Third Notice | | 8/7/2019 | 8/5/2019 | | DONE |
|
|
|
This permit finaled on the web by Joseph knight
|
Second Notice | | 7/20/2019 | 8/2/2019 | | DONE |
|
|
|
mailed out 8/5/19
|
First Notice | | 6/30/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
Permanent Occupancy | | | 6/20/2019 | | DONE |
|
|
|
|
BLD-Final | 6/13/2019 | 6/13/2019 | 6/13/2019 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joseph knight
|
BLD-Final | 6/13/2019 | 6/13/2019 | 6/13/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joseph knight
|
FIRE-Final Inspection | 6/13/2019 | 6/13/2019 | 6/13/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete.
|
Zoning Approval | 6/13/2019 | 6/13/2019 | 6/13/2019 | | PASS |
KayCee Babb
|
|
|
Rooftop mechanical equipment not visible, complying with CZC19-00061.
|
BLD-Framing/Rough-in | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | PASS |
Jim Storey
|
|
|
Have revised set og plans showing no changes to the bathroom. Building closes at 3pm Phone #: ###-#### Inspection requested via web by Joseph knight final ok pending fire.
|
FIRE-Final Inspection | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | CANC |
Jim Page
|
|
|
Inspection request will be rescheduled to coincide with fire sprinkler inspection. This request is cancelled per conversation with point of contact.
Joe Phone #: ###-####
|
Inspection Record Card- Bld | | | 5/10/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/10/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/10/2019 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 5/8/2019 | 5/8/2019 | 5/9/2019 | | PASS |
Joe Bruce
|
|
|
(plan mod) Cardinal Health
|
Routing - PLAN CHECK | 5/9/2019 | | 5/9/2019 | | PASS |
Joe Bruce
|
|
|
|
Permit Ready to Issue | | | 5/9/2019 | | DONE |
|
|
|
PLAN MOD
|
Plan Modification Accepted | | | 5/8/2019 | | DONE |
|
|
|
Bathroom floorplan was updated to reflect correct orientation on the plan. no changes to the proposed work are being made
|
BLD-Ceiling Grid Inspection | 5/2/2019 | 5/3/2019 | 5/3/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joseph knight
|
BLD-Framing/Rough-in | 4/28/2019 | 4/29/2019 | 4/29/2019 | A | PART |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Joseph knight Inspection of Curb on roof for HVAC.....OK to cover.
|
Issue PAID IN FULL permit | | | 4/26/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/26/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 4/26/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/26/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/25/2019 | | DONE |
|
|
|
ALL MET-Need-
GC form
Revised certificate of value
|
Plan assigned to (JHB) | 3/28/2019 | 3/28/2019 | 4/24/2019 | | PASS |
Joe Bruce
|
|
|
(2nd Rev Comp) 04/10 (L2) Cardinal Health USP 797 ePlan
|
Plan resubmittals received | | | 4/24/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing - Design Review | 4/24/2019 | | 4/24/2019 | | PASS |
Katelyn Menuge
|
|
|
Per CZC19-00061. Screening to be nonreflective and painted or naturally finished in a neutral color that complements the existing building.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/24/2019 | | DONE |
|
|
|
|
Routing - Design Review | 4/15/2019 | | 4/16/2019 | | FAIL |
KayCee Babb
|
|
|
Rooftop screening for the new equipment is required, per CZC19-00061. Screening material, location, and dimensions are required for Design Review.
|
Plan resubmittals received | | | 4/15/2019 | | DONE |
Joe Bruce
|
|
|
|
Route to Impact Fee Review | 4/10/2019 | 4/13/2019 | 4/11/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 3/28/2019 | 3/28/2019 | 4/10/2019 | | PASS |
Mark Scharfen
|
|
|
IFC review 04.10.2019.pdf uploaded.
|
1st review completed | | | 4/10/2019 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 4/10/2019 | | DONE |
Joe Bruce
|
|
|
CZC Appeal Period to end on Friday, April 12 @ 5:00pm.
|
Routing - PLAN CHECK | 3/28/2019 | | 4/9/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing PW Environmental | 3/28/2019 | | 4/1/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLUMBING | 3/28/2019 | | 4/1/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - MECHANICAL | 3/28/2019 | | 3/29/2019 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 3/28/2019 | | 3/28/2019 | | FAIL |
KayCee Babb
|
|
|
Design Review approval is required. CZC19-00061 has been submitted, but is still under review. No DR approval has been issued yet and no appeal period has occurred.
|
Intake Approval | | | 3/28/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 3/28/2019 | | 3/28/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/28/2019 | | 3/28/2019 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 3/27/2019 | | FAIL |
Joe Bruce
|
|
|
03/27/2019 - Joe Bruce (Please address the items below) Please provide the following to complete you prescreen:
1) The structural engineering calculations are missing a stamp/signature by the engineer. Provide stamp/signature on the calculations.
2) Engineers stamp is not legible on sheet G001. Provide a legible stamp/signature on this sheet.
3) A majority of the plan sheets are missing a stamp/signature by the registered design professional. Please have ALL sheets stamped and signed by an engineer or architect.
4) New rooftop units require a certificate of zoning compliance including the air handling unit, condensing unit, and exhaust fan. Please contact Katelyn Menuge at ###-#### for more information on the application requirements. This certificate must be obtained prior to permit submittal.
5) Provide Form #310 - Statement of Special Inspections for the special inspections noted on sheet G002. The form can be downloaded from the City of Boise's website here: https://pds.cityofboise.org/media/104147/final310_special_inspections.pdf
6) Plan sheets (A501, A502, CRA-1, CRA-2, CRA-3, CRAD-1, CRM-1, CRM-2, CRM-3, and G004) do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” (4"x4" on cover) space located 3” off the right sheet edge to allow for the title block. Verify ALL plan sheets have the required space for city approval stamp. See electronic submittal standards at this link: https://pds.cityofboise.org/media/464072/pdox86_electronic_standards_full_050718.pdf
7) COMCheck reports are required to be signed and printed on the plans as stated in the checklist. Please place these forms on a plan sheet and upload into the "drawings" folder.
|
Intake Approval | | | 3/5/2019 | | FAIL |
Joe Bruce
|
|
|
Please provide the following to complete you prescreen:
1) The structural engineering calculations are missing a stamp/signature by the engineer. Provide stamp/signature on the calculations.
2) Engineers stamp is not legible on sheet G001. Provide a legible stamp/signature on this sheet.
3) A majority of the plan sheets are missing a stamp/signature by the registered design professional. Please have ALL sheets stamped and signed by an engineer or architect.
4) New rooftop units require a certificate of zoning compliance including the air handling unit, condensing unit, and exhaust fan. Please contact Katelyn Menuge at ###-#### for more information on the application requirements. This certificate must be obtained prior to permit submittal.
5) Provide Form #310 - Statement of Special Inspections for the special inspections noted on sheet G002. The form can be downloaded from the City of Boise's website here: https://pds.cityofboise.org/media/104147/final310_special_inspections.pdf
6) Plan sheets (A501, A502, CRA-1, CRA-2, CRA-3, CRAD-1, CRM-1, CRM-2, CRM-3, and G004) do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” (4"x4" on cover) space located 3” off the right sheet edge to allow for the title block. Verify ALL plan sheets have the required space for city approval stamp. See electronic submittal standards at this link: https://pds.cityofboise.org/media/464072/pdox86_electronic_standards_full_050718.pdf
7) COMCheck reports are required to be signed and printed on the plans as stated in the checklist. Please place these forms on a plan sheet and upload into the "drawings" folder.
|
Application received | | | 2/28/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 28 2019 2:45PM
|