Routing - Design Review | 8/11/2020 | | 8/11/2020 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Energy code compliance | 5/12/2020 | 5/12/2020 | 5/12/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Travis Blackburn//main area ok//do not cover back bathroom or pool heater room//
|
BLD-Framing/Rough-in | 5/6/2020 | 5/7/2020 | 5/7/2020 | A | PASS |
Tell Riley
|
|
|
Approval to insulate Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok to insulate, pool room area not yet approved by mechanical//
|
BLD-Framing/Rough-in | 5/6/2020 | 5/6/2020 | 5/6/2020 | P | PART |
Tell Riley
|
|
|
Finish framing inspection Phone #: ###-#### Inspection requested via web by Travis Blackburn//Truss corrections made from previous day, othr 1/2 trusses checked, minor nailing corrections//will check other framing tomorrow//
|
BLD-Framing/Rough-in | 5/4/2020 | 5/5/2020 | 5/6/2020 | P | PART |
Tell Riley
|
|
|
Inspection to allow insulation install. Phone #: ###-#### Inspection requested via web by Travis Blackburn//add bolts as discussed, fix holddowns, 1/2 trusses were looked at, some corrections required, will check at next inspection//
|
BLD-Wall Bracing | 5/5/2020 | 5/5/2020 | 5/6/2020 | P | PASS |
Tell Riley
|
|
|
most shear corrections made, some hardware will be addressed during framing inspeciton//
|
BLD-Framing/Rough-in | 2/19/2020 | 2/20/2020 | 2/20/2020 | A | PART |
Tell Riley
|
|
|
Mail room only for prerock Phone #: ###-#### Inspection requested via web by Travis Blackburn//pre-rock areas ok to cover//fix hold down bolt prior to cover//
|
BLD-Wall Bracing | 12/17/2019 | 12/18/2019 | 12/18/2019 | P | FAIL |
Tell Riley
|
|
|
Shear inspection on clubhouse Phone #: ###-#### Inspection requested via web by Travis Blackburn//walked clubhouse with Ben--he has corrections noted on tablet onsite--holdowns issues, anchor bolt issues, nailing at sill plate and blocking in one area//
|
BLD-Concrete | 10/9/2019 | 10/14/2019 | 10/14/2019 | P | PASS |
Tell Riley
|
|
|
This is for the slab for our clubhouse. The pour actually takes place on Tuesday 10/15/19 at 6:30am Phone #: ###-#### Inspection requested via web by Matt Perry//vapor barrier ok//no bar for slab//specials will test concrete at time of pour///
|
BLD-Foundation | 9/16/2019 | 9/16/2019 | 9/16/2019 | P | PASS |
Tell Riley
|
|
|
This is a reinspection for reinforcement at corners. Pour time is at 2 pm Phone #: ###-#### Inspection requested via web by Travis Blackburn//working on clearances on bar while onsite//corrections made from previous inspection//ok pending specials//
|
BLD-Foundation | 9/10/2019 | 9/12/2019 | 9/12/2019 | P | FAIL |
Mike Jordan
|
|
|
Concrete pour is at 1pm Phone #: ###-#### Inspection requested via web by Travis Blackburn. Missing vertical reinforcement in corners. Need RFI for repair.
|
BLD-Footing | 9/5/2019 | 9/6/2019 | 9/6/2019 | P | PASS |
Tell Riley
|
|
|
Concrete is scheduled for 1pm to pour these footings Phone #: ###-#### Inspection requested via web by Travis Blackburn//pending specials//ok to pour//
|
Issue PAID IN FULL permit | | | 8/15/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/15/2019 | | DONE |
|
|
|
|
Meeting | | | 8/14/2019 | | DONE |
|
|
|
sent an email to scott and jason with ESI about sending in an extension request if these permits are not going to be paid for and issued by 5pm on 8/20
|
Permit Ready to Issue | | | 8/13/2019 | | DONE |
|
|
|
DO NOT ISSUE WITHOUT OHTER 13 PERMITS AND VOIDED PERMIT HAS PLAN CHECK FEES
met
RP
GC
Revised Certificate of Value
|
Routing PW Street Lights | 8/12/2019 | | 8/12/2019 | | PASS |
Tom Marshall
|
|
|
|
Plan assigned to (CJW) | 3/11/2019 | 3/11/2019 | 8/10/2019 | | PASS |
Carl Westfall
|
|
|
* (2nd done) 04/08/19 (new buildings - 25 days) (eplan) Village East Apartments (Clubhouse) (approved pending structural)
|
Plan Reviewer's activity | | | 8/10/2019 | | DONE |
|
|
|
See the routing under permit BLD19-00526 for all buildings.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/10/2019 | | DONE |
|
|
|
|
Routing - Design Review | 8/5/2019 | | 8/5/2019 | | PASS |
Andrea Tuning
|
|
|
|
Routing - FIRE | 7/9/2019 | 7/9/2019 | 7/16/2019 | | PASS |
Mark Scharfen
|
|
|
07/16-Village East Clubhouse resubmittal. MS. Completed fire review, uploaded rev_fire 07.16.2019.pdf. All permits approved on fire.
