First Notice | | 4/28/2019 | 4/23/2019 | | DONE |
|
|
|
This permit finaled on the web by Todd Kurns
|
Permanent Occupancy | | | 4/18/2019 | | DONE |
|
|
|
|
BLD-Final | 4/11/2019 | 4/12/2019 | 4/12/2019 | A | PASS |
Jim Sly
|
|
|
Jeff Phone #: ###-####
|
BLD-Final | 4/11/2019 | 4/12/2019 | 4/12/2019 | P | PASS |
Jim Sly
|
|
|
Jim,
I hope the HVAC is done. Thx. Todd. Code to door 0912 Phone #: ###-#### Inspection requested via web by Todd Kurns OK for Perm. Occ.
|
BLD-Final | 4/9/2019 | 4/10/2019 | 4/10/2019 | P | NR |
Jim Sly
|
|
|
Jim, thanks for heads up on HVAC inspection. Code to door is 0912. Thx todd Phone #: ###-#### Inspection requested via web by Todd Kurns Needd Mech......
|
BLD-Final | 4/8/2019 | 4/9/2019 | 4/9/2019 | P | NR |
Jim Sly
|
|
|
Jim,
The code is 0912 if no one is there. Call me if you have questions. Thx. Todd Phone #: ###-#### Inspection requested via web by Todd Kurns Need Mech final.
|
FIRE-Final Inspection | 4/9/2019 | 4/9/2019 | 4/9/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Troy. Lockbox code is 0912. Thx todd Phone #: ###-#### Inspection requested via web by Todd Kurns
|
BLD-Ceiling Grid Inspection | 3/5/2019 | 3/6/2019 | 3/6/2019 | A | PASS |
Jim Sly
|
|
|
Jim,
Here you go for ceiling inspection. Thanks Phone #: ###-#### Inspection requested via web by Todd Kurns
|
BLD-Framing/Rough-in | 3/4/2019 | 3/5/2019 | 3/5/2019 | A | PASS |
Jim Sly
|
|
|
Jim,
There is a lock box on the front door. The code is 0912. If you have issues getting in please call me. Thanks, Todd Phone #: ###-#### Inspection requested via web by Todd Kurns
|
Telephone call | | | 3/1/2019 | | DONE |
|
|
|
called Todd and left message that the address changed and he needs to let the sub contractors know. I also let him know he gave out the wrong BLD # to some of the subs and asked him to make sure he's using the correct BLD #
|
Issue PAID IN FULL permit | | | 2/20/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/20/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/13/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 2/13/2019 | | DONE |
|
|
|
Met
|
Plan assigned to (M_H) | 1/30/2019 | | 2/13/2019 | | DONE |
Michael Hanson
|
|
|
02/13 #518 L2 ePlan. 1st review completed - Pending floor plan changes.
|
Routing - PLAN CHECK | 2/12/2019 | | 2/12/2019 | | PASS |
Michael Hanson
|
|
|
|
Route to Impact Fee Review | 2/7/2019 | 2/10/2019 | 2/8/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 1/30/2019 | | 2/7/2019 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required.
|
1st review completed | | | 2/7/2019 | | FAIL |
Michael Hanson
|
|
|
|
Routing - Addressing | 1/30/2019 | | 1/31/2019 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 1/30/2019 | | 1/31/2019 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 1/30/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 1/25/2019 | | FAIL |
Joe Bruce
|
|
|
1. Fire extinguishers are a requirement of this space. Please provide fire extinguisher locations on the plans per the checklist.
2. The permit application does not have values for the electrical work shown on the plans. Provide an additional certificate of value form uploaded into the documents folder showing the value of work for all trades.
|
Application received | | | 1/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 21 2019 11:37AM
|