Permanent Occupancy | | | 9/17/2019 | | DONE |
|
|
|
|
Meeting | | | 9/17/2019 | | DONE |
|
|
|
Spoke with Julie about the changing of the suite number on plans and application to suite #108 per addressing.
|
BLD-Final | 8/27/2019 | 8/28/2019 | 8/28/2019 | A | PASS |
Jim Storey
|
|
|
Ann Phone #: ###-####
|
FIRE-Final Inspection | 8/22/2019 | 8/23/2019 | 8/23/2019 | A | PASS |
Troy Cobbley
|
|
|
life safety passed.
Ann Phone #: ###-####
|
FIRE-Final Inspection | 8/2/2019 | 8/8/2019 | 8/8/2019 | A | FAIL |
Jim Page
|
|
|
Corrections have not been made to the fire sprinkler modifications, FIR permit for area of work is still in issued status, FIR19-00459, reference notes entered by Troy Cobbley on 02AUG2019.
Ann Phone #: ###-####
|
FIRE-Final Inspection | 7/31/2019 | 8/2/2019 | 8/2/2019 | A | FAIL |
Troy Cobbley
|
|
|
Life safety wil be ok to pass when the project related fire sprinkler permit, FIR19-00459, is finaled. Ann Phone #: ###-####
|
FIRE-Final Inspection | 6/27/2019 | 6/28/2019 | 6/28/2019 | A | CANC |
Jim Page
|
|
|
Due to the history of this permit, the point of contact is going to reschedule for when Troy Cobbley is back in the office, this request is cancelled per conversation with point of contact.
Ann Phone #: ###-####
|
BLD-Final | 3/12/2019 | 3/14/2019 | 3/14/2019 | P | CANC |
Jim Storey
|
|
|
Ann Phone #: ###-####
|
FIRE-Final Inspection | 3/12/2019 | 3/13/2019 | 3/13/2019 | P | FAIL |
Troy Cobbley
|
|
|
Not ready for final inspection due to needing the fire sprinkler work permited and a fire sprinkler monitoring system installed. There are still other life safety items as marked on the plans that need addressed.
Ann Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/12/2019 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 2/25/2019 | 2/25/2019 | 3/5/2019 | | DONE |
Julie Romig
|
|
|
03/01 - IBC Rev Comp - 528 BMI Warehouse/office
|
Routing - FIRE | | 2/25/2019 | 3/5/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Fire Review 03.05.2019.pdf uploaded.
|
1st review completed | | | 3/5/2019 | | DONE |
Julie Romig
|
|
|
IBC Review complete 03/01/19
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/5/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/5/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/5/2019 | | DONE |
|
|
|
|
Telephone call | | | 3/5/2019 | | DONE |
|
|
|
spoke with chad informing him that this permit is ready to be picked
|
Case Summary (BLD) | | | 2/28/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/28/2019 | | 2/28/2019 | | PASS |
Julie Romig
|
|
|
IBC Review received and completed on 2/28/19 (4 days)
|
Routing - PUBLIC WORKS | 2/25/2019 | | 2/28/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Environmental | 2/26/2019 | | 2/27/2019 | | PASS |
Rick Christenson
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/25/2019 | | DONE |
|
|
|
|
Intake Approval | | | 2/25/2019 | | PASS |
Julie Romig
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/25/2019 | | DONE |
|
|
|
|
Routing - Addressing | 2/25/2019 | | 2/25/2019 | | PASS |
Laura Hunter
|
|
|
6/24 - CHANGED TO STE 108, PER JULIE AND THE OWNER ANN
|
First Notice | | 9/27/2019 | | | |
|
|
|
|
Application received | | 2/25/2019 | | | |
|
|
|
|