BLD-Final | 6/4/2020 | 6/5/2020 | 6/5/2020 | P | PASS |
Mike Jordan
|
|
|
screened // Rachael Phone #: ###-####
|
DOC - Permit Finaled | 6/5/2020 | 6/5/2020 | 6/5/2020 | P | PASS |
Mike Jordan
|
|
|
All issues resolved. Driveway and fire apperatus turn around have been paved and is per plan.
|
BLD-Final | 5/28/2020 | 5/29/2020 | 5/29/2020 | P | FAIL |
Tell Riley
|
|
|
Racheal Phone #: ###-####//CN issued//need address posted on home//need landing at exterior garage door// switch smoke and combo detector locations in hall//provide zoning approval of gravel drive and no hard surface at front//provide fire approval of entrance and turnaround area//
|
Routing - MECHANICAL | 5/28/2020 | | 5/28/2020 | | PASS |
Troy James
|
|
|
Resubmitted ACCA report
|
BLD-Framing/Rough-in | 1/26/2020 | 1/27/2020 | 1/27/2020 | A | PASS |
Mike Jordan
|
|
|
Call with any questions. Thanks! Phone #: ###-#### Inspection requested via web by Rachael Moore. All issues resolved. ok to cover.
|
BLD-Framing/Rough-in | 1/23/2020 | 1/24/2020 | 1/24/2020 | A | FAIL |
Mike Jordan
|
|
|
Call with any questions. Thanks! Phone #: ###-#### Inspection requested via web by Rachael Moore. Complete LAteral bracing on A2,A3,A4,A5,A6,A9,A11,A12,A13,A14 and A15 trusses. Nail 2ply A10 truss per the engineering. Correction notice posted. Do not sheet rock.
|
BLD-Framing/Rough-in | 1/14/2020 | 1/15/2020 | 1/15/2020 | A | FAIL |
Mike Jordan
|
|
|
Call with any questions, thanks! Phone #: ###-#### Inspection requested via web by Rachael Moore. Caulk sill plates at exterior walls to concrete. Provide pressure treated bottom plate to concrete floor at interior wall. Provide truss engineering. Correction notice posted. ok to insulate.
|
BLD-Other | 10/22/2019 | 10/23/2019 | 10/23/2019 | A | PASS |
Mike Jordan
|
|
|
Wall bracing/sheeting re-inspect Phone #: ###-#### Inspection requested via web by Rachael Moore
|
BLD-Other | 9/16/2019 | 9/18/2019 | 9/18/2019 | A | FAIL |
Mike Jordan
|
|
|
Wall bracing/sheathing Phone #: ###-#### Inspection requested via web by Rachael Moore. Attach missed areas, provide 6ft. shear panel in garage as noted on plans.
|
BLD-Foundation | 4/8/2019 | 4/9/2019 | 4/9/2019 | A | PART |
Mike Jordan
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Rachael Moore
|
BLD-Footing | 3/28/2019 | 3/28/2019 | 3/28/2019 | P | NR |
Jim Sly
|
|
|
Late afternoon if possible please. Please call Dan at listed number. Same site as BLD19-00699 inspection request. Phone #: ###-#### Inspection requested via web by Rachael Moore
|
Issue PAID IN FULL permit | | | 3/22/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/22/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 3/21/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 3/14/2019 | 3/14/2019 | 3/21/2019 | | DONE |
Jenny Nelson
|
|
|
1st complete 3/14, headers with girder truss loads, garage beam, update code year
|
Routing - PLAN CHECK | 3/21/2019 | | 3/21/2019 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 3/21/2019 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 3/11/2019 | 3/11/2019 | 3/14/2019 | | DEFR |
Brian McGowan
|
|
|
03/22 (L1, sfd) ePlan
|
Routing - PLAN CHECK | 3/11/2019 | | 3/14/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 3/11/2019 | | 3/14/2019 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 3/14/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Route to Impact Fee Review | 3/11/2019 | 3/14/2019 | 3/12/2019 | | PASS |
Karina Myles
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 3/11/2019 | | 3/12/2019 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 3/11/2019 | | 3/12/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/11/2019 | | 3/12/2019 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/11/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/11/2019 | | DONE |
|
|
|
|
Intake Approval | | | 3/11/2019 | | PASS |
|
|
|
|
Intake Approval | | | 3/6/2019 | | FAIL |
|
|
|
File names need ot be A2.0_Floor plan
Need to show location of crawlspace and size
Show crawlspace venting
|
Application received | | | 3/5/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 5 2019 7:33PM
|