire sprinklered for A-2 occupant load over 300 and an A-2 fire area exceeding 5000 sq. ft.. Any alterations to the sprinkler system will require a separate permit and shall comply with NFPA 13 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/2/20198/2/20198/2/2019PPASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Joel Hartman
FIRE-Final Inspection8/2/20198/2/20198/2/2019PPASS
DetailsJim Page
Final life fire safety inspection for scope of work complete.

Joel Phone #: ###-####
Zoning Approval8/2/20198/2/20198/2/2019 PASS
DetailsKayCee Babb
Per DRH19-00015.
CHANGE STATUS TO (FNL)  8/2/2019 DONE
BLD-Energy code compliance6/10/20196/10/20196/11/2019PPASS
DetailsDave Hannah
insulation in roof trusses ok
BLD-Other6/10/20196/10/20196/10/2019APASS
DetailsDave Hannah
Going to start drywall on ceiling today, wasn''t sure if you need to look at the insulation before we cover. Phone #: ###-#### Inspection requested via web by Joel Hartman ok to cover after other trades ok rough ins
BLD-Other5/14/20195/15/20195/15/2019APEND
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Joel Hartman roof framing ok but need engineer sign off on epx bolts
Issue PAID IN FULL permit  2/21/2019 DONE
Letter of compliance/Occupancy  2/21/2019 DONE
Plan assigned to (CDM)1/15/20191/15/20192/15/2019 PASS
DetailsCarl D Madsen
China Blue Repair
Case Summary (BLD)  2/15/2019 DONE
PLANS/APPL TAKEN TO FRONT DESK  2/15/2019 DONE
Routing Off Site - STRUCTURAL2/15/2019 2/15/2019 PASS
DetailsCarl D Madsen
Permit Ready to Issue  2/15/2019 DONE
MET
need
gc
rev cert of val
Print Occupancy Form  2/15/2019 DONE
Inspection Record Card- Bld  2/15/2019 DONE
Telephone call  2/15/2019 DONE
Spoke with Steven informing him that this permit is ready but still need the 302 and 306 forms filled out by the GC so we can add in the rest of the fees
Plan Modification Accepted  2/4/2019 DONE
2nd submittal-received 3 sets of calcs, S0.0, S2.0 & S3.0-took to Carl M who had me send to outside engineering with CH2nhill-left message on there phone
Route to Impact Fee Review1/29/20192/1/20191/30/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit

No impact fees assessed as no change in use and no new square footage. SLC
Routing - FIRE1/15/20191/19/20191/23/2019 PASS
DetailsErika Akin
Attached comments to case and plans
1st review completed  1/23/2019 DONE
Routing Off Site - STRUCTURAL1/29/2019 1/19/2019 FAIL
DetailsCarl D Madsen
Case Summary (BLD)  1/19/2019 DONE
Routing - PLAN CHECK1/15/2019 1/19/2019 PASS
DetailsCarl D Madsen
Routing - Design Review1/15/2019 1/15/2019 PASS
DetailsKayCee Babb
Per DRH19-00015. Comply with all conditions of approval, including exterior plates shall be non-reflective and finished appropriately.
CHANGE STATUS TO (REV)  1/15/2019 DONE
DetailsAdele J Schaffeld-Griffin
Issued on Accident
Plans ACCEPTED BY PLAN TECH  1/15/2019 DONE
Intake Approval  1/15/2019 PASS
Recd Pcfee & Taken To Pln CK  1/15/2019 DONE
Application received 1/15/2019