BLD-Final | 7/17/2019 | 7/17/2019 | 7/17/2019 | P | PASS |
Dave Hannah
|
|
|
Blaine Phone #: ###-####
|
FIRE-Final Inspection | 6/3/2019 | 6/5/2019 | 6/5/2019 | A | PASS |
Jim Page
|
|
|
No fire sprinkler modifications, fire alarm inspection is complete, fire extinguisher is mounted with a current inspection tag. Final life fire safety inspection for area of work complete.
Blaine Phone #: ###-####
|
FIRE-Final Inspection | 5/31/2019 | 6/3/2019 | 6/3/2019 | A | FAIL |
Jim Page
|
|
|
Left a voicemail with the point of contact provided, FIR permit for project related fire alarm modifications needs to be completed before life fire safety inspection can be completed.
blaine Phone #: ###-####
|
BLD-Framing/Rough-in | 5/6/2019 | 5/7/2019 | 5/7/2019 | A | PASS |
Dave Hannah
|
|
|
Blaine Phone #: ###-####
|
Print Occupancy Form | | | 5/2/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/2/2019 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 2/26/2019 | 2/26/2019 | 3/6/2019 | | PASS |
Carl Westfall
|
|
|
* 03/06/19 (L2 - 7 days) (ePlan - 13 sheets) IHFA 3rd Floor Remodel
|
Routing - PLAN CHECK | 2/26/2019 | | 3/6/2019 | | PASS |
Carl Westfall
|
|
|
IBC plan review completed and approved
|
1st review completed | | | 3/6/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/6/2019 | | DONE |
|
|
|
met
NEED
GC FORM
REVISED VALUE
|
Intake Approval | | | 2/26/2019 | | PASS |
Michael Hanson
|
|
|
Prescreen approved by Michael Hanson
|
Application received | | | 2/19/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 19 2019 10:10AM
|