Permit Information
Permit NumberBLD19-00411
StatusFinaled
Name VERTICAL CORP
Site Address 8050 W RIFLEMAN ST Unit: 100
Project NameBPA Health, Inc.
Customer Number 
ePlanReviewYes
Description
(BPA HEALTH, INC) Permit is for 7,354 s.f. office tenant improvement. Interior Demo Permit: BLD18-04408, Prior tenant was All Season Mental Health: BLD08-01770. Approval is contingent upon adhering to the approved plans on file. Work to include: new installation of interior non-bearing walls to create a Copy Room, Waiting Area and Hallway, removal of walls from Demo Permit to create Open Pffice and Customer Service Areas, remodel existing Bathroom to be a Locker Room with a ADA Code Compliant shower and separate Toilet Room, relocate fixtures, mechanical, and interior finishes in compliance with Ch. 8 of the 2015 IBC. This building is fully Fire Sprinklered with a Fire Alarm System. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **BJM**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 7/20/20197/24/2019 DONE
This permit finaled on the web by Todd Weltner
First Notice 6/24/20197/10/2019 DONE
mailed 7-11
BLD-Final6/14/20196/14/20196/14/2019PPASS
DetailsMike Jordan
Kent Phone #: ###-####. Ok for perm occ.
FIRE-Final Inspection6/13/20196/14/20196/14/2019APASS
DetailsTroy Cobbley
Life safety passed

Kent Phone #: ###-####
Permanent Occupancy  6/14/2019 DONE
BLD-Framing/Rough-in4/1/20194/2/20194/2/2019APASS
DetailsMike Jordan
Kent Phone #: ###-####. Interior steel stud framed walls ok.
Issue PAID IN FULL permit  3/22/2019 DONE
Inspection Record Card- Bld  3/22/2019 DONE
Print Occupancy Form  3/22/2019 DONE
Plan assigned to (BJM)2/21/20192/21/20193/21/2019 DONE
DetailsBrian McGowan
03/19 1st Review Complete 02/28 (L2) BPA Health, Inc - ePlan (@ FIRE)
Routing - MECHANICAL3/13/2019 3/21/2019 PASS
DetailsChad Schwendiman
PLANS/APPL TAKEN TO FRONT DESK  3/21/2019 DONE
DetailsBrian McGowan
Permit Ready to Issue  3/21/2019 DONE
MET
Need:
GC
Rev Val
Routing - PLAN CHECK3/13/2019 3/19/2019 PASS
DetailsBrian McGowan
Routing - FIRE3/13/20193/13/20193/18/2019 PASS
DetailsErika Akin
Attached comments to case
Routing - FIRE2/21/20192/21/20193/5/2019 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
1st review completed  3/5/2019 DONE
Routing - PLAN CHECK2/21/2019 2/27/2019 FAIL
DetailsBrian McGowan
Routing - Erosion and Sediment2/21/2019 2/26/2019 PASS
DetailsMichael Zawacki
TI, no esc plan required.
Routing - MECHANICAL2/21/2019 2/25/2019 FAIL
DetailsChad Schwendiman
Need to show means for protecting duct penetrations in fire walls
Routing - PLUMBING2/21/2019 2/21/2019 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - Addressing2/21/2019 2/21/2019 PASS
DetailsDoug Chausow
Ste 100
Routing - PUBLIC WORKS2/21/2019 2/21/2019 PASS
DetailsAngela Hardy
Routing - Design Review2/21/2019 2/21/2019 FAIL
DetailsKayCee Babb
Proposed project requires Design Review for all exterior alterations, including diesal generator and related site improvements. A Zoning Certificate approval is needed prior to Building permit approval.
Intake Approval  2/15/2019 PASS
DetailsBrian McGowan
Prescreen approved by Brian McGowan
Intake Approval  2/11/2019 FAIL
DetailsBrian McGowan
2/11/19 -Please provide a Key Plan for this prescreen to be approved.
Thank you,
Brian McGowan
Application received  2/8/2019 DONE
Application submitted via PDS Online on Feb 8 2019 11:10AM
Routing - Design Review3/13/2019   PASS
DetailsKayCee Babb
Diesal generator and fuel tank are not included in scope of project. No exterior alterations are approved through this permit. Any future exterior alterations will require Design Review approval prior to submittal of Building permits.