Letter of compliance/Occupancy | | | 7/1/2019 | | DONE |
|
|
|
emailed to tiffani@idbearconstruction.com
|
BLD-Final | 6/26/2019 | 6/28/2019 | 6/28/2019 | A | PASS |
Mike Jordan
|
|
|
victor Phone #: ###-####
|
DOC - Permit Finaled | 6/28/2019 | 6/28/2019 | 6/28/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 6/14/2019 | 6/17/2019 | 6/18/2019 | A | NR |
Mike Jordan
|
|
|
Victor Phone #: ###-####. Drivewahy not completed.
|
BLD-Framing/Rough-in | 5/30/2019 | 5/31/2019 | 5/31/2019 | A | PASS |
Jim Storey
|
|
|
Kyle Phone #: ###-#### no branch wiring.
|
BLD-Framing/Rough-in | 5/28/2019 | 5/29/2019 | 5/29/2019 | A | PEND |
Mike Jordan
|
|
|
Victor Phone #: ###-####. Electrical work? If so, complete and have inspected.
|
BLD-Wall Bracing | 5/28/2019 | 5/29/2019 | 5/29/2019 | A | FAIL |
Mike Jordan
|
|
|
Victor Phone #: ###-####. Provide portal frame at garage door opening. Correction notice posted.
|
Plan assigned to (RDP) | 5/21/2019 | 5/21/2019 | 5/28/2019 | | DONE |
Rob Patrick
|
|
|
05/27 Foundation Walk-in L2 PAPER...05/23 Waiting for new plan from applicant
|
Routing - PLAN CHECK | 5/23/2019 | | 5/28/2019 | | PASS |
Rob Patrick
|
|
|
|
Routing - PLANNING | 5/23/2019 | | 5/28/2019 | | PASS |
Sue Cummings
|
|
|
REDLINED Please verify a 5 ft. setback on the side of the garage
|
Inspection Record Card- Bld | | | 5/28/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/28/2019 | | DONE |
|
|
|
Plan Mod approved
|
Telephone call | | | 5/28/2019 | | DONE |
|
|
|
Left Voicemail for Victor to inform him the plan mod has been approved and can be picked up.
|
CHANGE STATUS TO (ISS) | | | 5/28/2019 | | DONE |
|
|
|
plan mod
|
Plan resubmittals received | | | 5/23/2019 | | DONE |
|
|
|
Braced wall line calcs, sheet 2 and site plan stamped and taken to RDP
|
Plan Modification Accepted | | | 5/21/2019 | | DONE |
Rob Patrick
|
|
|
plan mod per customer and rob
|
BLD-Framing/Rough-in | 5/15/2019 | 5/17/2019 | 5/17/2019 | A | NR |
Mike Jordan
|
|
|
garage // Kyle Phone #: ###-####. Permit is for foundation only. It appears that a seperate permit is required for the garage. garage footing/foundation has been inspected and placed.
|
BLD-Foundation | 4/29/2019 | 4/29/2019 | 4/29/2019 | P | PASS |
Mike Jordan
|
|
|
Kile- have conrete at 2:30 please come by an hour before Phone #: ###-####
|
BLD-Footing | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | PART |
Mike Jordan
|
|
|
call when your on your way- Kyle Phone #: ###-####
|
BLD-Footing | 4/24/2019 | 4/25/2019 | 4/25/2019 | P | NR |
Mike Jordan
|
|
|
Kyle Phone #: ###-####
|
BLD-Final | 4/1/2019 | 4/2/2019 | 4/2/2019 | P | PASS |
Mike Jordan
|
|
|
stem wall // Kyle Phone #: ###-####
|
BLD-Footing | 3/20/2019 | 3/22/2019 | 3/22/2019 | A | PART |
Mike Jordan
|
|
|
pouring at 11 // Victor Phone #: ###-####
|
BLD-Foundation | 3/18/2019 | 3/19/2019 | 3/19/2019 | A | NR |
Mike Jordan
|
|
|
foundation for a mobile home, also detached garage // Victor Phone #: ###-####. No one on site, footings not yey excavated.
|
Issue PAID IN FULL permit | | | 3/12/2019 | | DONE |
|
|
|
|
Plan assigned to (RDP) | 2/7/2019 | 2/7/2019 | 2/25/2019 | | DONE |
Rob Patrick
|
|
|
02/20 sfd L1 PAPER (Foundation Only)...02/12 Failed per Planning
|
Routing - PLAN CHECK | 2/25/2019 | | 2/25/2019 | | PASS |
Rob Patrick
|
|
|
No ESC...No Energy
|
Case Summary (BLD) | | | 2/25/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/25/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 2/25/2019 | | DONE |
|
|
|
met-Need
MET-ACHD
|
Inspection Record Card- Bld | | | 2/25/2019 | | DONE |
|
|
|
|
Telephone call | | | 2/25/2019 | | DONE |
|
|
|
Left voicemail informing Victor that the permit is ready, what fees are due and that we need something from ACHD about impact fees.
|
Plan resubmittals received | | | 2/21/2019 | | DONE |
|
|
|
Resubmittal received new site plan-assigned to P&Z and Rob
|
Routing - PLANNING | 2/21/2019 | | 2/21/2019 | | PASS |
Sue Cummings
|
|
|
Site plan corrected 2/21/19
|
1st review completed | | | 2/12/2019 | | FAIL |
Rob Patrick
|
|
|
Incorrect site plan submitted per Planning
|
Routing - PLAN CHECK | | | 2/12/2019 | | FAIL |
Rob Patrick
|
|
|
Incorrect site plan submitted per Planning
|
Routing - PLANNING | | | 2/12/2019 | | FAIL |
|
|
|
The site plan, the GIS map and the subdiision plat are all different. They all need to match.
|
Route to Impact Fee Review | 2/7/2019 | 2/10/2019 | 2/8/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 2/7/2019 | | 2/8/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/7/2019 | | 2/8/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/7/2019 | | DONE |
|
|
|
|
Intake Approval | | | 2/7/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/7/2019 | | DONE |
|
|
|
|
Application received | | 2/7/2019 | | | |
|
|
|
|