Third Notice | | 1/4/2020 | 2/6/2020 | | DONE |
|
|
|
mailed 2-7-20 with third and final letter
|
Third Follow up | | | 2/6/2020 | | DONE |
|
|
|
final letter
|
Third Notice | | 12/2/2019 | 12/30/2019 | | DONE |
|
|
|
mailed 1-1-20 with second follow up
|
Second Follow up | | | 12/30/2019 | | DONE |
|
|
|
|
Third Notice | | 11/3/2019 | 11/27/2019 | | DONE |
|
|
|
mailed 12-2-19 with first follow up
|
First Follow up | | | 11/27/2019 | | DONE |
|
|
|
|
Third Notice | | 9/23/2019 | 10/29/2019 | | DONE |
|
|
|
mailed 11-1
|
Third Notice | | 8/18/2019 | 9/18/2019 | | DONE |
|
|
|
mailed 9-19-19
|
Second Notice | | 7/20/2019 | 8/13/2019 | | DONE |
|
|
|
mailed 8-14
|
First Notice | | 6/3/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
BLD-Final | 5/23/2019 | 5/24/2019 | 5/24/2019 | A | PASS |
Jim Storey
|
|
|
John Phone #: ###-####
|
Permanent Occupancy | | | 5/24/2019 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/17/2019 | 5/17/2019 | 5/17/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguishers are placed with current inspection tags. Door handle between break room area to corridor to be changed before final BLD inspection, lock in the path of travel to be removed/changed. Final life fire safety inspection complete.
Call ahead // Jon Phone #: ###-####
|
BLD-Wall Bracing | 4/23/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Jim Storey
|
|
|
John Phone #: ###-#### backing ok restarooms
|
BLD-Framing/Rough-in | 4/2/2019 | 4/3/2019 | 4/3/2019 | P | PASS |
Jim Storey
|
|
|
John Phone #: ###-#### stud framing ok to cover/pending backing restarooms.
|
Issue PAID IN FULL permit | | | 4/2/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/2/2019 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 3/8/2019 | 3/8/2019 | 4/1/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 03/18/19 (L2 - 7 days) (ePlan - 9 sheets) Tobacco Connection (routed back to applicant)
|
Routing - PLAN CHECK | 3/26/2019 | | 4/1/2019 | | PASS |
Carl Westfall
|
|
|
Drawings approved after the resubmittal review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/1/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/1/2019 | | DONE |
|
|
|
Need GC
Need Rev Val
|
Plan resubmittals received | | | 3/26/2019 | | DONE |
|
|
|
Came in on a Tuesday. The Plans Examiner was on vacation through Friday. Did the resubmittal review on the following Monday when he got back.
|
Route to Impact Fee Review | 3/22/2019 | 3/25/2019 | 3/25/2019 | | PASS |
Karina Myles
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 3/8/2019 | 3/8/2019 | 3/22/2019 | | PASS |
Mark Scharfen
|
|
|
03/22 Tabbacco Connection TI
|
1st review completed | | | 3/22/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 3/22/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/8/2019 | | 3/20/2019 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - MECHANICAL | 3/8/2019 | | 3/13/2019 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 3/8/2019 | | 3/12/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Addressing | 3/8/2019 | | 3/11/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PLUMBING | 3/8/2019 | | 3/11/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 3/8/2019 | | PASS |
Michael Hanson
|
|
|
Prescreen approved by Michael Hanson.
|
Intake Approval | | | 3/5/2019 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following:
1. Provide #518 checklist completed, item locations listed, signed and dated.
2. Provide fire extinguisher locations.
3. Provide structural engineering or letter from Idaho registered structural engineer for which demonstrates structural capacity in existing structure for new mechanical work.
4. Provide #310 Special inspections form for onsite welding of structural component.
|
Application received | | | 3/4/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 4 2019 1:40PM
|