|
Routing PW Drainage | 7/15/2019 | | 7/15/2019 | | PASS |
Brian Murphy
|
|
|
|
Plan resubmittals received | | | 7/8/2019 | | DONE |
|
|
|
See the routing under permit BLD19-00526 for the 3rd plan review. None of the permits can be issued until all plan reviews are approved. CJW
|
Routing - FIRE | 6/13/2019 | 6/13/2019 | 6/24/2019 | | FAIL |
Mark Scharfen
|
|
|
06/26-Village East Clubhouse Building resubmittal MS. Completed review. Need info on playhouse in kids room. Uploaded rev_fire 06.24.2019.pdf and emailed architect.
|
Routing - Design Review | 6/17/2019 | | 6/17/2019 | | FAIL |
Andrea Tuning
|
|
|
A total of 272 bicycle parking spaces will be required. A minimum of 68 of the bicycle parking spaces are required to be covered. To provide a safe, covered and efficient location for the bicycles, design the spaces to be a minimum of 6-feet long and 2.5 feet wide and have an overhead clearance of 7-feet if covered. A 4-foot wide aisle is required between rows of bicycle parking or nearby walls. Stationary racks shall be located on improved non-permeable surfaces and anchored to the ground. A detail of the rack and how it is attached to the wall should be submitted with the building permit.
Vertical curbing shall be utilized adjacent to all landscaping and pedestrian walk ways. Permanent wheel restraints may be utilized in lieu of curbing adjacent to pedestrian walk ways.
All interior and terminal planter islands shall provide at least one Class II tree within all of the interior and terminal planters.
Provide an easement for portions of the Valley Regional transit stop located on private property.
Continue to work with staff to provide a cohesive and quality exterior building design in regard to material breaks, the application of brick on each building and the color palette for the development. This may include providing a brick wainscot or brick corner elements on each building, reevaluating the location of material breaks and further refining the color palette.
Employ techniques to recess windows above the ground floor a minimum of 2-inches from the façade or incorporated window trim at least 4-inches in width. Submit a window detail showing this recess.
|
Plan Reviewer's activity | | | 6/13/2019 | | DONE |
|
|
|
See the routing under permit BLD19-00526 for the 2nd plan review. None of the permits can be issued until all plan reviews are approved. CJW
|
Route to Impact Fee Review | 4/18/2019 | 4/21/2019 | 4/19/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 3/11/2019 | | 4/17/2019 | | FAIL |
Carl Westfall
|
|
|
|
1st review completed | | | 4/17/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 4/17/2019 | | DONE |
|
|
|
|
Routing - FIRE | 3/11/2019 | 3/11/2019 | 4/12/2019 | | FAIL |
Mark Scharfen
|
|
|
IFC 1st review 04.12.2019.pdf
|
Routing Off Site - STRUCTURAL | 3/11/2019 | | 3/27/2019 | | FAIL |
Carl Westfall
|
|
|
Cory Harelson (KPFF)
|
Routing - Erosion and Sediment | 3/11/2019 | | 3/27/2019 | | PASS |
Andy J. Long
|
|
|
see ESC19-00181 for details
|
Routing PW Sewer Design | 3/12/2019 | | 3/26/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Solid Waste | 3/12/2019 | | 3/21/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Drainage | 3/12/2019 | | 3/21/2019 | | FAIL |
Brian Murphy
|
|
|
|
Routing - PLANNING | 3/11/2019 | | 3/19/2019 | | FAIL |
Leon Letson
|
|
|
See DR comments
|
Routing - MECHANICAL | 3/11/2019 | | 3/15/2019 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 3/11/2019 | | 3/13/2019 | | FAIL |
Andrea Tuning
|
|
|
|
Routing - Addressing | 3/11/2019 | | 3/12/2019 | | PASS |
Doug Chausow
|
|
|
Clubhouse: 11972 W Fairview Ave
|
Routing - PUBLIC WORKS | 3/11/2019 | | 3/12/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing PW Street Lights | 3/12/2019 | | 3/12/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing - PLUMBING | 3/11/2019 | | 3/11/2019 | | PASS |
Daryl Spivey
|
|
|
Meet suds relief requirements and per ISPC.
|
Intake Approval | | | 3/5/2019 | | PASS |
|
|
|
|
Application received | | | 2/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 21 2019 5:02PM
|