Description
(MICRON B #50) Install new HVAC Unit outside of the N/E corner of B50. Ductwork, piping and fire rated shaft constructed crossing stairwell. This is a scope of work with a certificate of completion to be issued upon completion and approval of the project. This building is fully fire sprinklered and alarmed. ANy alteration to the sprinkler system will require a separate permit and shall comply with NFPA 13 and 72 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/10/20207/13/20207/13/2020APASS
DetailsJim Storey
call 15 min before arrival. Meet B26 lobby Phone #: ###-#### Inspection requested via web by Daniel Cook
DOC - Permit Finaled7/13/20207/13/20207/13/2020PPASS
DetailsJim Storey
BLD-Framing/Rough-in6/10/20206/11/20206/11/2020APASS
DetailsJim Storey
call ahead 15 minutes. Meet B26 lobby. Phone #: ###-#### Inspection requested via web by Daniel Cook shaft linner and ch studes ok to cover.
BLD-Final4/16/20204/17/20204/17/2020ACANC
DetailsJim Storey
meet in B26 lobby. thanks Phone #: ###-#### Inspection requested via web by Daniel Cook remove exterior membrane and call for insp.
FIRE-Final Inspection4/15/20204/16/20204/16/2020ACANC
DetailsJim Page
please call 1/2 before arrival. Meet in B26 lobby thanks Phone #: ###-#### >> Inspection requested via web by Daniel Cook Inspection cancelled from web by: Daniel Cook
FIRE-Final Inspection3/26/20203/26/20203/26/2020APASS
DetailsJim Page
Fire sprinkler inspection is complete, no fire alarm modifications, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work is complete, signature card not available at time of inspection.
BLD-Framing/Rough-in2/12/20202/13/20202/13/2020ACANC
DetailsJim Storey
Please call 1/2 hour before arrival. Meet in B26 lobby. Thanks Phone #: ###-#### Inspection requested via web by Daniel Cook dan canc via phone call.
Issue PAID IN FULL permit  1/31/2020 DONE
Meeting  1/7/2020 DONE
sent an email to paul suggesting to turn in a request for an extension if this permit is not going to be picked up soon (155 days past date)
Meeting  12/2/2019 DONE
sent an email to paul suggesting to turn in a request for an extension if this permit is not going to be picked up soon
Plan assigned to (CDM)11/19/201911/19/201911/19/2019 PASS
DetailsCarl D Madsen
Micron B #50
Routing - PLAN CHECK11/19/2019 11/19/2019 PASS
DetailsCarl D Madsen
1st review completed  11/19/2019 DONE
PLANS/APPL TAKEN TO FRONT DESK  11/19/2019 DONE
Permit Ready to Issue  11/19/2019 DONE
Need
GC Form
Intake Approval  11/19/2019 PASS
Intake Approval  7/29/2019 FAIL
DetailsMichael Hanson
This permit has failed prescreen due to the following:
1. Missing 518 checklist
2. Missing 304 form
3. Missing planning and zoning approval letter
4. Construction drawings must be monochrome. Color prints are not allowed.
5. Show location of the new HVAC units
6. Provide U.L or G.A. assembly number and detail.
7. Provide City of Boise stamping area at bottom right of construction drawings.
Application received  2/5/2019 DONE
Application submitted via PDS Online on Feb 5 2019 3:35PM