BLD-Final | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Dave Hannah
|
|
|
Ryan Phone #: ###-####
|
DOC - Permit Finaled | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Blower Door Test Results | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Dave Hannah
|
|
|
4.7
|
Plan Reviewer's activity | | | 8/9/2019 | | DONE |
Michael Hanson
|
|
|
Owner would like to move in without a building permit final. He would like to build the pool which means allot of heavy equipment and he doesn't want to pour the driveway before he moves in. Met with Brent Moore he is not allowing a bond so I gave him Tony Youngs and Bob Archibald to contact to resolve timing of driveway installation.
|
BLD-Energy code compliance | 5/23/2019 | 5/24/2019 | 5/24/2019 | A | PASS |
Dave Hannah
|
|
|
Ryan Phone #: ###-####
|
BLD-Framing/Rough-in | 5/22/2019 | 5/22/2019 | 5/23/2019 | P | PART |
Tony Young
|
|
|
Ryan Phone #: ###-####,, needs sprinklers,, ok to insulate
|
BLD-Wall Bracing | 5/21/2019 | 5/22/2019 | 5/22/2019 | P | PART |
Tony Young
|
|
|
Ryan Phone #: ###-####,, work in progress,, ok
|
BLD-Framing/Rough-in | 5/21/2019 | 5/21/2019 | 5/21/2019 | P | PART |
Brandon Shaw
|
|
|
Wall brace- nail PFH and install hold downs as per plans...
|
BLD-Foundation | 4/1/2019 | 4/2/2019 | 4/2/2019 | P | PASS |
Tony Young
|
|
|
Bryan Phone #: ###-####
|
BLD-Footing | 4/1/2019 | 4/1/2019 | 4/1/2019 | P | PASS |
Tony Young
|
|
|
Brian Phone #: ###-####-called to late for a AM insp
|
OVERRIDE | | | 3/14/2019 | | |
|
|
|
|
Telephone call | | | 3/14/2019 | | DONE |
|
|
|
Spoke with Ryan to inform him the permit is ready and what fees are due.
|
Issue PAID IN FULL permit | | | 3/14/2019 | | DONE |
|
|
|
|
Plan assigned to (M_H) | | | 3/14/2019 | | DONE |
Michael Hanson
|
|
|
03/08 #402 L1 Paper. 1st review completed - See changemarks in ePlan for corrections required.
|
Routing - PLAN CHECK | 3/14/2019 | | 3/14/2019 | | PASS |
Michael Hanson
|
|
|
|
Routing - PLANNING | 3/14/2019 | | 3/14/2019 | | PASS |
Sue Cummings
|
|
|
Per Cody
|
Case Summary (BLD) | | | 3/14/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/14/2019 | | DONE |
Michael Hanson
|
|
|
|
Inspection Record Card- Bld | | | 3/14/2019 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 3/14/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 3/14/2019 | | DONE |
|
|
|
met
|
Plan resubmittals received | | | 3/13/2019 | | DONE |
|
|
|
Two copies of RV Bay tall wall and lateral design packets and two copies of plan sheets A-1, A-2, A-2a, A-3, A-4, A-4a, A-6, A-7, S-1 and E-1. taken to Michael
|
1st review completed | | | 3/11/2019 | | FAIL |
Michael Hanson
|
|
|
Plan check was completed on 03/08 see email. Fire review was delayed by illness completed on 03/11.
|
Routing - FIRE | 3/6/2019 | | 3/11/2019 | | PASS |
Lee G Meredith
|
|
|
03/08-4123 W. Garnet Res. Lot setback.
3-11-19: access and hydrant distance exceed maximum distances allowed. NFPA 13D sprinkler system required. Resubmittal required.
3-14-19: Applicant added a note to the site plan that indicates an NFPA 13D sprinkler system will be provided.
|
Routing - PLAN CHECK | | | 3/8/2019 | | FAIL |
Michael Hanson
|
|
|
Plan check was completed on 03/08 see email. Fire review was delayed by illness completed on 03/11.
|
Routing - MECHANICAL | 3/7/2019 | | 3/7/2019 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 3/7/2019 | | DONE |
|
|
|
Resubmittals blought in- 2 site plans & 2 sheets A-1-took to M_H
|
Routing - MECHANICAL | 3/1/2019 | | 3/6/2019 | | FAIL |
Troy James
|
|
|
Emailed corrections to designer
|
Routing - PLANNING | 2/27/2019 | | 3/1/2019 | | FAIL |
|
|
|
Talked to Ryan about the changes needed to the site plan. He's bringing in a new one.
|
Route to Impact Fee Review | 2/26/2019 | 3/1/2019 | 2/28/2019 | | PASS |
Karina Myles
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 2/25/2019 | | 2/27/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/25/2019 | | 2/27/2019 | | PASS |
Angela Hardy
|
|
|
|
Override - Parcel Holds | | | 2/26/2019 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/25/2019 | | DONE |
|
|
|
|
Intake Approval | | | 2/25/2019 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/25/2019 | | DONE |
|
|
|
|
Application received | | 2/25/2019 | | | |
|
|
|
|