Permanent Occupancy | | | 3/13/2019 | | DONE |
|
|
|
|
Permanent Occupancy | | | 3/13/2019 | | DONE |
|
|
|
|
BLD-Final | 3/8/2019 | 3/12/2019 | 3/12/2019 | P | PASS |
Mike Jordan
|
|
|
Emily Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 3/11/2019 | 3/12/2019 | 3/12/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Smoke evac system functioned.
Emily Phone #: ###-####
|
FIRE-Final Inspection | 3/8/2019 | 3/11/2019 | 3/11/2019 | P | FAIL |
Troy Cobbley
|
|
|
Need the smoke evac system tested and the racks that exceed 8' in height addressed as per conversation.
Emily Phone #: ###-####
|
Plan Reviewer's activity | | | 3/11/2019 | | |
Brian McGowan
|
|
|
Returned Emily's call letting her know that there should be an existing permit or a new permit must be obtained for the racking.
|
Permit Ready to Issue | | | 3/8/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/8/2019 | | DONE |
|
|
|
|
Telephone call | | | 3/8/2019 | | DONE |
|
|
|
called Mark to let know permit is ready
|
Issue PAID IN FULL permit | | | 3/8/2019 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 3/4/2019 | 3/4/2019 | 3/7/2019 | | DONE |
Brian McGowan
|
|
|
03/08 (#528) Attic Salt
|
Routing - PLAN CHECK | 3/6/2019 | | 3/7/2019 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 3/7/2019 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 3/7/2019 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/7/2019 | | DONE |
Brian McGowan
|
|
|
|
Routing - PUBLIC WORKS | | | 3/6/2019 | | PASS |
|
|
|
|
Routing - Addressing | 3/4/2019 | | 3/5/2019 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 3/4/2019 | | PASS |
Brian McGowan
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/4/2019 | | DONE |
|
|
|
|
First Notice | | 3/23/2019 | | | |
|
|
|
|
First Notice | | 3/23/2019 | | | |
|
|
|
|
Application received | | 3/4/2019 | | | |
|
|
|
|