Telephone call | | | 12/2/2019 | | DONE |
|
|
|
Spoke with Skyler Dabell to check on the project value and mechanical value. The mechanical that was submitted was for demo work only, no MEC permit was required (see attahced MIS case). Project changed becuse the cost of work went down.
|
Second Notice | | 11/4/2019 | 11/25/2019 | | DONE |
|
|
|
mailed 12-2-19
|
First Notice | | 10/13/2019 | 10/25/2019 | | DONE |
|
|
|
mailed 11-1-19
|
Permanent Occupancy | | | 10/3/2019 | | DONE |
|
|
|
|
BLD-Final | 10/1/2019 | 10/2/2019 | 10/2/2019 | A | PASS |
Mike Jordan
|
|
|
Josh Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 9/16/2019 | 9/18/2019 | 9/18/2019 | A | FAIL |
Mike Jordan
|
|
|
Josh Phone #: ###-####. Provide the additional hand rail at north west exit. everything else ok.
|
FIRE-Final Inspection | 9/16/2019 | 9/17/2019 | 9/17/2019 | P | PASS |
Mike Jordan
|
|
|
Josh Phone #: ###-####. All previously noted items have been repaired.
|
Zoning Approval | 9/17/2019 | 9/17/2019 | 9/17/2019 | | PASS |
KayCee Babb
|
|
|
Per DRH19-00013, as revised 4-10-19.
|
FIRE-Final Inspection | 7/23/2019 | 7/23/2019 | 7/23/2019 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled per Josh-please call when on way so can meet with you Phone #: ###-####
|
FIRE-Final Inspection | 7/10/2019 | 7/10/2019 | 7/10/2019 | P | FAIL |
Troy Cobbley
|
|
|
No small documents on site. I noted that one exit discharge light did not function and the other was not installed yet. We discussed CO alarm and occupant load signage. Fire extinguisher and hood suppression inspections are current. Per the contractor there was no change of kitchen equipment or change of hvac equipment.
Josh- please call before arriving Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | PASS |
Mike Jordan
|
|
|
josh Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 6/3/2019 | 6/4/2019 | 6/4/2019 | A | NR |
Mike Jordan
|
|
|
Josh Phone #: ###-####. Needs mep's and finish install.
|
BLD-Wall Bracing | 5/28/2019 | 5/28/2019 | 5/28/2019 | P | PASS |
Mike Jordan
|
|
|
shear // Josh Phone #: ###-####
|
BLD-Footing | 5/20/2019 | 5/20/2019 | 5/20/2019 | P | PART |
Mike Jordan
|
|
|
Josh Phone #: ###-####. Contractor has gotten special inspection on adhesive anchors, will have conrete tested as well. Work in progress on installing remaining reinforcement Ok for concrete.
|
BLD-Footing | 5/16/2019 | 5/17/2019 | 5/17/2019 | A | NR |
Mike Jordan
|
|
|
josh Phone #: ###-####. Special inspection is required for the adhesive anchors. Work is still inprogress.
|
BLD-Framing/Rough-in | 5/14/2019 | 5/15/2019 | 5/15/2019 | A | PASS |
Mike Jordan
|
|
|
Josh-please call 30 minutes prior to meet Phone #: ###-####. New facade framing ok.
|
Print Occupancy Form | | | 5/1/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/1/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 4/17/2019 | | |
|
|
|
|
Plan assigned to (JG) | 4/11/2019 | 4/11/2019 | 4/17/2019 | | PASS |
Javier Guzman
|
|
|
2nd rev, McDonald's #13630
|
Routing - PLAN CHECK | 4/12/2019 | | 4/17/2019 | | PASS |
Javier Guzman
|
|
|
|
Permit Ready to Issue | | | 4/17/2019 | | DONE |
|
|
|
Need_all met
GC Form-met
RP
Revised Value-met
|
Routing - Design Review | 4/12/2019 | | 4/16/2019 | | PASS |
KayCee Babb
|
|
|
Per DRH19-00013, select changes to the exterior are approved as shown on sheets A1.0, A2.0, A4.0, A4,1, A7.1. All conditions of approval, including color selection, shall be met.
|
Plan resubmittals received | | | 4/11/2019 | | DONE |
|
|
|
Resubmittal received in e plan-changes to the outside of the building decor
|
OVERRIDE | | | 4/2/2019 | | |
|
|
|
|
Route to Impact Fee Review | 4/2/2019 | 4/5/2019 | 4/2/2019 | | PASS |
Karina Myles
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (JG) | 3/9/2019 | 3/9/2019 | 4/2/2019 | | PASS |
Javier Guzman
|
|
|
03/27 L3 McDonalds ePlan, pend fire and eng
|
Routing Off Site - STRUCTURAL | 3/21/2019 | | 4/2/2019 | | PASS |
Javier Guzman
|
|
|
Signed off in ePlan by KPFF Sidney Gold
|
1st review completed | | | 4/2/2019 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/2/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/2/2019 | | DONE |
|
|
|
NEED-
GC form
Revised Cert of Value
RP-met
|
Routing - FIRE | 3/9/2019 | 3/9/2019 | 4/1/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Review 04.01.2019.pdf uploaded.
|
Routing - PLAN CHECK | 3/9/2019 | | 3/28/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing PW Environmental | 3/11/2019 | | 3/18/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - Design Review | 3/9/2019 | | 3/12/2019 | | PASS |
KayCee Babb
|
|
|
Per DRH19-00013. All conditions of approval, including color selection, shall be met.
|
Routing - MECHANICAL | 3/9/2019 | | 3/11/2019 | | PASS |
Troy James
|
|
|
No mechanical work shown.
|
Routing - PLUMBING | 3/9/2019 | | 3/11/2019 | | PASS |
Daryl Spivey
|
|
|
See redline notes and per plan and ISPC.
|
Routing - Addressing | 3/9/2019 | | 3/11/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/9/2019 | | 3/11/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 3/9/2019 | | 3/11/2019 | | PASS |
Michael Zawacki
|
|
|
Follow provided ESC map and plan
|
Intake Approval | | | 3/6/2019 | | PASS |
|
|
|
|
Intake Approval | | | 2/28/2019 | | FAIL |
Brian McGowan
|
|
|
Please provide the following information in order to process the Prescreen;
1. Provide Planning and Zoning Approval Letters.
2. Complete the cover sheet of Form #310.
3. DOC_McDonalds.ESC is not signed and stamped.
4. The exterior Menu Board designs were uploaded twice. These will need to be applied for in a separate permit. (The exterior Menu Board design is stamped and signed by a Tennessee Engineer. The stamp needs to be an Idaho Stamp.)
5. Sheets DT1.1, DT1.2, DT1.3 are not stamped by an Engineer.
6. DOC_Persona DT Sign Calcs are for Mountain Home, not Boise.
7. DOC_Persona DT Sign Dwgs is for Mountain Home.
8. DWG_Coates ODMB- 115 MPH has a Tennessee stamp and 2012 IBC. It is for a sign and should be submitted for in a separate permit.
9. No Sheet A10.0 was uploaded for the finish schedule or required plumbing fixtures. It is referenced to for Accessibility as well.
10. A1.1 does not show Exit signs and Emergency lighting.
11. DOC_McDonalds.ESC.Narrative has the wrong address on the cover sheet and is not stamped and signed.
12. The documents and drawings for the signs and foundations/footings for the signs must be applied for in a separate permit and pass Planning.
Note that many of the sheets specified as to where to find the information was not correct. Please verify that the Sheet number matches where the information can be found.
Than you,
|
Application received | | | 2/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 21 2019 1:41PM
|