Second Notice | | 7/20/2019 | 7/24/2019 | | DONE |
|
|
|
This permit finaled on the web by Todd Weltner
|
First Notice | | 6/24/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
BLD-Final | 6/14/2019 | 6/14/2019 | 6/14/2019 | P | PASS |
Mike Jordan
|
|
|
Kent Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 6/13/2019 | 6/14/2019 | 6/14/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Kent Phone #: ###-####
|
Permanent Occupancy | | | 6/14/2019 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 4/1/2019 | 4/2/2019 | 4/2/2019 | A | PASS |
Mike Jordan
|
|
|
Kent Phone #: ###-####. Interior steel stud framed walls ok.
|
Issue PAID IN FULL permit | | | 3/22/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/22/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/22/2019 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 2/21/2019 | 2/21/2019 | 3/21/2019 | | DONE |
Brian McGowan
|
|
|
03/19 1st Review Complete 02/28 (L2) BPA Health, Inc - ePlan (@ FIRE)
|
Routing - MECHANICAL | 3/13/2019 | | 3/21/2019 | | PASS |
Chad Schwendiman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 3/21/2019 | | DONE |
|
|
|
MET
Need:
GC
Rev Val
|
Routing - PLAN CHECK | 3/13/2019 | | 3/19/2019 | | PASS |
Brian McGowan
|
|
|
|
Routing - FIRE | 3/13/2019 | 3/13/2019 | 3/18/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - FIRE | 2/21/2019 | 2/21/2019 | 3/5/2019 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
1st review completed | | | 3/5/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/21/2019 | | 2/27/2019 | | FAIL |
Brian McGowan
|
|
|
|
Routing - Erosion and Sediment | 2/21/2019 | | 2/26/2019 | | PASS |
Michael Zawacki
|
|
|
TI, no esc plan required.
|
Routing - MECHANICAL | 2/21/2019 | | 2/25/2019 | | FAIL |
Chad Schwendiman
|
|
|
Need to show means for protecting duct penetrations in fire walls
|
Routing - PLUMBING | 2/21/2019 | | 2/21/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 2/21/2019 | | 2/21/2019 | | PASS |
Doug Chausow
|
|
|
Ste 100
|
Routing - PUBLIC WORKS | 2/21/2019 | | 2/21/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Design Review | 2/21/2019 | | 2/21/2019 | | FAIL |
KayCee Babb
|
|
|
Proposed project requires Design Review for all exterior alterations, including diesal generator and related site improvements. A Zoning Certificate approval is needed prior to Building permit approval.
|
Intake Approval | | | 2/15/2019 | | PASS |
Brian McGowan
|
|
|
Prescreen approved by Brian McGowan
|
Intake Approval | | | 2/11/2019 | | FAIL |
Brian McGowan
|
|
|
2/11/19 -Please provide a Key Plan for this prescreen to be approved.
Thank you,
Brian McGowan
|
Application received | | | 2/8/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 8 2019 11:10AM
|
Routing - Design Review | 3/13/2019 | | | | PASS |
KayCee Babb
|
|
|
Diesal generator and fuel tank are not included in scope of project. No exterior alterations are approved through this permit. Any future exterior alterations will require Design Review approval prior to submittal of Building permits.
|