Temporary Occupancy | 7/10/2020 | 10/8/2020 | 7/10/2020 | | DONE |
Gemma Flores
|
|
|
|
Zoning Approval | 7/10/2020 | 7/10/2020 | 7/10/2020 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Final | 7/8/2020 | 7/9/2020 | 7/9/2020 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by chad stradley. Per Jim Storey - TCO only - OK for Perm with ELE and Zoning Final
|
FIRE-Final Inspection | 7/8/2020 | 7/9/2020 | 7/9/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed for building 5. Phone #: ###-#### Inspection requested via web by chad stradley
|
Telephone call | | | 6/12/2020 | | DONE |
|
|
|
per Joe Bruce: no MEC or PLM signature required. See DOCs
|
BLD-Framing/Rough-in | 6/2/2020 | 6/3/2020 | 6/3/2020 | P | PASS |
Jim Storey
|
|
|
Fire barrier wall sheet rock Inspection. Phone #: ###-#### Inspection requested via web by chad stradley
|
PubWorks Occupancy Approval | 5/27/2020 | 5/27/2020 | 5/27/2020 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Framing/Rough-in | 5/18/2020 | 5/19/2020 | 5/19/2020 | P | PASS |
Jim Storey
|
|
|
for cover inspection. Phone #: ###-#### Inspection requested via web by chad stradley
|
BLD-Aging Inspection | 5/1/2020 | 5/1/2020 | 5/1/2020 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Footing | 12/16/2019 | 12/19/2019 | 12/19/2019 | P | PART |
Tell Riley
|
|
|
They will be pouring at 2 pm. Strata will be on site at 145 PM for testing Phone #: ###-#### Inspection requested via web by chad stradley//ok pend specials//cleaning footings to meet frost depth while onsite//blankets onsite//
|
BLD-Footing | 12/16/2019 | 12/18/2019 | 12/16/2019 | P | CANC |
Jim Storey
|
|
|
They are looking to pour footer at 2PM. Strata will be on site at 245PM. Thank you. Phone #: ###-#### >> Inspection requested via web by chad stradley Inspection cancelled from web by: chad stradley
|
Change Expiration Date Only | | | 7/17/2019 | | DONE |
|
|
|
permit reissued by mistake on 7/16/19
|
Print Occupancy Form | | | 7/16/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/16/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/15/2019 | | DONE |
|
|
|
DO NOT REISSUE - PLAN MOD
|
Plan assigned to (JHB) | 6/13/2019 | 6/13/2019 | 7/12/2019 | | PASS |
Joe Bruce
|
|
|
(plan mod) Falcon One, Bldg 2B
|
Routing Off Site - STRUCTURAL | 7/11/2019 | | 7/12/2019 | | PASS |
Joe Bruce
|
|
|
|
Plan resubmittals received | | | 7/11/2019 | | DONE |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 7/8/2019 | | DONE |
Joe Bruce
|
|
|
Emailed structural comments to architect.
|
Routing - PLAN CHECK | 6/21/2019 | | 7/3/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 6/21/2019 | | 7/3/2019 | | FAIL |
Joe Bruce
|
|
|
|
Plan Modification Accepted | | | 6/13/2019 | | DONE |
|
|
|
Plan mod accepted in e plan-changing footing & framing design -assigned to Joe B
|
BLD-Foundation | 5/3/2019 | 5/6/2019 | 5/6/2019 | A | PASS |
Jim Storey
|
|
|
damp proofing on building retaining walls Phone #: ###-#### Inspection requested via web by chad stradley
|
CHANGE ISSUED DATE | | | 2/13/2019 | | DONE |
|
|
|
permit reissued by mistake on 7/16/19
|
Permit Ready to Issue | | | 2/13/2019 | | DONE |
|
|
|
Need
Revised Value- (for each building)
(DO NOT ISSUE WITHOUT ALL PERMITS, BLD18-03877, BLD18-04070 TO BLD18-04076, BLD19-00314 TO BLD19-000317)
|
Issue PAID IN FULL permit | | | 2/13/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/13/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/13/2019 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 11/14/2018 | 11/14/2018 | 2/11/2019 | | PASS |
Joe Bruce
|
|
|
(3rd Rev Comp) 12/07 - (502) Falcon One Storage Condos Bldg 2(B)
|
Routing Off Site - STRUCTURAL | 2/8/2019 | | 2/11/2019 | | PASS |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/8/2019 | | DONE |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 2/6/2019 | | FAIL |
Joe Bruce
|
|
|
Structural resubmittal required.
|
Routing Off Site - STRUCTURAL | 1/30/2019 | | 2/6/2019 | | FAIL |
Joe Bruce
|
|
|
See structural comment in the Agency Comments folder for remaining issue to address. Provide a complete written response outlining the analysis method you are taking responsibility for.
|
Routing PW Sewer Design | 1/30/2019 | | 1/31/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing - FIRE | 1/17/2019 | 1/17/2019 | 1/30/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Plan resubmittals requested | | | 1/30/2019 | | FAIL |
Joe Bruce
|
|
|
PW Sewer and Structutral have additional comments. **JHB**
|
Plan resubmittals received | | | 1/30/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 1/17/2019 | | 1/28/2019 | | FAIL |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 1/17/2019 | | 1/28/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing PW Sewer Design | 1/17/2019 | | 1/23/2019 | | FAIL |
DeAnn Brown
|
|
|
|
Routing - Design Review | 1/17/2019 | | 1/18/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - FIRE | 11/14/2018 | 11/14/2018 | 12/12/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 12/12/2018 | | FAIL |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 11/14/2018 | | 12/7/2018 | | FAIL |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 11/14/2018 | | 11/29/2018 | | FAIL |
Joe Bruce
|
|
|
|
Routing - MECHANICAL | 11/14/2018 | | 11/26/2018 | | PASS |
Troy James
|
|
|
|
Routing PW Drainage | 11/14/2018 | | 11/20/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLUMBING | 11/14/2018 | | 11/19/2018 | | PASS |
Dan Ediger
|
|
|
|
Routing - Design Review | 11/14/2018 | | 11/16/2018 | | FAIL |
Katelyn Menuge
|
|
|
|
Routing PW Street Lights | 11/14/2018 | | 11/15/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 11/14/2018 | | 11/15/2018 | | FAIL |
DeAnn Brown
|
|
|
|
Routing - PLANNING | 11/14/2018 | | 11/15/2018 | | PASS |
Leon Letson
|
|
|
|
Routing PW Solid Waste | 11/14/2018 | | 11/14/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Addressing | 11/14/2018 | | 11/14/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/14/2018 | | 11/14/2018 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 11/14/2018 | | 11/14/2018 | | CANC |
Andy J. Long
|
|
|
|
Intake Approval | | | 11/7/2018 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 10/25/2018 | | FAIL |
Javier Guzman
|
|
|
|
Application received | | 10/22/2018 | 10/22/2018 | | DONE |
|
|
|
|