BLD-Final | 2/28/2020 | 3/3/2020 | 3/3/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 3/3/2020 | 3/3/2020 | 3/3/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 2/28/2020 | 3/3/2020 | 3/3/2020 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.58
|
BLD-Energy code compliance | 12/26/2019 | 12/30/2019 | 12/30/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 12/20/2019 | 12/26/2019 | 12/26/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Wall Bracing | 12/16/2019 | 12/16/2019 | 12/16/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Other | 12/16/2019 | 12/16/2019 | 12/16/2019 | P | PASS |
Brandon Shaw
|
|
|
Soffit
|
BLD-Energy code compliance | 12/16/2019 | 12/16/2019 | 12/16/2019 | P | CANC |
Brandon Shaw
|
|
|
Jorhe Phone #: ###-####
|
BLD-Wall Bracing | 11/25/2019 | 11/26/2019 | 11/26/2019 | A | PASS |
Brandon Shaw
|
|
|
OK to cover exterior...
|
BLD-Foundation | 9/23/2019 | 9/23/2019 | 9/23/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 9/19/2019 | 9/20/2019 | 9/20/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
PubWorks Subgrade Approval | 9/18/2019 | 9/18/2019 | 9/18/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 9/9/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/9/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 9/5/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 9/3/2019 | 9/3/2019 | 9/5/2019 | | DONE |
Rob Patrick
|
|
|
Waiting for Fire to Review
|
Routing - PLAN CHECK | 9/5/2019 | | 9/5/2019 | | PASS |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 9/5/2019 | | DONE |
|
|
|
met
|
Routing - FIRE | 8/30/2019 | 8/30/2019 | 9/3/2019 | | PASS |
Lee G Meredith
|
|
|
09/06 Cutler 1473 S Bouler View Ln
Sprinklers are not required.
|
Plan assigned to (RDP) | 2/26/2019 | 2/26/2019 | 8/29/2019 | | DONE |
Rob Patrick
|
|
|
03/11 sfd L1 ePlan...03/07 Failed; Corrections Req'd
|
Routing - PLAN CHECK | 8/29/2019 | | 8/29/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/29/2019 | | DONE |
Rob Patrick
|
|
|
|
CHANGE STATUS TO (REV) | | | 8/29/2019 | | DONE |
|
|
|
Sent back to review from FEE status. Missed Fire review.
|
Routing - PLAN CHECK | 8/26/2019 | | 8/26/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Plan Reviewer's activity | | | 8/21/2019 | | |
Rob Patrick
|
|
|
Emailed Amy to let her know this perimit request will expire on the 25th and let me know what they intend to do.
|
1st review completed | | | 3/7/2019 | | FAIL |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 2/26/2019 | | 3/7/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Route to Impact Fee Review | 2/26/2019 | 3/1/2019 | 2/27/2019 | | PASS |
Karina Myles
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 2/26/2019 | | 2/27/2019 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 2/26/2019 | | 2/27/2019 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 2/26/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 26 2019 11:40AM
|
Plans ACCEPTED BY PLAN TECH | | | 2/26/2019 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/26/2019 | | DONE |
|
|
|
|
Intake Approval | | | 2/26/2019 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 2/26/2019 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/26/2019 | | DONE |
|
|
|
|
Routing - PLANNING | 2/26/2019 | | 2/26/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - PUBLIC WORKS | 2/26/2019 | | 2/26/2019 | | PASS |
Angela Hardy
|
|
|
|