Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD19-00320
StatusFinaled
Name GENERAL DYNAMICS INFORMATION TECHNO
Site Address 682 E BOISE AVE
Project Name822732 Boise_Eastgate - AT&T
Customer Number 
ePlanReviewYes
Description
(AT&T) Scope of work as per Title Sheet - AT&T proposes to remove (3) antennas, and (6) RRH’s; install (3) antennas, (1) squid, (9) RRH’s, (3) mounts, (2) DC cables, and (1) fiber cable on existing tower. AT&T also proposes to replace (1) power plant and (1) battery rack and battery system within existing compound. All work to be done as per plans, documents, engineering and local codes. No change in the height of the tower is proposed. ***BJM***
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  7/31/2019 DONE
emailed dgibson@tkkcommunications.com the case summary for his records
BLD-Final7/29/20197/29/20197/29/2019PDONE
DetailsBrandon Shaw
Dillon Phone #: ###-####
DOC - Permit Finaled7/29/20197/29/20197/29/2019PPASS
DetailsBrandon Shaw
Issue PAID IN FULL permit  3/27/2019 DONE
Inspection Record Card- Bld  3/27/2019 DONE
Plan assigned to (BJM)1/31/20191/31/20193/12/2019 DONE
DetailsBrian McGowan
1st review complete 02/14 L2 AT&T Antenna ePlan- Must Pass FIRE
Routing - PLAN CHECK3/12/2019 3/12/2019 PASS
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  3/12/2019 DONE
DetailsBrian McGowan
Permit Ready to Issue  3/12/2019 DONE
ALL MET email: sarah.baird@crowncastle.com

NEED GC
NEED revised cert of val
Routing - FIRE3/5/20193/5/20193/8/2019 PASS
DetailsMark Scharfen
IFC Final review 03.08.2019.pdf
Route to Impact Fee Review2/14/20192/17/20192/15/2019 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLAN CHECK1/31/2019 2/14/2019 FAIL
DetailsBrian McGowan
Must pass FIRE
1st review completed  2/14/2019 FAIL
DetailsBrian McGowan
Routing - FIRE1/31/20191/31/20192/12/2019 FAIL
DetailsMark Scharfen
IFC Fire Code Review 02.12.2019. Emailed architecht.
Intake Approval  1/31/2019 PASS
DetailsJavier Guzman
Routing - PLANNING1/31/2019 1/31/2019 PASS
DetailsSue Cummings
See CAA19-00017
Application received  1/29/2019 DONE
Application submitted via PDS Online on Jan 29 2019 1:50PM
First Notice7/29/20197/29/2019   
DetailsBrandon Shaw