BLD-Aging Inspection | 2/24/2020 | 2/24/2020 | 2/24/2020 | | PASS |
Brandon Shaw
|
|
|
|
DOC - Permit Finaled | 2/24/2020 | 2/24/2020 | 2/24/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Conference | 4/10/2019 | 4/11/2019 | 4/11/2019 | A | PART |
Tony Young
|
|
|
I would like to meet on site and confer on some notes that plan review pointed out before we start the actual install. Give me a call on you way out and I''ll meet you there. 208.850.8965 I''ll have access to the house and garage set up. thanks guys, Ryan King Phone #: ###-#### Inspection requested via web by Ryan King// moving array around to land on the 2x8s ,, ok per engineer
|
Issue PAID IN FULL permit | | | 4/10/2019 | | DONE |
|
|
|
emailed ryank@evengreentechnology.com to sign building permit and send back
|
Plan assigned to (JAB) Josh | 2/27/2019 | 2/27/2019 | 4/3/2019 | | PASS |
Josh Bogle
|
|
|
3/5 PV, ePlan - 1st done
|
Routing - PLAN CHECK | 4/3/2019 | | 4/3/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 4/3/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/27/2019 | | 2/28/2019 | | FAIL |
Josh Bogle
|
|
|
no engineering or roof structure provided
|
1st review completed | | | 2/28/2019 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | | 2/27/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 27 2019 1:36PM
|
Routing - PLANNING | 2/27/2019 | | 2/27/2019 | | PASS |
Tiffany Carson-Herker
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/27/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/27/2019 | | DONE |
|
|
|
|
Intake Approval | | | 2/27/2019 | | PASS |
|
|
|
|