BLD-Final | 7/24/2019 | 7/26/2019 | 7/26/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 7/26/2019 | 7/26/2019 | 7/26/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Blower Door Test Results | 7/24/2019 | 7/26/2019 | 7/26/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall 4.7
|
BLD-Energy code compliance | 5/17/2019 | 5/22/2019 | 5/22/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 5/16/2019 | 5/20/2019 | 5/20/2019 | A | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall ok to insulate but c/n on site
|
BLD-Wall Bracing | 5/2/2019 | 5/2/2019 | 5/2/2019 | P | PASS |
Brandon Shaw
|
|
|
Rudy Phone #: ###-####
|
BLD-Foundation | 3/28/2019 | 3/29/2019 | 3/29/2019 | A | PASS |
Brandon Shaw
|
|
|
No change in location, footing and foundation are ok to pour, with no new Geo soil subgrade, per phone call with Melissa Jannusch
|
BLD-Footing | 3/26/2019 | 3/27/2019 | 3/27/2019 | A | PEND |
Dave Hannah
|
|
|
Ryan Phone #: ###-#### ok after new geo tech is aproved
|
BLD-Footing | 3/25/2019 | 3/26/2019 | 3/26/2019 | A | FAIL |
Dave Hannah
|
|
|
Ryan Phone #: ###-#### needs a new geo tec on soil
|
BLD-Foundation | 3/1/2019 | 3/4/2019 | 3/4/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Conference | 2/22/2019 | 2/22/2019 | 2/22/2019 | P | PASS |
Brandon Shaw
|
|
|
Footing... Work in progress...
|
PubWorks Subgrade Approval | 2/20/2019 | 2/20/2019 | 2/20/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 2/8/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 1/30/2019 | 1/30/2019 | 2/8/2019 | | DONE |
Rob Patrick
|
|
|
02/11 sfd L1 ePlan...2-6 1st done Failed; Need Beam Size
|
Issue PAID IN FULL permit | | | 2/8/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/8/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/8/2019 | | 2/8/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/8/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 2/8/2019 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 1/30/2019 | | 2/6/2019 | | FAIL |
Rob Patrick
|
|
|
Need Beam Size
|
1st review completed | | | 2/6/2019 | | FAIL |
Rob Patrick
|
|
|
|
Routing - MECHANICAL | 1/30/2019 | | 2/6/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 1/30/2019 | 2/2/2019 | 1/31/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (BJM) | 1/30/2019 | 1/30/2019 | 1/30/2019 | | DEFR |
Brian McGowan
|
|
|
02/11 sfd L1 ePlan
|
Routing - FIRE | 1/30/2019 | 1/30/2019 | 1/30/2019 | | PASS |
Lee G Meredith
|
|
|
No sprinklers requried.
|
Routing - PLANNING | 1/30/2019 | | 1/30/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 1/30/2019 | | 1/30/2019 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 1/30/2019 | | 1/30/2019 | | PASS |
Angela Hardy
|
|
|
|
Application received | | | 1/29/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 29 2019 7:05AM
|
Plans ACCEPTED BY PLAN TECH | | | 1/29/2019 | | DONE |
|
|
|
|
Intake Approval | | | 1/29/2019 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 1/29/2019 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/29/2019 | | DONE |
|
|
|
|