Permit Information
Permit NumberBLD19-00485
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 2382 S TRAPPER PL
Project NameHarris Ranch North #1
Customer Number 
ePlanReviewYes
Description
**HILLSIDE** **WUI FOOTSHILLS ZONE A REQUIREMENTS** **PRESCRIPTIVE ENERGY REQUIREMENTS** Permit for the construction of a new 3191 sq. ft., one story single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 316 sq. ft. of covered patio/porch and a 828 sq. ft. attached garage per the approved plans and any notations. SP-01 zoning and setbacks per planning. JJN *SPRINKLERS ARE NOT REQUIRED. LGM * A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.


Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/4/201910/4/201910/4/2019PPASS
DetailsBrandon Shaw
Les Phone #: ###-####
DOC - Permit Finaled10/4/201910/4/201910/4/2019PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results10/4/201910/4/201910/4/2019PDONE
DetailsBrandon Shaw
ACH50- 3.73
PubWorks Occupancy Approval10/2/201910/2/201910/2/2019 DONE
DetailsMelissa Jannusch
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department.
BLD-Energy code compliance7/8/20197/8/20197/8/2019PCANC
DetailsBrandon Shaw
Les Phone #: ###-####
BLD-Energy code compliance7/5/20197/5/20197/5/2019PPASS
DetailsBrandon Shaw
Corrections SAT...
BLD-Framing/Rough-in6/27/20196/27/20196/27/2019PPEND
DetailsBrandon Shaw
Need Engineering approval for cut trusses A1- A4...
BLD-Other6/27/20196/27/20196/27/2019APASS
DetailsBrandon Shaw
Soffit...
BLD-Final6/26/20196/27/20196/27/2019ACANC
DetailsBrandon Shaw
Less- safet inspection Phone #: ###-####
BLD-Wall Bracing6/7/20196/7/20196/7/2019PPASS
DetailsBrandon Shaw
Corrections SAT...
BLD-Wall Bracing6/5/20196/6/20196/6/2019APEND
DetailsBrandon Shaw
Renail edge and field nailing as per plans...
BLD-Wall Bracing6/3/20196/3/20196/3/2019PFAIL
DetailsJim Storey
Les Phone #: ###-#### nails overdrinen at garage house covered w/o insp.
BLD-Foundation5/8/20195/8/20195/8/2019PPASS
DetailsBrandon Shaw
Work in progress...
BLD-Footing5/7/20195/7/20195/7/2019PPASS
DetailsJim Storey
Dion-would like as late as possible Phone #: ###-####
PubWorks Subgrade Approval5/7/20195/7/20195/7/2019 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. A footing inspection may now be scheduled with the Building Department.
Inspection Record Card- Bld  4/4/2019 DONE
Issue PAID IN FULL permit  4/4/2019 DONE
OVERRIDE  3/1/2019  
Plan assigned to (J_N)2/21/20192/21/20193/1/2019 DONE
DetailsJenny Nelson
03/14 sfd L2 ePlan. 1st complete 2/22, waiting for fire, esc and hillside reviews. Need calcs for foundation footings, only showing retaining wall calcs.
Permit Ready to Issue  3/1/2019 DONE
met
PLANS/APPL TAKEN TO FRONT DESK  3/1/2019 DONE
DetailsJenny Nelson
Routing - PLAN CHECK3/1/2019 3/1/2019 PASS
DetailsJenny Nelson
1st review completed  2/26/2019 DONE
DetailsJenny Nelson
Routing PW Grading-Hillside2/21/2019 2/26/2019 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.


Routing - FIRE2/21/20192/21/20192/25/2019 PASS
DetailsLee G Meredith
03/13 HHS Construction Residential Home

Sprinklers not required.
Routing - Erosion and Sediment2/21/2019 2/25/2019 PASS
DetailsMichael Zawacki
Route to Impact Fee Review2/21/20192/24/20192/22/2019 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - PLAN CHECK2/21/2019 2/22/2019 FAIL
DetailsJenny Nelson
Calcs not showing footings calcs
Intake Approval  2/21/2019 PASS
Recd Pcfee & Taken To Pln CK  2/21/2019 DONE
Plans ACCEPTED BY PLAN TECH  2/21/2019 DONE
Routing - PUBLIC WORKS2/21/2019 2/21/2019 PASS
DetailsAngela Hardy
Routing - Addressing2/21/2019 2/21/2019 PASS
DetailsDoug Chausow
Routing - PLANNING2/21/2019 2/21/2019 PASS
DetailsSue Cummings
Routing - MECHANICAL2/21/2019 2/21/2019 PASS
DetailsTroy James
CHANGE STATUS TO (PND)  2/20/2019 DONE
plan check fee hasn't been paid yet, didnt mean to start routing
Application received  2/19/2019 DONE
Application submitted via PDS Online on Feb 19 2019 8:01AM