Second Notice | | 4/18/2019 | 5/6/2019 | | DONE |
|
|
|
mailed 5-10-19
|
First Notice | | 3/18/2019 | 4/8/2019 | | DONE |
|
|
|
mailed 4-11-19
|
Permanent Occupancy | | | 3/8/2019 | | DONE |
|
|
|
|
BLD-Final | 3/1/2019 | 3/5/2019 | 3/5/2019 | A | PASS |
Tony Young
|
|
|
call for access- Lena Phone #: ###-####
|
BLD-Final | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | NR |
Tony Young
|
|
|
call for access- Lena Phone #: ###-####,, needs trades
|
FIRE-Final Inspection | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | PASS |
Jim Page
|
|
|
No fire sprinkler modifications, no fire alarm modifications, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete.
Lina Phone #: ###-####
|
BLD-Conference | 2/27/2019 | 2/28/2019 | 2/28/2019 | A | PART |
Tony Young
|
|
|
call for access- Lena Phone #: ###-####,, ?s on final,, need trades,, SWDH not required
|
FIRE-Final Inspection | 2/27/2019 | 2/28/2019 | 2/28/2019 | A | FAIL |
Troy Cobbley
|
|
|
Provide the permanant address as discussed, provide a tagged and mounted fire extinguisher as discussed, repair emergency light, remove tape from sprinkler pendants, provide single action door hardware for the interior doors.
Lena Phone #: ###-####
|
Plan assigned to (JAR) | 2/14/2019 | 2/14/2019 | 2/27/2019 | | DONE |
Julie Romig
|
|
|
02/27 - L2 Replenish Smoothie
|
Routing - PLAN CHECK | | | 2/27/2019 | | PASS |
Julie Romig
|
|
|
|
Case Summary (BLD) | | | 2/27/2019 | | DONE |
|
|
|
|
1st review completed | | | 2/27/2019 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/27/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/27/2019 | | DONE |
|
|
|
NEED- all met
GC FORM
REVISED VALUE
(LETTER FROM OWNER IF TENANT IS GC)
|
Print Occupancy Form | | | 2/27/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/27/2019 | | DONE |
|
|
|
|
Routing PW Environmental | 2/19/2019 | | 2/26/2019 | | PASS |
Terry Alber
|
|
|
No grease abatement required at this time.
|
Routing - PLUMBING | 2/25/2019 | | 2/25/2019 | | PASS |
Dan Ediger
|
|
|
Per ISPC and plans
|
Routing - PUBLIC WORKS | | | 2/25/2019 | | PASS |
|
|
|
|
Routing - Addressing | 2/14/2019 | | 2/19/2019 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 2/14/2019 | | PASS |
Julie Romig
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/14/2019 | | DONE |
|
|
|
|
Application received | | 2/14/2019 | | | |
|
|
|
|