Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-00658
StatusIssued
Name CM COMPANY
Site Address 3434 N BOGUS BASIN RD
Project NameHighlands Elementary School
Customer NumberCUP18-00088
ePlanReviewYes
Description
(HIGHLANDS ELEMENTARY SCHOOL) (Project Management Ron Hill) **WUI ZONE A REQUIREMENTS** **DEFERRED SUBMITTAL FOR BLEACHERS** Permit for the construction of a new single-story, 42,775 sq. ft. elementary school to replace the existing 26,247 sq ft school that is to be demolished. Work will include demolishing the existing building, removing existing modular classrooms, general site work, utilities and construction of the new building per the approved plans, attached engineering and any comments. Building includes 3,512 sq ft of equipment platform; NO storage is permitted in this area. Special inspections required per attached Form 310. This is a fully fire sprinklered and alarmed building for E fire area over 12,000 sq. ft. and building area increase. *JAR*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/4/20208/5/20208/5/2020APEND
DetailsTony Young
Josh *screened* Phone #: ###-####557,, temp occupancy ok
BLD-Conference8/4/20208/5/20208/4/2020ADONE
DetailsTony Young
Josh *screened* Phone #: ###-####557
BLD-Wall cover7/13/20207/14/20207/14/2020PPART
DetailsTony Young
SCREENED // Josh Phone #: ###-####// temp occupancy ok.. pending trades on full occ.,, contractor will deliver final letters of ok from engineers for records
PubWorks Occupancy Approval7/14/20207/14/20207/14/2020 DONE
DetailsTiffany Lowery
Zoning Approval Temp7/14/20207/14/20207/14/2020 DONE
DetailsDavid Moser
Current Planning for Temp C of O
CHANGE STATUS TO (ISS)  7/13/2020 DONE
NOT SHOWING WHY IN FNL STATUS. CONTRACOR CALLING IN FOR FINAL
FIRE-Final Inspection7/7/20207/8/20207/8/2020APASS
DetailsGreg Ruxton
Fire Life Safety inspection passed. Building inspector to verify main entry doors panic hardware is code compliant for egress and over rides electric strike card reader once system is fully operational.

Josh *screened* Phone #: ###-####
BLD-Ceiling Grid Inspection6/30/20206/30/20206/30/2020PPASS
DetailsTony Young
Josh Phone #: ###-####.. kitchen and restrooms ok
BLD-Aging Inspection6/18/20206/18/20206/24/2020 PASS
DetailsTony Young
BLD-Aging Inspection6/17/20206/17/20206/24/2020 PASS
DetailsTony Young
BLD-Ceiling Grid Inspection5/11/20205/11/20205/11/2020PPASS
DetailsDave Hannah
Josh *screened* Phone #: ###-####
BLD-Ceiling Grid Inspection4/1/20204/2/20204/2/2020APASS
DetailsTony Young
Josh Phone #: ###-####
BLD-Ceiling Grid Inspection3/30/20203/30/20203/30/2020PPASS
DetailsJim Storey
Josh Phone #: ###-#### area b ok
BLD-Framing/Rough-in2/3/20202/4/20202/4/2020APASS
DetailsTony Young
Josh Phone #: ###-####,, kitchen areas ok
BLD-Energy code compliance1/21/20201/21/20201/21/2020PPART
DetailsTony Young
Josh Phone #: ###-####// area C ok pending trades
FIRE-Conference1/15/20201/16/20201/16/2020ACANC
DetailsJim Page
Josh ###-####
FIRE-Conference1/15/20201/15/20201/15/2020PDONE
DetailsJim Page
Follow up conference scheduled for 16JAN2020 for question asked about attic sprinkler coverage, need further verification for sprinkler head coverage in question.

Josh Phone #: ###-####
BLD-Energy code compliance1/7/20201/7/20201/7/2020PPART
DetailsDave Hannah
Josh Phone #: ###-#### ext walls west wing ok
BLD-Framing/Rough-in12/31/201912/31/201912/31/2019PPART
DetailsTony Young
Josh Phone #: ###-####// n/west area wing ok to insulate
BLD-Energy code compliance12/26/201912/27/201912/27/2019APART
DetailsTony Young
Josh Phone #: ###-####,, east wing ok
BLD-Framing/Rough-in12/20/201912/20/201912/20/2019PPART
DetailsDave Hannah
jOSH Phone #: ###-#### area ( B ) ok to insulate.
