Print Statement | | | 7/23/2019 | | DONE |
|
|
|
|
Print Statement | | | 7/23/2019 | | DONE |
|
|
|
|
First Notice | | 5/20/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
BLD-Final | 5/8/2019 | 5/10/2019 | 5/10/2019 | A | PASS |
Mike Jordan
|
|
|
Hello Mike can you give me a heads up phone call 20 minutes prior to inspection? Phone #: ###-#### Inspection requested via web by Jim Carriveau. OK for perm occ.
|
FIRE-Final Inspection | 5/8/2019 | 5/10/2019 | 5/10/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Permanent Occupancy | | | 5/10/2019 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 5/2/2019 | 5/3/2019 | 5/3/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Nate Carriveau
|
Print Occupancy Form | | | 5/2/2019 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 4/25/2019 | | DONE |
|
|
|
04.25.2019-Recieved HMIS from Rick Bagley and cut sheets. Under MAQ. Attached HMIS in Tidemark.
|
Telephone call | | | 4/24/2019 | | DONE |
|
|
|
04.15.2019 Recieved email from Romeo regarding HMIS needed for storage in warehouse. Call has been made to Rick with Wurth Luis. 04/15-Said he would get a HMIS over. Called 4/18-was waiting on someone in SLC for list. Left message 04.23.2019. HMIS will be needed before fire final can be signed off.
|
BLD-Energy code compliance | 4/11/2019 | 4/11/2019 | 4/11/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Nate Carriveau
|
BLD-Framing/Rough-in | 4/4/2019 | 4/8/2019 | 4/8/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Nate Carriveau. Interior steel stud framed walls and hardkid ok.
|
Issue PAID IN FULL permit | | | 3/13/2019 | | DONE |
|
|
|
emailed jnorton@jwci.com.COM to sign the permit
|
Print Occupancy Form | | | 3/13/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 2/8/2019 | 2/8/2019 | 3/8/2019 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 2/19 L2 Wurth Louis ePlan, pend fire
|
Plan Reviewer's activity | | | 3/8/2019 | | DONE |
Brian McGowan
|
|
|
I am reviewing the Plumbing fixture requirements for Javier since he is out sick.
|
Routing - PLAN CHECK | 3/8/2019 | | 3/8/2019 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/8/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 3/8/2019 | | DONE |
|
|
|
MET RYAN@LARSONARCHITECTS.BIZ
Need
GC form
Revised Value
|
Route to Impact Fee Review | 2/21/2019 | 2/24/2019 | 2/21/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 2/8/2019 | 2/8/2019 | 2/21/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Fire Review 02.21.2019
|
1st review completed | | | 2/21/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 2/8/2019 | | 2/15/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 2/8/2019 | | 2/13/2019 | | PASS |
Troy James
|
|
|
|
Routing PW Environmental | 2/8/2019 | | 2/13/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLUMBING | 2/8/2019 | | 2/8/2019 | | PASS |
Daryl Spivey
|
|
|
Per p[lan and ISPC.
|
Routing - Addressing | 2/8/2019 | | 2/8/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/8/2019 | | 2/8/2019 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 2/7/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 2/4/2019 | | FAIL |
Brian McGowan
|
|
|
Please remove the PRELIMINARY note from the Architect's stamp and signature on Sheets 0, A-1, A-2 and A-3.
|
Application received | | | 1/29/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 29 2019 8:37AM
|
Intake Approval | | | 1/29/2019 | | FAIL |
Brian McGowan
|
|
|
Sheet M-1 has been crashing our ePlan on my end. Would you please resubmit that drawing using the exact same name in order to version over the sheet that is causing issues.
I will be able to finish the prescreen then.
Thank you,
Brian McGowan
|