BLD-Final | 9/3/2019 | 9/4/2019 | 9/4/2019 | A | PASS |
Mike Jordan
|
|
|
Garage code 7530 Phone #: ###-#### Inspection requested via web by Rustin Ray
|
DOC - Permit Finaled | 9/4/2019 | 9/4/2019 | 9/4/2019 | P | PASS |
Mike Jordan
|
|
|
All issues have been resolved. An additional handrail has been installed on opposite side of existing handrail.
|
BLD-Blower Door Test Results | 9/4/2019 | 9/4/2019 | 9/4/2019 | A | DONE |
Mike Jordan
|
|
|
5.6
|
BLD-Final | 7/31/2019 | 8/1/2019 | 8/1/2019 | A | FAIL |
Mike Jordan
|
|
|
Garage code 7530 Phone #: ###-#### Inspection requested via web by Rustin Ray. Provide blower door test results and post. Complte fire caulking in gargae. provide code compliant handrail.
|
BLD-Final | 7/16/2019 | 7/16/2019 | 7/16/2019 | P | NR |
Mike Jordan
|
|
|
Garage code 7530 Phone #: ###-#### Inspection requested via web by Rustin Ray. Mech. final has failed.
|
BLD-Energy code compliance | 4/24/2019 | 4/25/2019 | 4/25/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Rustin Ray
|
BLD-Framing/Rough-in | 4/22/2019 | 4/23/2019 | 4/23/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Rustin Ray
|
BLD-Wall Bracing | 4/2/2019 | 4/3/2019 | 4/3/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Rustin Ray
|
BLD-Foundation | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | PASS |
Brandon Shaw
|
|
|
Previous enrty note error... Foundation is ok to pour...
|
BLD-Foundation | 2/15/2019 | 2/15/2019 | 2/15/2019 | P | NR |
Brandon Shaw
|
|
|
Need Geo sub-grade letter submitted and approved by PW...
|
BLD-Footing | 2/12/2019 | 2/13/2019 | 2/13/2019 | A | PART |
Mike Jordan
|
|
|
Darrin Phone #: ###-####, please go towards the end of the morning if possible, thank you
|
Place hold on job | 2/7/2019 | | 2/11/2019 | | DONE |
Tiffany Carson-Herker
|
|
|
waiting for signed permit
|
Inspection Record Card- Bld | | | 2/7/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/7/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 2/6/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 1/30/2019 | 1/30/2019 | 2/6/2019 | | DONE |
Jenny Nelson
|
|
|
02/04 #402 L1 ePlan. 2nd complete, unreadable plans. 1st complete 1/31, clarify girder truss at back of house
|
Routing - PLAN CHECK | 2/6/2019 | | 2/6/2019 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/6/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 2/6/2019 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 2/4/2019 | | 2/4/2019 | | FAIL |
Jenny Nelson
|
|
|
Unreadable plans
|
1st review completed | | | 1/31/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 1/22/2019 | | 1/31/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Plan assigned to (M_H) | 1/22/2019 | | 1/30/2019 | | DEFR |
Michael Hanson
|
|
|
02/04 #402 L1 ePlan
|
Route to Impact Fee Review | 1/22/2019 | 1/25/2019 | 1/24/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 1/23/2019 | | 1/23/2019 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 1/22/2019 | | 1/23/2019 | | FAIL |
Troy James
|
|
|
Emailed corrections to Rubin.
|
Routing - PLANNING | 1/22/2019 | | 1/22/2019 | | PASS |
Sue Cummings
|
|
|
See redlines on site plan.
|
Routing - Addressing | 1/22/2019 | | 1/22/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/22/2019 | | 1/22/2019 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/22/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/22/2019 | | DONE |
|
|
|
|
Intake Approval | | | 1/18/2019 | | FAIL |
|
|
|
Need to re-upload sheets - not readable. Need crawl space access and attic access. Need demo permit info - are they going to pull a separate permit, put a demo on this permit, or move the house.
|
Application received | | | 1/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 17 2019 4:30PM
|