BLD-Conference12/10/201912/10/201912/10/2019PPART
DetailsTony Young
Josh Phone #: ###-####,, interior shear,, roof details, roof insulation,, extensive walk through,, Josh will note on plans
BLD-Other11/22/201911/22/201911/22/2019PPART
DetailsTony Young
roof nailing // Josh Phone #: ###-####,, work in progress,, ok
BLD-Framing/Rough-in11/19/201911/20/201911/20/2019PPART
DetailsTony Young
Josh Phone #: ###-####// area C wall bracing ok
BLD-Other11/7/201911/8/201911/8/2019PPART
DetailsTony Young
roof nailing // Josh Phone #: ###-####,, ok after re-nailing missed areas marked by paint,, north/west building
BLD-Wall Bracing11/7/201911/8/201911/8/2019APART
DetailsTony Young
north buildings // Josh Phone #: ###-####,, work in progress,, ok to cover after finishing
BLD-Other11/6/201911/7/201911/7/2019PPART
DetailsTony Young
roof nailing // Josh Phone #: ###-####,, partial on area A,, need to redo some and finish upper areas
BLD-Other10/30/201910/31/201910/31/2019PPART
DetailsTony Young
roof nailing // Josh Phone #: ###-####,, area B and the gym ok
BLD-Conference10/22/201910/22/201910/22/2019PPASS
DetailsTony Young
Josh - Framing questions, wanted a consultation Phone #: ###-####,, fireblock ?s, bracing ?s
BLD-Foundation10/1/201910/1/201910/1/2019PPEND
DetailsTony Young
rebar // Josh Phone #: ###-####,, pending special inspection
BLD-Other9/26/20199/27/20199/27/2019PPEND
DetailsTony Young
2pm - grout and rebar // Josh Phone #: ###-####
BLD-Other9/23/20199/24/20199/24/2019APART
DetailsTony Young
grout // Josh Phone #: ###-####,, pending special inspection
BLD-Footing9/16/20199/17/20199/17/2019APART
DetailsTony Young
rebar // Josh Phone #: ###-####,, pending special inspection results
BLD-Foundation9/11/20199/11/20199/11/2019PPART
DetailsTony Young
rebar // josh Phone #: ###-####,, pending special inspection
BLD-Footing9/6/20199/6/20199/6/2019PPART
DetailsTony Young
Josh Phone #: ###-####,, pending special inspection reports
BLD-Footing9/5/20199/6/20199/6/2019APART
DetailsTony Young
Josh Phone #: ###-####,, area C
BLD-Footing8/28/20198/29/20198/29/2019PPEND
DetailsTony Young
Josh- rebar inspection and footing wall Phone #: ###-####,, pending special inspection report
BLD-Foundation8/21/20198/22/20198/22/2019APEND
DetailsTony Young
wall rebar // Josh Phone #: ###-####,, special inspection
BLD-Concrete8/20/20198/20/20198/20/2019PPART
DetailsTony Young
rebar-Josh Phone #: ###-####
BLD-Foundation8/19/20198/20/20198/20/2019APART
DetailsTony Young
foundation insulation // Josh Phone #: ###-####,, work oin progress,, special inspector reports
BLD-Foundation8/14/20198/15/20198/15/2019PPART
DetailsTony Young
Josh Phone #: ###-####,, stem wall,, pending special inspection reports
BLD-Foundation8/8/20198/9/20198/9/2019APEND
DetailsTony Young
rebar // Izaak Phone #: ###-####,, pending S, I. report
BLD-Footing8/6/20198/7/20198/8/2019PPART
DetailsTony Young
rebar // Issac Phone #: ###-####.. special inspector to be on site
BLD-Foundation8/6/20198/6/20198/6/2019PPART
DetailsTony Young
rebar // Issac Phone #: ###-####,, pending special inspection report,, not pouring until Thursday
BLD-Foundation7/31/20198/1/20198/1/2019PPART
DetailsTony Young
rebar // Josh Phone #: ###-####,, grid L and 3,, s/w gym area, deep footings,, pending special reports,, MTI
Issue PAID IN FULL permit  6/28/2019 DONE
Print Occupancy Form  6/28/2019 DONE
Telephone call  6/27/2019 DONE
customer came in to pick up permit but all fees had not been paid. Gave him the fees due so he could give it to the school dist
OVERRIDE  5/16/2019  
Plan assigned to (JAR)3/21/20193/21/20195/16/2019 DONE
DetailsJulie Romig
05/16 - 4th Rev - 1st Rev Comp - 502 Highlands Elementary - **Expedited Review**
Routing - PLAN CHECK5/10/2019 5/16/2019 PASS
DetailsJulie Romig
4th Review
PLANS/APPL TAKEN TO FRONT DESK  5/16/2019 DONE
Permit Ready to Issue  5/16/2019 DONE
NEED
ACHD

MET (ROBH@CMCOMPANY.COM)
GC FORM
REVISED VALUE (SCHOOL PROJECT DON'T GO OVER STATES PLAN CHECK FEE)
Routing - ELECTRICAL5/10/2019 5/13/2019 PASS
DetailsJavier Guzman
4th Review
Routing - FIRE5/1/20195/1/20195/7/2019 PASS
DetailsErika Akin
Attached comments to case
Routing - PLAN CHECK5/1/2019 5/7/2019 FAIL
DetailsJulie Romig
Corrections required per ePlanReview. Contacted applicant to discuss.
