First Notice | | 5/24/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
BLD-Final | 5/13/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Mike Jordan
|
|
|
Rick Phone #: ###-####
|
FIRE-Final Inspection | 5/13/2019 | 5/14/2019 | 5/14/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Rick Phone #: ###-####
|
Permanent Occupancy | | | 5/14/2019 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 5/7/2019 | 5/8/2019 | 5/8/2019 | A | PASS |
Mike Jordan
|
|
|
Rick Phone #: ###-####. Inteior steel stud framed walls and soffit ok. Pending electrical and plumbing rough in inspections.
|
Issue PAID IN FULL permit | | | 3/19/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/19/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/19/2019 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 2/20/2019 | 2/20/2019 | 3/18/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 03/07/19 (L3 - 15 days) (ePlan - 36 sheets) Starbucks (routed back to applicant)
|
Plan resubmittals received | | | 3/18/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/18/2019 | | 3/18/2019 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/18/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/18/2019 | | DONE |
|
|
|
MET AMANDA.H@BRAZOSCONTRACTORS.COM
NEED
GC FORM
REVISED VALUE
|
Route to Impact Fee Review | 3/14/2019 | 3/17/2019 | 3/15/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 2/20/2019 | 2/20/2019 | 3/14/2019 | | PASS |
Mark Scharfen
|
|
|
IFC final review 03.14.2019.pdf
|
1st review completed | | | 3/14/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 3/14/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/20/2019 | | 3/8/2019 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - Erosion and Sediment | 2/20/2019 | | 2/26/2019 | | PASS |
Michael Zawacki
|
|
|
Interior TI, no ESC review required.
|
Routing - MECHANICAL | 2/20/2019 | | 2/25/2019 | | PASS |
Chad Schwendiman
|
|
|
Existing mechanical system shown to remain with no changes.
|
Routing - PLUMBING | 2/20/2019 | | 2/20/2019 | | PASS |
Daryl Spivey
|
|
|
See redline remarks and install per ISPC.
|
Routing - PLANNING | 2/20/2019 | | 2/20/2019 | | PASS |
Susan Riggs
|
|
|
|
Routing - Addressing | 2/20/2019 | | 2/20/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/20/2019 | | 2/20/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 2/15/2019 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following:
1. #304 form missing - COMPLETED
2. #518 missing sheet locations of items.
3. CDHD approval letter or stamped review missing. - COMPLETED
4. Update G-0001 scope of work per our email.
5. Provide energy code compliance for lighting. - COMPLETED
|
Intake Approval | | | 2/15/2019 | | PASS |
|
|
|
|
Application received | | | 2/5/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 5 2019 10:26AM
|
Intake Approval | | | 2/5/2019 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following:
1. #304 form missing
2. #518 missing sheet locations of items.
3. CDHD approval letter or stamped review missing
4. Provide planning and zoning letters of approval.
5. Provide energy code compliance for lighting.
|