BLD-Final | 6/3/2020 | 6/3/2020 | 6/3/2020 | A | DONE |
Dave Hannah
|
|
|
All structural has been completed. A seperate electrical permit will be required when owner installes electrical wiring.
|
DOC - Permit Finaled | | | 6/3/2020 | | DONE |
Dave Hannah
|
|
|
Electrical to be installed at a later date under seperate permit.
|
BLD-Conference | 5/15/2020 | 5/19/2020 | 5/19/2020 | A | DONE |
Dave Hannah
|
|
|
Status? ext of project is done
|
BLD-Aging Inspection | 2/12/2020 | 2/12/2020 | 2/19/2020 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 2/11/2020 | 2/11/2020 | 2/19/2020 | | PEND |
Dave Hannah
|
|
|
|
BLD-Other | 10/24/2019 | 10/25/2019 | 10/25/2019 | A | PASS |
Mike Jordan
|
|
|
extiror drywall // robur Phone #: ###-####
|
Plan Modification Accepted | | | 10/11/2019 | | DONE |
|
|
|
Robere Kazadi delete 2 windows, add 5/8" drywall to a portion of the bld, reduce eve to 4". 2 copies of sheet A-1 through A-6
|
Plan assigned to (M_H) | 10/11/2019 | | 10/11/2019 | | DONE |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 10/11/2019 | | 10/11/2019 | | PASS |
Michael Hanson
|
|
|
Plan mod approval no fees
|
Inspection Record Card- Bld | | | 10/11/2019 | | DONE |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 10/11/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 10/11/2019 | | DONE |
|
|
|
as per M_H-no plan mod fees due-no plans to scan-
|
CHANGE STATUS TO (ISS) | | | 10/11/2019 | | DONE |
|
|
|
as per M_H no plan mod fees due-no plans to scan-
|
BLD-Wall Bracing | 9/27/2019 | 9/30/2019 | 9/30/2019 | P | PART |
Dave Hannah
|
|
|
Robere Phone #: ###-#### ext ok to cover but needs to install hold downs at garage door
|
BLD-Other | 9/16/2019 | 9/16/2019 | 9/16/2019 | P | DONE |
Bob Archibald
|
|
|
Parcel tag has been removed, inspections and permits can now be obtained. A plan modification is required to address the fire rated requirements of the northern wall.
|
Plan Reviewer's activity | | | 9/16/2019 | | DONE |
Michael Hanson
|
|
|
Variance not required per Cody Riddle.
|
Plan Reviewer's activity | | | 9/16/2019 | | DONE |
Michael Hanson
|
|
|
Distance from center of flume to foundation as is okayed by Jason Taylor.
|
Case Summary (BLD) | | | 9/10/2019 | | DONE |
Jason Blais
|
|
|
|
Meeting | | | 9/10/2019 | | DONE |
Jason Blais
|
|
|
Met with builder Robere Kazadi to listen to his concerns and discuss outstanding issues with the project. Owners have submitted a Variance application to Planning. Due to some change in scope, approval from Planning and Public Works needed prior to submitting any plan changes to the Building Division to approve. Robere requested a meeting to be scheduled with Building, Planning and Public Works all together. Robere also inquired on status of citation issued. Will check with Legal.
|
BLD-Other | 8/13/2019 | 8/13/2019 | 8/13/2019 | A | DONE |
Bob Archibald
|
|
|
Reviewed site @ 11:15 am no work in progress. Roof sheathing had been completed since issuance of 1st citation.
|
Override - Parcel Holds | | | 8/13/2019 | | |
|
|
|
|
BLD-Conference | 8/12/2019 | 8/12/2019 | 8/12/2019 | A | DONE |
Bob Archibald
|
|
|
Issued citation to contractor, Robert Kazadi, Violation-BCC 9-1 Sec. R114.3
|
Override - Parcel Holds | | | 8/12/2019 | | |
|
|
|
|
BLD-Other | 8/8/2019 | 8/8/2019 | 8/8/2019 | A | DONE |
Bob Archibald
|
|
|
Tom with Code enforcement and I visited site to issue a citation for continuing to work after issuance of a SWO. No work in progress and no one on site. No citation issued.
|
Override - Parcel Holds | | | 8/8/2019 | | |
|
|
|
|
BLD-Conference | 8/6/2019 | 8/6/2019 | 8/7/2019 | P | DONE |
Dave Hannah
|
|
|
Issue SWO need plan modification and variance approval. swo issued and posted
|
Plan Reviewer's activity | | | 8/5/2019 | | DONE |
Michael Hanson
|
|
|
Dave Hannah indicated that the GC was moving forward on the building. I talked with Nicolette Womack and verified that they planning variance was not approved. Discussed situation with Jason Blais, Carl Madsen, and Dave Hannah. Direction was given to escalate to Bob Archibald and Cody Riddle to try to reach an agreement with the owner and GC on how to move forward.
|
Routing Walk-In (BLD) | 6/10/2019 | 6/10/2019 | 6/10/2019 | A | FAIL |
Josh Bogle
|
|
|
not my deal - brought in Michael, KayCee, 425
|
Meeting | | | 6/10/2019 | | DONE |
Michael Hanson
|
|
|
Ethan Mansfield (Current Planning), Kaycee Babb (Historic), Michael Hanson (Building), Robere Kazadi (Kazadi Group - GC) met to discuss path forward for the project since the existing garage has been torn down and the new construction doesn't meet setback requirements.
|
BLD-Footing | 5/31/2019 | 6/3/2019 | 6/4/2019 | A | PASS |
Dave Hannah
|
|
|
Robere Phone #: ###-####
|
Plan Reviewer's activity | | | 6/3/2019 | | DONE |
Michael Hanson
|
|
|
Left voicemail for Deanna regarding descrepancy between permitted structure and what is being built.
|
Plan Reviewer's activity | | | 6/3/2019 | | DONE |
Michael Hanson
|
|
|
Discussed issues over the phone with Deanna. She is having the GC come in to discuss a path forward.
|
Routing Walk-In (BLD) | 4/29/2019 | 4/29/2019 | 4/29/2019 | P | PASS |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 4/29/2019 | | 4/29/2019 | | PASS |
Michael Hanson
|
|
|
|
Inspection Record Card- Bld | | | 4/29/2019 | | DONE |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 4/29/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/29/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 4/29/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/29/2019 | | DONE |
|
|
|
no ESC no Energy per Michael
|
Routing Walk-In (Zoning) | 3/11/2019 | 3/11/2019 | 3/11/2019 | P | PASS |
Ethan Mansfield
|
|
|
|
Routing Walk-In (BLD) | 3/11/2019 | 3/11/2019 | 3/11/2019 | P | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 3/11/2019 | | 3/11/2019 | | FAIL |
Josh Bogle
|
|
|
lacked building plans
|
Routing Walk-In (Zoning) | 2/15/2019 | 2/15/2019 | 2/15/2019 | A | FAIL |
KayCee Babb
|
|
|
Verification from TV that plans meet conditions of approval of DRH18-00502.
|
1st review completed | | | 2/15/2019 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 2/15/2019 | | | |
|
|
|
|