Routing - ELECTRICAL5/1/2019 5/3/2019 FAIL
DetailsJavier Guzman
Previous changemark request not addressed emailed applicant to try and resolve.
Routing PW Sewer Design5/1/2019 5/2/2019 PASS
DetailsDeAnn Brown
Routing - PLAN CHECK4/18/2019 4/25/2019 FAIL
DetailsJulie Romig
Routing PW Drainage4/18/2019 4/25/2019 PASS
DetailsBrian Murphy
Routing - FIRE4/17/20194/17/20194/24/2019 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Routing - ELECTRICAL4/17/2019 4/24/2019 FAIL
DetailsJavier Guzman
Previous changemark request not addressed.
Routing Off Site - STRUCTURAL4/18/2019 4/22/2019 PASS
DetailsJulie Romig
KPFF
Routing PW Sewer Design4/18/2019 4/18/2019 FAIL
DetailsDeAnn Brown
See changemarks on sheet C2 (demo) and C5 (utility).
Route to Impact Fee Review4/8/20194/11/20194/9/2019 PASS
DetailsKarina Myles
Review requested for Commercial Permit
1st review completed  4/8/2019 FAIL
DetailsJulie Romig
Routing Off Site - STRUCTURAL3/21/2019 4/8/2019 FAIL
DetailsJulie Romig
KPFF
Routing PW Flood Plain3/26/2019 4/5/2019 PASS
DetailsJason C. Taylor
Project is outside Special Flood Hazzard Area, no floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
Routing - FIRE3/21/20193/21/20194/3/2019 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Routing - PLAN CHECK3/21/2019 4/3/2019 FAIL
DetailsJulie Romig
Routing - ELECTRICAL3/21/2019 4/2/2019 FAIL
DetailsJavier Guzman
04/03 - **Expedited Review ** - 502 Highlands Elementary
Routing PW Environmental3/26/2019 4/1/2019 PASS
DetailsRick Christenson
Routing PW Drainage3/26/2019 3/28/2019 FAIL
DetailsBrian Murphy
need perc test soils
Routing PW Street Lights3/26/2019 3/28/2019 PASS
DetailsTom Marshall
Routing - PLANNING3/21/2019 3/28/2019 PASS
DetailsDavid Moser
Routing PW Sewer Design3/26/2019 3/27/2019 FAIL
DetailsDeAnn Brown
See changemarks. Manholes need labeling, show existing service connections on demo plan, finish label for sewer services, add tap permit notes.
Routing - MECHANICAL3/21/2019 3/27/2019 PASS
DetailsTroy James
Routing PW Solid Waste3/26/2019 3/27/2019 PASS
DetailsEvan Carpenter
Routing - PLUMBING3/21/2019 3/26/2019 PASS
DetailsDaryl Spivey
04/03 - **Expedited Review ** - 502 Highlands Elementary
Per plan and ISPC.
Routing - Addressing3/21/2019 3/26/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS3/21/2019 3/26/2019 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment3/21/2019 3/26/2019 PASS
DetailsMichael Zawacki
Pre construction SWPPP. Still needs RP and all responsible parties added.
Site prep will be required.
Intake Approval  3/21/2019 PASS
DetailsCarl Westfall
Prescreen approved/fees paid 3/21/19
Plan Reviewer's activity  3/20/2019 PASS
Plan intake review approved
Intake Approval  3/12/2019 FAIL
Have not done a plan intake review because the filled out Form 502 Plan Intake Checklist has not been uploaded into the Documents Folder in ePlanReview. Upload the document and complete your task so that the Plan Intake review can be done.
Intake Approval  3/12/2019 FAIL
3-12-19 Refer to the circled item in the plan intake checklist. Resolve each item as directed. CJW
Intake Approval  3/7/2019 FAIL
Fill out and upload the 502 plan intake checklist into the Documents Folder in ePlanReview. Upload spec book 1 if there is one. “ehvejhdo.4xl” did not upload. Try again with a different file name. The 6 week timeframe for 1st review does not start until the plan intake review is approved and the plan review fee is paid. To avoid further delays, make sure everything that is required in the check list is uploaded. CJW
Application received  3/4/2019 DONE
Application submitted via PDS Online on Mar 4 2019 8:57AM