BLD-Final | 2/3/2020 | 2/3/2020 | 2/3/2020 | P | PASS |
Tony Young
|
|
|
Call to meet // Manny Phone #: ###-####
|
DOC - Permit Finaled | 2/3/2020 | 2/3/2020 | 2/3/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 12/10/2019 | 12/10/2019 | 12/10/2019 | P | FAIL |
Dave Hannah
|
|
|
Manny Phone #: ###-#### hand rail and guard rails
|
Zoning Approval | 12/5/2019 | 12/5/2019 | 12/5/2019 | | DONE |
Ted Vanegas
|
|
|
|
BLD-Conference | 10/29/2019 | 10/30/2019 | 10/30/2019 | A | PART |
Tony Young
|
|
|
Many Phone #: ###-####,, hand rail ?s,, ok,, resurfaced existing stairs
|
BLD-Energy code compliance | 7/29/2019 | 7/29/2019 | 7/29/2019 | P | PASS |
Tony Young
|
|
|
Manny Phone #: ###-####
|
BLD-Framing/Rough-in | 7/23/2019 | 7/23/2019 | 7/23/2019 | P | PASS |
Jim Storey
|
|
|
MANNY c/n made ok
|
Routing Walk-In (BLD) | 7/23/2019 | 7/23/2019 | 7/23/2019 | P | FAIL |
Michael Hanson
|
|
|
Questions about not doing an ADU and maybe doing a plan mod for basement. Informed them Josh is gone. Informed applicant that I would need to talk with my supervisor for this. Built as an ADU but do not want to finish as ADU. Discussed with Carl Madsen they would need to reapply with zoning and remove the fixtures that make it an ADU.
|
BLD-Framing/Rough-in | 7/19/2019 | 7/22/2019 | 7/22/2019 | A | FAIL |
Dave Hannah
|
|
|
Jeff Phone #: ###-#### c/n on site fire blocking and pluming fixes on floor joist
|
BLD-Energy code compliance | 5/29/2019 | 5/29/2019 | 5/29/2019 | P | PART |
Tony Young
|
|
|
Manny Phone #: ###-####,, garage ok
|
BLD-Framing/Rough-in | 5/24/2019 | 5/28/2019 | 5/28/2019 | A | PART |
Tony Young
|
|
|
Many Phone #: ###-####,, garage ok to insulate,, needs tempered windows by stairs by final.. (they are installed on other wall)
|
BLD-Conference | 5/21/2019 | 5/21/2019 | 5/21/2019 | P | DONE |
Dave Hannah
|
|
|
Manny Phone #: ###-#### needs engineer to ok change to ftg size
|
BLD-Wall Bracing | 4/19/2019 | 4/19/2019 | 4/19/2019 | P | PART |
Jim Sly
|
|
|
Manny Phone #: ###-#### Exterior nailing only......OK. Installing hold downs........
|
BLD-Footing | 3/7/2019 | 3/8/2019 | 3/8/2019 | A | PART |
Tony Young
|
|
|
J.R requesting footing inspection for ESC19-00138. Please call for acess Phone #: ###-####,, garage footing ok after cleaning out loose material
|
Issue PAID IN FULL permit | | | 2/28/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 2/27/2019 | | |
|
|
|
|
Telephone call | | | 2/27/2019 | | DONE |
|
|
|
called Jeff to let know permit is ready and how much is owed
|
Case Summary (BLD) | | | 2/27/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/27/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/27/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 2/4/2019 | 2/4/2019 | 2/26/2019 | | PASS |
Josh Bogle
|
|
|
2/8 remodel, paper - 1st done - ADU under separate permit
|
Plan Reviewer's activity | | | 2/26/2019 | | DONE |
Josh Bogle
|
|
|
Troy James OK'd go ahead with no Mech sign-off
|
Inspection Record Card- Bld | | | 2/26/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 2/26/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/26/2019 | | DONE |
Josh Bogle
|
|
|
OK for release without Mech ok by Troy James
|
Routing Walk-In (BLD) | 2/11/2019 | 2/11/2019 | 2/11/2019 | A | PASS |
Josh Bogle
|
|
|
resubmittal of additional plans - page S0.00 - Plan Review OK, waiting on revised ACCA report
|
Routing - PLAN CHECK | 2/4/2019 | | 2/8/2019 | | FAIL |
Josh Bogle
|
|
|
missing garage hear info
|
1st review completed | | | 2/8/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing - MECHANICAL | 2/4/2019 | | 2/5/2019 | | FAIL |
Troy James
|
|
|
Emailed corrections to TML
|
Routing Walk-In (Zoning) | 2/4/2019 | 2/4/2019 | 2/4/2019 | A | PASS |
Ted Vanegas
|
|
|
|
Routing Walk-In (BLD) | 2/4/2019 | 2/4/2019 | 2/4/2019 | A | PASS |
Josh Bogle
|
|
|
took in as a level two, routed to Mech
|
Application received | | 2/4/2019 | | | |
|
|
|
|