BLD-Final | 9/5/2019 | 9/6/2019 | 9/6/2019 | A | PART |
Tell Riley
|
|
|
Tell we fire caulked as requested and added the glass and can show you that it is fire rated so if you would please give me a 20 minute head start i will be in Meridian tomorrow. thank you Phone #: ###-#### Inspection requested via web by Russell Valline//corrections made//final is complete pending fire final approval//temp occupancy approved until fire finals//
|
BLD-Final | 9/4/2019 | 9/5/2019 | 9/6/2019 | A | FAIL |
Tell Riley
|
|
|
Tell came out but only gave partial due to fire final not complete this was completed september 4 2019 Phone #: ###-#### Inspection requested via web by Russell Valline//need to fire caulk penetrations in rated rooms and corridor//need to add glass in doors to complete rated corridor//
|
FIRE-Final Inspection | 9/4/2019 | 9/5/2019 | 9/5/2019 | A | PART |
Troy Cobbley
|
|
|
A temporary for life safety is ok per boise fire until the upgrade agreement for the fire alarm system has been finalized. Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Final | 8/15/2019 | 8/16/2019 | 8/16/2019 | A | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline//emergency discharge light is now working//need doors on rooms//
|
FIRE-Final Inspection | 8/15/2019 | 8/16/2019 | 8/16/2019 | A | PART |
Mark Scharfen
|
|
|
Emergency discharge light not working. All e-lights inside functioned correctly. Extinguisher hung. No doors are hung. Will verify discharge either at fire alarm test or when building final is rescheduled.
Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Ceiling Grid Inspection | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | PASS |
Tell Riley
|
|
|
Please give me a call if you cant make it by 3:00 Phone #: ###-#### Inspection requested via web by Russell Valline//trades passed for grid cover//grid ok per plans//
|
BLD-Other | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | DONE |
Tell Riley
|
|
|
Please give me a call if you cant make it by 3:00 Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Ceiling Grid Inspection | 8/1/2019 | 8/2/2019 | 8/2/2019 | A | NR |
Tell Riley
|
|
|
Thomas Phone #: ###-####//need fire rough in inspection and electrical rough for cover of ceiling grid//
|
BLD-Framing/Rough-in | 7/11/2019 | 7/12/2019 | 7/12/2019 | A | PASS |
Tell Riley
|
|
|
Tell we have all the other inspector coming also to sign off on hv/ac and plumbing rough in. Maybe give me a call before your arrival. Phone #: ###-#### Inspection requested via web by Russell Valline//rough ins all passed//ok to cover framing//
|
BLD-Framing/Rough-in | 7/3/2019 | 7/8/2019 | 7/8/2019 | A | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline//framing ok per plans//ok to one side at plumbing walls//add nail plates wher needed//call for grid inspection//no insulation--interior walls//
|
BLD-Framing/Rough-in | 6/26/2019 | 6/27/2019 | 6/27/2019 | A | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline//wanted to start rated corridors//no cover until mech/plumbing/electrical roughs//advised to call Daryl to discuss//
|
BLD-Ceiling Grid Inspection | 4/24/2019 | 4/25/2019 | 4/25/2019 | A | PART |
Jim Sly
|
|
|
come late in the am if you could have fire roughin in the am. Thanks Phone #: ###-#### Inspection requested via web by Russell Valline Areas West side of Gym......OK.
|
Issue PAID IN FULL permit | | | 3/22/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/22/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/11/2019 | | DONE |
|
|
|
MET
Need
GC Form
Revised Cert of Value (DO NOT CHARGE OVER STATE PLAN REVIEW FEE)
|
Plan assigned to (CDM) | 2/7/2019 | 2/7/2019 | 3/9/2019 | | PASS |
Carl D Madsen
|
|
|
Fairmont School (expedited)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/9/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/5/2019 | | 3/9/2019 | | PASS |
Carl D Madsen
|
|
|
|
Routing - FIRE | 3/5/2019 | 3/5/2019 | 3/8/2019 | | PASS |
Mark Scharfen
|
|
|
IFC final review 03.08.2019.pdf
|
Routing - MECHANICAL | 3/5/2019 | | 3/6/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 2/21/2019 | 2/24/2019 | 2/21/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 2/21/2019 | | DONE |
|
|
|
|
Routing - ELECTRICAL | 2/7/2019 | | 2/21/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 2/7/2019 | | 2/20/2019 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - FIRE | 2/7/2019 | 2/7/2019 | 2/14/2019 | | FAIL |
Mark Scharfen
|
|
|
IFC Fire code 1st review 02.14.2019.pdf. Emailed architect.
|
Routing - MECHANICAL | 2/7/2019 | | 2/8/2019 | | FAIL |
Troy James
|
|
|
|
Routing - Addressing | 2/7/2019 | | 2/8/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/7/2019 | | 2/8/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLUMBING | 2/7/2019 | | 2/7/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC
|
Intake Approval | | | 2/4/2019 | | PASS |
|
|
|
|
Intake Approval | | | 1/24/2019 | | FAIL |
Joe Bruce
|
|
|
1) Plan sheets do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” (4"x4" on cover) space located 3” off the right sheet edge to allow for the title block. Verify ALL plan sheets have the required space for city approval stamp. See city submittal standards document at this link: https://pds.cityofboise.org/media/464072/pdox86_electronic_standards_full_050718.pdf
|
Application received | | | 1/18/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 18 2019 3:39PM
|
Agreement of Future work | 11/8/2019 | 12/31/2022 | | | |
Joe Bruce
|
|
|
(FAIRMONT JUNIOR HIGH) Upgrade Agreement attached to this case - work to be completed by 12/31/2022.
|