BLD-Final | 9/16/2019 | 9/16/2019 | 9/16/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Elaina Berti
|
DOC - Permit Finaled | 9/16/2019 | 9/16/2019 | 9/16/2019 | P | PASS |
Mike Jordan
|
|
|
All issues have been resolved.
|
BLD-Conference | 8/13/2019 | 8/13/2019 | 8/13/2019 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Elaina Berti. Provide code compliant handrails to basement and on xterior deck. Provide code compliant guards on deck.
|
BLD-Framing/Rough-in | 3/21/2019 | 3/21/2019 | 3/21/2019 | P | PASS |
Mike Jordan
|
|
|
Elaina Phone #: ###-####
|
BLD-Framing/Rough-in | 3/12/2019 | 3/12/2019 | 3/12/2019 | P | PART |
Mike Jordan
|
|
|
Elaine Phone #: ###-####. Complete airseal and all fireblocking.
|
BLD-Framing/Rough-in | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | NR |
Mike Jordan
|
|
|
Elaina Phone #: ###-####. Will get MEP permits and rough in inspections first.
|
Routing Walk-In (BLD) | 2/28/2019 | 2/28/2019 | 2/28/2019 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 2/28/2019 | | 2/28/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 2/28/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 2/28/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/28/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 2/28/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/28/2019 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 2/13/2019 | 2/13/2019 | 2/13/2019 | P | FAIL |
Josh Bogle
|
|
|
this project will need structural engineering
|
Routing Walk-In (Zoning) | 2/11/2019 | 2/11/2019 | 2/11/2019 | P | FAIL |
Sue Cummings
|
|
|
no site plan
|
Routing Walk-In (BLD) | 2/11/2019 | 2/11/2019 | 2/11/2019 | P | FAIL |
Josh Bogle
|
|
|
plans lack needed details
|
Routing - PLAN CHECK | 2/11/2019 | | 2/11/2019 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 2/11/2019 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 2/11/2019 | | | |
|
|
|
|