First Notice | | 6/16/2019 | 6/26/2019 | | DONE |
|
|
|
This permit finaled on the web by Michael McHargue
|
Permanent Occupancy | | | 6/6/2019 | | DONE |
|
|
|
|
BLD-Final | 6/4/2019 | 6/5/2019 | 6/5/2019 | A | PASS |
Mike Jordan
|
|
|
Plumbing inspector signed off plumbing final. Ready to final. Phone #: ###-#### Inspection requested via web by Michael McHargue. OK for perm occ. Plumbing has signed perm.
|
BLD-Final | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | PART |
Brandon Shaw
|
|
|
OK for temp CofO... Pending back flow cert. see PLM19-00890... No other issues...
|
FIRE-Final Inspection | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Adam Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 5/31/2019 | | |
|
|
|
per notes of Mike Jordan - 5/28/2019
|
BLD-Final | 5/28/2019 | 5/28/2019 | 5/28/2019 | A | PASS |
Mike Jordan
|
|
|
(This activity was added in error so we have changed the case status back to Issued.)
|
BLD-Conference | 5/28/2019 | 5/28/2019 | 5/28/2019 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Final | 5/23/2019 | 5/23/2019 | 5/23/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Adam Joslin. All issues resolved. Ok for perm occ.
|
BLD-Ceiling Grid Inspection | 5/15/2019 | 5/15/2019 | 5/15/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Adam Joslin
|
BLD-Ceiling Grid Inspection | 5/14/2019 | 5/15/2019 | 5/15/2019 | A | FAIL |
Mike Jordan
|
|
|
Fire Sprinkler Inspected scheduled for AM - likely to occur early morning. Ceiling Grid Inspection to follow - late morning if possible. Phone #: ###-#### Inspection requested via web by Adam Joslin. Remove all tile for inspection.
|
BLD-Ceiling Grid Inspection | 5/13/2019 | 5/14/2019 | 5/14/2019 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Adam Joslin. Needs fire sprinkler rough in first.
|
BLD-Energy code compliance | 4/8/2019 | 4/10/2019 | 4/10/2019 | A | PASS |
Mike Jordan
|
|
|
Adam Phone #: ###-####
|
BLD-Framing/Rough-in | 4/5/2019 | 4/8/2019 | 4/8/2019 | A | PASS |
Mike Jordan
|
|
|
Adam-late am if possible Phone #: ###-####. Interior wood framed walls ok.
|
CHANGE STATUS TO (ISS) | | | 3/26/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/26/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/22/2019 | | DONE |
|
|
|
plan mod so don't re issue
|
Plan assigned to (M_H) | 3/13/2019 | | 3/22/2019 | | DONE |
Michael Hanson
|
|
|
03/19 Plan Mod Prusik Construction T.I.ePlan
|
Routing - PLAN CHECK | 3/19/2019 | | 3/22/2019 | | PASS |
Michael Hanson
|
|
|
1 hour plan mod fee
|
Routing - PLUMBING | 3/19/2019 | | 3/20/2019 | | PASS |
Dan Ediger
|
|
|
Per plans and ISPC
|
Plan Reviewer's activity | | | 3/18/2019 | | DONE |
Javier Guzman
|
|
|
Failed preescreen for Michael as he was out and prescreen became due
Plan sheet A1.00 and A10.0 required to be stamped by the Idaho licensed architect
|
Plan Modification Accepted | | | 3/13/2019 | | DONE |
|
|
|
plan modification for relocation of the mop sink. Eplan work flow started.
|
Issue PAID IN FULL permit | | | 3/7/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/7/2019 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 2/20/2019 | | 3/1/2019 | | DONE |
Michael Hanson
|
|
|
02/22 #520 L3 ePlan. 1st review completed - Accessibility and IECC corrections required.
|
Routing - PLAN CHECK | 2/21/2019 | | 3/1/2019 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/1/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 3/1/2019 | | DONE |
|
|
|
all met-NEED
GC FORM
REVISED VALUE
MET
ACHD
3-5-19 emailed Prisk Const the fees due
|
Route to Impact Fee Review | 2/21/2019 | 2/24/2019 | 2/22/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 1/30/2019 | 1/30/2019 | 2/21/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Fire Code review 02.21.2019.pdf uploaded and complete.
|
1st review completed | | | 2/21/2019 | | FAIL |
Michael Hanson
|
|
|
Accessibility and IECC corrections required. See changemarks for additional information.
|
Routing - PLAN CHECK | 1/30/2019 | | 2/21/2019 | | FAIL |
Michael Hanson
|
|
|
Accessibility and IECC corrections required. See changemarks for additional information.
|
Plan assigned to (JG) | 1/30/2019 | 1/30/2019 | 2/20/2019 | | DEFR |
Javier Guzman
|
|
|
2/22 L3 Prisik Construction ePlan
|
Routing - MECHANICAL | 1/30/2019 | | 2/5/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 1/30/2019 | | 1/31/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PLANNING | 1/30/2019 | | 1/31/2019 | | PASS |
Nicolette Womack
|
|
|
Exterior sign is not approved. Required to submit a separate sign permit in accordance with the Master Sign Program.
|
Routing - Addressing | 1/30/2019 | | 1/30/2019 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 1/30/2019 | | 1/30/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 1/30/2019 | | 1/30/2019 | | PASS |
Michael Zawacki
|
|
|
TI, no ESC needed.
|
Routing - Design Review | 1/30/2019 | | 1/30/2019 | | PASS |
KayCee Babb
|
|
|
Per CZC19-00010.
|
Intake Approval | | | 1/28/2019 | | PASS |
|
|
|
|
Application received | | | 1/24/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 24 2019 9:42AM
|