Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-00497
StatusFinaled
Name CHARLES BRAD DEBOER
Site Address 5120 W OVERLAND RD Unit: 100
Project NameGranny C's Bakery - Occupancy
Customer Number 
ePlanReviewNo
Description
(GRANNY C’S BAKERY – OCCUPANCY) The fire sprinkler system is used for occupancy. Application for inspection to determine the requirements for the issuance of a Certificate of Occupancy for an existing 1,553 square foot tenant space to be used to cook, serve, and retail fresh baked good. Egress is directly to the outside at grade. No new work is authorized under this permit except for minor work that may be needed to correct noncompliant conditions that may exist. Painting, carpeting, counter tops, shelves, and similar finish work are not required to have a building permit. Compliance is required with the items listed in the plan review report under Referenced Code Sections because noncompliance with these items is believed to constitute a distinct hazard to life and safety or to discriminate against the disabled. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/16/20197/17/20197/17/2019APASS
DetailsBrandon Shaw
Bred Phone #: ###-####
DOC - Permit Finaled7/17/20197/17/20197/17/2019PPASS
DetailsBrandon Shaw
Permanent Occupancy  7/17/2019 DONE
Temporary Occupancy7/5/201910/3/20197/5/2019 DONE
DetailsCandy A. Nichols
Jason Blais ok'd temp c of o for 30 days starting 7/4/19
Telephone call  7/2/2019 DONE
emailed cbraddeboer@gmail.com that the temp c of o will expire and they need to call in the final or req an extension
BLD-Aging Inspection6/13/20196/13/20196/14/2019 DONE
DetailsTell Riley
needs mechanical permit and inspection for final occupancy.
BLD-Final4/4/20194/5/20194/5/2019APART
DetailsJim Sly
Brad Phone #: ###-####
OK for Temp. Occ. OK for Perm. Occ. when Mech. signs off for Perm.
Temporary Occupancy4/5/20197/4/20194/5/2019 DONE
DetailsTiffany Carson-Herker
FIRE-Final Inspection4/4/20194/4/20194/4/2019PPASS
DetailsTroy Cobbley
life safety passed. Cooler has been removed.

Charles Phone #: ###-####
FIRE-Conference3/28/20193/28/20193/28/2019PDONE
DetailsTroy Cobbley
Owner had questions on difference between the night lights and the emergency lights.
BLD-Final3/27/20193/27/20193/28/2019PNR
DetailsJim Sly
Charles- please call Phone #: ###-####
Need Fire Final.
FIRE-Final Inspection3/26/20193/27/20193/27/2019AFAIL
DetailsTroy Cobbley
Provide suite number, repair emergency lights, provide sprinkler coverage for the walkin cooler.

Brad Phone #: ###-####
Route to Impact Fee Review2/25/20192/28/20192/28/2019 PASS
DetailsKarina Myles
Review requested for Commercial Permit
Permit Ready to Issue  2/26/2019 DONE
Print Occupancy Form  2/26/2019 DONE
Telephone call  2/26/2019 DONE
spoke with brad informing him that this permit is ready and which ever tech he sees when he comes in will go over the required inspections
Issue PAID IN FULL permit  2/26/2019 DONE
Plan assigned to (CJW)2/19/20192/19/20192/25/2019 PASS
DetailsCarl Westfall
Occupancy
Routing - PLAN CHECK2/25/2019 2/25/2019 PASS
DetailsCarl Westfall
Routing - PUBLIC WORKS2/19/2019 2/25/2019 PASS
DetailsAngela Hardy
1st review completed  2/25/2019 DONE
PLANS/APPL TAKEN TO FRONT DESK  2/25/2019 DONE
Routing PW Environmental2/20/2019 2/22/2019 PASS
DetailsTerry Alber
Routing - Addressing2/19/2019 2/20/2019 PASS
DetailsDoug Chausow
Plans ACCEPTED BY PLAN TECH  2/19/2019 DONE
Intake Approval  2/19/2019 PASS
DetailsCarl Westfall
Recd Pcfee & Taken To Pln CK  2/19/2019 DONE
First Notice 7/27/2019   
First Notice7/17/20197/17/2019   
DetailsBrandon Shaw
Application received 2/19/2019