BLD-Final | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hartman
|
FIRE-Final Inspection | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Jim Page
|
|
|
Final life fire safety inspection for scope of work complete.
Joel Phone #: ###-####
|
Zoning Approval | 8/2/2019 | 8/2/2019 | 8/2/2019 | | PASS |
KayCee Babb
|
|
|
Per DRH19-00015.
|
CHANGE STATUS TO (FNL) | | | 8/2/2019 | | DONE |
|
|
|
|
BLD-Energy code compliance | 6/10/2019 | 6/10/2019 | 6/11/2019 | P | PASS |
Dave Hannah
|
|
|
insulation in roof trusses ok
|
BLD-Other | 6/10/2019 | 6/10/2019 | 6/10/2019 | A | PASS |
Dave Hannah
|
|
|
Going to start drywall on ceiling today, wasn''t sure if you need to look at the insulation before we cover. Phone #: ###-#### Inspection requested via web by Joel Hartman ok to cover after other trades ok rough ins
|
BLD-Other | 5/14/2019 | 5/15/2019 | 5/15/2019 | A | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hartman roof framing ok but need engineer sign off on epx bolts
|
Issue PAID IN FULL permit | | | 2/21/2019 | | DONE |
|
|
|
|
Letter of compliance/Occupancy | | | 2/21/2019 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 1/15/2019 | 1/15/2019 | 2/15/2019 | | PASS |
Carl D Madsen
|
|
|
China Blue Repair
|
Case Summary (BLD) | | | 2/15/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/15/2019 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 2/15/2019 | | 2/15/2019 | | PASS |
Carl D Madsen
|
|
|
|
Permit Ready to Issue | | | 2/15/2019 | | DONE |
|
|
|
MET
need
gc
rev cert of val
|
Print Occupancy Form | | | 2/15/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/15/2019 | | DONE |
|
|
|
|
Telephone call | | | 2/15/2019 | | DONE |
|
|
|
Spoke with Steven informing him that this permit is ready but still need the 302 and 306 forms filled out by the GC so we can add in the rest of the fees
|
Plan Modification Accepted | | | 2/4/2019 | | DONE |
|
|
|
2nd submittal-received 3 sets of calcs, S0.0, S2.0 & S3.0-took to Carl M who had me send to outside engineering with CH2nhill-left message on there phone
|
Route to Impact Fee Review | 1/29/2019 | 2/1/2019 | 1/30/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
No impact fees assessed as no change in use and no new square footage. SLC
|
Routing - FIRE | 1/15/2019 | 1/19/2019 | 1/23/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case and plans
|
1st review completed | | | 1/23/2019 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 1/29/2019 | | 1/19/2019 | | FAIL |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 1/19/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/15/2019 | | 1/19/2019 | | PASS |
Carl D Madsen
|
|
|
|
Routing - Design Review | 1/15/2019 | | 1/15/2019 | | PASS |
KayCee Babb
|
|
|
Per DRH19-00015. Comply with all conditions of approval, including exterior plates shall be non-reflective and finished appropriately.
|
CHANGE STATUS TO (REV) | | | 1/15/2019 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Issued on Accident
|
Plans ACCEPTED BY PLAN TECH | | | 1/15/2019 | | DONE |
|
|
|
|
Intake Approval | | | 1/15/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/15/2019 | | DONE |
|
|
|
|
Application received | | 1/15/2019 | | | |
|
|
|
|