BLD-Final | 6/30/2020 | 6/30/2020 | 6/30/2020 | P | PASS |
Tell Riley
|
|
|
permit complete per scope of work//corrections made//header in egress window was not changed and is existing-no change in width per contractor//minor gyp board repairs will be completed in garage where cut for plumbing access-per contractor//
|
DOC - Permit Finaled | 6/30/2020 | 6/30/2020 | 6/30/2020 | P | PASS |
Tell Riley
|
|
|
|
BLD-Final | 6/29/2020 | 6/30/2020 | 6/30/2020 | A | CANC |
Tell Riley
|
|
|
Please give me 30 minutes or so notice so I can be there. We will be ready first thing in the morning. I''ve corrected the issues we reviewed on Friday. Thanks! Jay Phone #: ###-#### Inspection requested via web by Jay Bedsole//Jay is still working on corrections, rescheduled for PM//
|
BLD-Final | 6/25/2020 | 6/26/2020 | 6/26/2020 | P | FAIL |
Mike Jordan
|
|
|
Please give me a call 30 minutes ahead so that I can meet you on site for a walk through. Thank you. Jay Phone #: ###-#### Inspection requested via web by Jay Bedsole//CN issued//handrails need added and adjusted to meet code at stairway inside home//window near shower needs safety glazed//smok and smoke/co combos need to be interconnected--wireless interconnection allowed by code//adjust spring hinges on garage door//egress window needed in bedroom converted from den per plans and description//other window sizes were not changed//
|
BLD-Final | 6/16/2020 | 6/17/2020 | 6/17/2020 | P | CANC |
Tell Riley
|
|
|
Steve *screened* Phone #: ###-####//talked with Jay, will re-schedule, needs mechanical requirement removed from inspection requirements//will provide photos of the rough framing etc, as no rough in framing inspection was completed//
|
Routing Walk-In (BLD) | 2/12/2019 | 2/12/2019 | 2/12/2019 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 2/12/2019 | | 2/12/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 2/12/2019 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 2/12/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 2/12/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/12/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 2/12/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/12/2019 | | DONE |
|
|
|
|
Application received | | 2/12/2019 | | | |
|
|
|
|