Permit Information
Permit NumberBLD19-00586
StatusIssued
Name STEVEN S TROUT
Site Address 3907 S MESA VIEW LN
Project NameStevens + Trout Art Studio Bld
Customer Number 
ePlanReviewYes
Description
Permit to build a deteched office/art studio/storage building that includes 827sq' of habitable space, 326sq' of uncondititoned storage, & 200sq' of covered patio. A half-bath is in the habitable space. Heating/cooling via Air-source heat-pump. Make-up fresh air source required. All work per plans, notations, attachments, engineering, local codes & ordinances. Separate electrical, plumbing & mechanical permits required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection6/25/20206/25/20206/25/2020 DEFR
DetailsBrandon Shaw
BLD-Aging Inspection6/24/20206/24/20206/25/2020 DEFR
DetailsBrandon Shaw
Extend Permit 90/180 days6/25/20206/25/20206/25/2020PDONE
DetailsBrandon Shaw
BLD-Wall Bracing2/11/20202/11/20202/11/2020PPASS
DetailsBrandon Shaw
Ok to cover exterior...
BLD-Foundation7/26/20197/29/20197/29/2019PPASS
DetailsBrandon Shaw
Work in progress...
BLD-Foundation7/22/20197/23/20197/23/2019PPASS
DetailsBrandon Shaw
Steve Phone #: ###-####
Issue PAID IN FULL permit  3/7/2019 DONE
Inspection Record Card- Bld  3/7/2019 DONE
Meeting  3/7/2019 DONE
emailed Steve the permit to sign.
OVERRIDE  3/6/2019  
Permit Ready to Issue  3/6/2019 DONE
Plan assigned to (JAB) Josh2/27/20192/27/20193/5/2019 PASS
DetailsJosh Bogle
3/5 deteched office, ePlan - 1st done
Routing - PLAN CHECK3/5/2019 3/5/2019 PASS
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  3/5/2019 DONE
DetailsJosh Bogle
ESC yes - Energy yes
1st review completed  3/4/2019 FAIL
DetailsJosh Bogle
Routing - PLAN CHECK2/27/2019 3/4/2019 FAIL
DetailsJosh Bogle
thermal issues - see PR notes & email to Steve 3/4/19
Routing - PLANNING2/27/2019 2/28/2019 PASS
DetailsNicolette Womack
Plans ACCEPTED BY PLAN TECH  2/27/2019 DONE
Intake Approval  2/27/2019 PASS
Application received  2/26/2019 DONE
Application submitted via PDS Online on Feb 26 2019 12:01PM