Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-00199
StatusFinaled
Name CBH HOMES
Site Address 5944 S CHINOOK WAY
Project NameLOT 03 BLK 04 FORK SOUTH SUB N
Customer Number 
ePlanReviewYes
Description
Permit for the construction of a new 2,230 sq. ft., two story (first story 1,218 sq. ft., second story 1,012 sq. ft.) single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 59 sq. ft. of covered patio/porch and a 707-sq. ft. attached garage per the approved plans, engineering, local codes and any notations. Prescriptive Energy Compliance. R-1C zoning and setbacks per planning. ***RDP***
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/21/20196/24/20196/24/2019APASS
DetailsMike Jordan
garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD-Blower Door Test Results6/24/20196/24/20196/24/2019ADONE
DetailsMike Jordan
4.8
DOC - Permit Finaled6/24/20196/24/20196/24/2019PPASS
DetailsMike Jordan
BLD-Energy code compliance4/29/20194/30/20194/30/2019APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD-Framing/Rough-in4/22/20194/26/20194/26/2019PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Install missed lateral brace on E1 truss in garage. Ok to insulate.
BLD-Wall Bracing4/17/20194/18/20194/18/2019APASS
DetailsJim Sly
This one already had shear documented done, but I believe it was a mix up with house down the street with same lot and block, Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD-Foundation3/28/20193/28/20193/28/2019PPASS
DetailsDave Hannah
Dane Phone #: ###-####
BLD-Footing3/26/20193/27/20193/27/2019PPASS
DetailsMike Jordan
Dane Phone #: ###-####
BLD-Framing/Rough-in2/26/20192/27/20192/27/2019PCANC
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Wrong permit called in. this lot not built yet.
BLD-Wall Bracing2/18/20192/19/20192/19/2019APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Joel Hirtle
Issue PAID IN FULL permit  2/15/2019 DONE
OVERRIDE  1/31/2019  
Plan assigned to (RDP)1/18/20191/18/20191/31/2019 DONE
DetailsRob Patrick
1/30 sfd L1 ePlan...1/24; Failed...1/30; Failed, No Comments Addressed
Routing - PLAN CHECK1/31/2019 1/31/2019 PASS
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  1/31/2019 DONE
DetailsRob Patrick
Permit Ready to Issue  1/31/2019 DONE
Met
Routing - PLAN CHECK1/30/2019 1/30/2019 FAIL
DetailsRob Patrick
No comments were addressed
Routing - PLAN CHECK1/30/2019 1/30/2019 FAIL
DetailsRob Patrick
Corrections Required
Routing - PLAN CHECK1/18/2019 1/24/2019 FAIL
DetailsRob Patrick
Corrections Required
1st review completed  1/24/2019 FAIL
DetailsRob Patrick
Corrections Required
Routing - MECHANICAL1/17/2019 1/23/2019 PASS
DetailsChad Schwendiman
Route to Impact Fee Review1/17/20191/20/20191/18/2019 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Plan assigned to (J_N)1/17/20191/17/20191/18/2019 DEFR
DetailsJenny Nelson
Routing - Addressing1/17/2019 1/18/2019 PASS
DetailsDoug Chausow
Application received  1/17/2019 DONE
Application submitted via PDS Online on Jan 17 2019 10:10AM
Intake Approval  1/17/2019 FAIL
1.The Calcs and the ACHD receipt are named the exact same. Can you please re-upload them with different file names in the document folder. (we can delete the current files once they have been re-uploaded)
2. Please provide the stair section details showing the treads and risers requirements.
Plans ACCEPTED BY PLAN TECH  1/17/2019 DONE
Intake Approval  1/17/2019 PASS
Recd Pcfee & Taken To Pln CK  1/17/2019 DONE
Routing - PUBLIC WORKS1/17/2019 1/17/2019 PASS
DetailsMorgan Webb
Routing - PLANNING1/17/2019 1/17/2019 PASS
DetailsSue Cummings