BLD-Aging Inspection | 6/25/2020 | 6/25/2020 | 6/25/2020 | | DEFR |
Brandon Shaw
|
|
|
|
BLD-Aging Inspection | 6/24/2020 | 6/24/2020 | 6/25/2020 | | DEFR |
Brandon Shaw
|
|
|
|
Extend Permit 90/180 days | 6/25/2020 | 6/25/2020 | 6/25/2020 | P | DONE |
Brandon Shaw
|
|
|
|
BLD-Wall Bracing | 2/11/2020 | 2/11/2020 | 2/11/2020 | P | PASS |
Brandon Shaw
|
|
|
Ok to cover exterior...
|
BLD-Foundation | 7/26/2019 | 7/29/2019 | 7/29/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Foundation | 7/22/2019 | 7/23/2019 | 7/23/2019 | P | PASS |
Brandon Shaw
|
|
|
Steve Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/7/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2019 | | DONE |
|
|
|
|
Meeting | | | 3/7/2019 | | DONE |
|
|
|
emailed Steve the permit to sign.
|
OVERRIDE | | | 3/6/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 3/6/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 2/27/2019 | 2/27/2019 | 3/5/2019 | | PASS |
Josh Bogle
|
|
|
3/5 deteched office, ePlan - 1st done
|
Routing - PLAN CHECK | 3/5/2019 | | 3/5/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/5/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
1st review completed | | | 3/4/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 2/27/2019 | | 3/4/2019 | | FAIL |
Josh Bogle
|
|
|
thermal issues - see PR notes & email to Steve 3/4/19
|
Routing - PLANNING | 2/27/2019 | | 2/28/2019 | | PASS |
Nicolette Womack
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/27/2019 | | DONE |
|
|
|
|
Intake Approval | | | 2/27/2019 | | PASS |
|
|
|
|
Application received | | | 2/26/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 26 2019 12:01PM
|