Telephone call | | | 12/5/2019 | | DONE |
|
|
|
called GC spoke with Elva about the value that was submitted on the Plumbing. I informed her that there is no plumbing permit to this project, she was going to contact the plumbing company "Plumbing Solutions" and call back with information.
|
Third Notice | | 8/10/2019 | 9/20/2019 | | DONE |
|
|
|
mailed 9-23-19
|
Second Notice | | 7/20/2019 | 8/5/2019 | | DONE |
|
|
|
mailed 8-5-19
|
First Notice | | 7/5/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
BLD-Final | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. OK for perm occ.
|
FIRE-Final Inspection | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####
|
Permanent Occupancy | | | 6/25/2019 | | DONE |
|
|
|
|
BLD-Final | 6/12/2019 | 6/13/2019 | 6/13/2019 | P | PART |
Mike Jordan
|
|
|
David Phone #: ###-####**Originallly schedule for AM change to PM**. Ok for perm occ. only. Needs other trades to sign perm and need to inspect racking system once permit has been issued.
|
FIRE-Final Inspection | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | PART |
Jim Page
|
|
|
Previously noted items have been corrected, fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers will be placed in discussed location. TCO is authorized contingent on the racking permit (BLD19-02023) getting inspected and passed. After racking permit is finaled then a final life fire safety inspection will be required to finalize inspection process for life safety.
David Phone #: ###-####
|
BLD-Final | 6/11/2019 | 6/12/2019 | 6/12/2019 | A | NR |
Mike Jordan
|
|
|
David Phone #: ###-####
|
FIRE-Final Inspection | 6/11/2019 | 6/11/2019 | 6/11/2019 | P | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to pass when the hardware for door 113 is addressed and the transfer grill is installed for the smoke evac system from the Mall space as per the approved plans. Still need racking permit inspected. I'm ok for product to be brought into the store but the racks can not be used until the racking permit is approved.
David Phone #: ###-####
|
BLD-Final | 6/6/2019 | 6/10/2019 | 6/10/2019 | P | NR |
Mike Jordan
|
|
|
David Phone #: ###-####
|
FIRE-Final Inspection | 6/6/2019 | 6/10/2019 | 6/10/2019 | A | FAIL |
Troy Cobbley
|
|
|
The only item ready for testing/inspection was the smoke evac system which functioned correctly.
David Phone #: ###-####
|
BLD-Framing/Rough-in | 5/29/2019 | 5/30/2019 | 5/30/2019 | P | PASS |
Mike Jordan
|
|
|
David Phone #: ###-####. Interior steel stud framed walls and hardlids for restrooms ok.
|
BLD-Framing/Rough-in | 5/7/2019 | 5/8/2019 | 5/8/2019 | A | PASS |
Mike Jordan
|
|
|
David Phone #: ###-####
|
BLD-Framing/Rough-in | 5/3/2019 | 5/6/2019 | 5/6/2019 | A | PASS |
Mike Jordan
|
|
|
David Phone #: ###-####. Interior steel stud framed walls only ok.
|
BLD-Framing/Rough-in | 4/23/2019 | 4/24/2019 | 4/24/2019 | A | PASS |
Mike Jordan
|
|
|
David Phone #: ###-####. INterior steel stud furred wall for panels.
|
BLD-Framing/Rough-in | 4/16/2019 | 4/16/2019 | 4/16/2019 | P | PASS |
Mike Jordan
|
|
|
Taylor- demising wall inspection Phone #: ###-####. Interior steel stud framed demissing wall only ok to cover.
|
BLD-Framing/Rough-in | 4/15/2019 | 4/15/2019 | 4/16/2019 | P | FAIL |
Mike Jordan
|
|
|
framing insp. just for the demising wall // Taylor Phone #: ###-####. No city approved plans on site.
|
Print Occupancy Form | | | 4/12/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/12/2019 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 1/31/2019 | 1/31/2019 | 3/15/2019 | | PASS |
Joe Bruce
|
|
|
03/15 (1st Resub) 02/12 (L2) Hollister ePlan
|
Routing - PLAN CHECK | 3/11/2019 | | 3/15/2019 | | PASS |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/15/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/15/2019 | | DONE |
|
|
|
ALL MET-
NEED
GC FORM
REVISED VALUE
|
Routing Off Site - STRUCTURAL | 3/11/2019 | | 3/14/2019 | | PASS |
Joe Bruce
|
|
|
ahj
|
Plan resubmittals received | | | 3/11/2019 | | DONE |
Joe Bruce
|
|
|
Received resubmittal items. **JHB**
|
Routing - Design Review | 3/11/2019 | | 3/11/2019 | | PASS |
Katelyn Menuge
|
|
|
Zoning Certificate competed
|
Route to Impact Fee Review | 2/12/2019 | 2/15/2019 | 2/14/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - Design Review | 2/12/2019 | | 2/12/2019 | | FAIL |
Katelyn Menuge
|
|
|
New RTUs require a Zoning Certificate #123 prior to building permit issuance. Please submit this application.
|
1st review completed | | | 2/12/2019 | | FAIL |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 1/31/2019 | | 2/12/2019 | | FAIL |
Joe Bruce
|
|
|
|
Routing - FIRE | 1/31/2019 | 1/31/2019 | 2/8/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Fire 02.08.2019.pdf.
|
Routing Off Site - STRUCTURAL | 1/31/2019 | | 2/8/2019 | | FAIL |
Joe Bruce
|
|
|
ahj
|
Routing - MECHANICAL | 1/31/2019 | | 2/7/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 1/31/2019 | | 2/5/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 1/31/2019 | | 2/1/2019 | | PASS |
Laura Hunter
|
|
|
Added space number 2091
|
Routing - PUBLIC WORKS | 1/31/2019 | | 2/1/2019 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 1/30/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 1/29/2019 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
• The uploaded form 310 is incomplete, fill out 310 completely the cover sheet (permit #, address, inspection firm, design professional info, owner info, owner signature or design professional signature) approved inspection firms can be found at https://pds.cityofboise.org/media/173900/approved-special-inspection-firms-list-6-14-16.pdf
|
Intake Approval | | | 1/25/2019 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
• Provide a completed Form #310 – Statement of Special Inspections stamped, signed and dated by an Idaho design engineer (for welding of the joist support reinforcement) the form 310 can be found at https://pds.cityofboise.org/media/104147/final310_special_inspections.pdf
• Provide evidence the existing rooftop mechanical equipment weight is the same or more in weight than the new rooftop equipment, if the new mechanical rooftop equipment is more in weight provide engineering calculations that are stamped, signed and dated by an Idaho licensed engineer.
|
Application received | | | 1/22/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 22 2019 12:19PM
|