BLD-Final | 6/4/2020 | 6/5/2020 | 6/5/2020 | P | PASS |
Mike Jordan
|
|
|
screened // Rachael Phone #: ###-####
|
DOC - Permit Finaled | 6/5/2020 | 6/5/2020 | 6/5/2020 | P | PASS |
Mike Jordan
|
|
|
All issues resolved. Driveway and fire apperatus turnaround have been paved and are per approved plan.
|
BLD-Final | 5/28/2020 | 5/29/2020 | 5/29/2020 | P | FAIL |
Tell Riley
|
|
|
Racheal Phone #: ###-####//CN issued//need address posted on home//need landing at exterior garage door//provide zoning approval of gravel drive and no hard surface at front//provide fire approval of entrance and turnaround area//
|
Routing - MECHANICAL | 5/28/2020 | | 5/28/2020 | | PASS |
Troy James
|
|
|
Resubmitted ACCA report
|
BLD-Framing/Rough-in | 2/10/2020 | 2/11/2020 | 2/11/2020 | A | PASS |
Mike Jordan
|
|
|
Final framing inspection for cover. Call with any questions. Thanks! Phone #: ###-#### Inspection requested via web by Rachael Moore. All issues have been resolved.
|
BLD-Energy code compliance | 2/11/2020 | 2/11/2020 | 2/11/2020 | A | PASS |
Mike Jordan
|
|
|
Final framing inspection for cover. Call with any questions. Thanks! Phone #: ###-#### Inspection requested via web by Rachael Moore
|
BLD-Framing/Rough-in | 2/9/2020 | 2/10/2020 | 2/10/2020 | P | DONE |
Mike Jordan
|
|
|
Call to meet to go over truss build. Thanks! Phone #: ###-#### Inspection requested via web by Rachael Moore
|
BLD-Framing/Rough-in | 2/7/2020 | 2/7/2020 | 2/7/2020 | A | FAIL |
Mike Jordan
|
|
|
Framing and rough in and reinspect for bracing hold downs. Please call with any questions. Thanks! Phone #: ###-#### Inspection requested via web by Rachael Moore. Fire block around duct work at ceiling. Provide additional 2x6 studs under 3 ply CG1 truss. Install straps at portal frame. Provide hangar for 2ply A8 truss. Provide addtional 2x studs in garage at beam. Install h2.5 on trusses. Complete lateral bracing on A8 truss. Provide truss repair for missed bearing on trusses at west wall at fron patio cover. Correction notice posted. ok to insulate.
|
Routing - MECHANICAL | 1/3/2020 | | 1/3/2020 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Conference | 10/22/2019 | 10/23/2019 | 10/23/2019 | A | PART |
Mike Jordan
|
|
|
Wall bracing/sheeting Phone #: ###-#### Inspection requested via web by Rachael Moore. Needs to install the missing hold downs on south end of house as noted on the approved plans. Ok to cover the exterior.
|
BLD-Foundation | 4/8/2019 | 4/9/2019 | 4/9/2019 | A | PART |
Mike Jordan
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Rachael Moore
|
BLD-Concrete | 3/29/2019 | 4/1/2019 | 4/1/2019 | A | PART |
Mike Jordan
|
|
|
Dan Phone #: ###-####
|
BLD-Footing | 3/28/2019 | 3/28/2019 | 3/28/2019 | P | NR |
Jim Sly
|
|
|
Late afternoon if possible please. Please call Dan at listed number. Same site as BLD19-00698 inspection request. Phone #: ###-#### Inspection requested via web by Rachael Moore
|
Issue PAID IN FULL permit | | | 3/22/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/22/2019 | | DONE |
|
|
|
|
Plan assigned to (J_N) | 3/6/2019 | 3/6/2019 | 3/21/2019 | | DONE |
Jenny Nelson
|
|
|
03/19 sfd L1 ePlan. 1st complete 3/11, structural deficiencies, code year, wind speed
|
Routing - PLAN CHECK | 3/21/2019 | | 3/21/2019 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 3/21/2019 | | DONE |
|
|
|
|
Routing - FIRE | 3/11/2019 | 3/11/2019 | 3/11/2019 | | PASS |
Lee G Meredith
|
|
|
03/19 SFD L1 EPlan Flag Lot.
Approved per Ron Johnson.
3-14-19 Rachael Moore emailed to state the driveway will be compacted and finished to a minimum weight rating of 75,000 pounds.
|
Plan Reviewer's activity | | | 3/11/2019 | | DONE |
|
|
|
Per Ron Johnson, passed as is anticipated that more hydrants are expected in the near future that will be within 600 feet.
|
1st review completed | | | 3/11/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 3/6/2019 | | 3/11/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Route to Impact Fee Review | 3/6/2019 | 3/9/2019 | 3/7/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 3/6/2019 | | 3/7/2019 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 3/6/2019 | | 3/7/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/6/2019 | | 3/6/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/6/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/6/2019 | | DONE |
|
|
|
|
Intake Approval | | | 3/6/2019 | | PASS |
|
|
|
|
Routing - PLANNING | 3/6/2019 | | 3/6/2019 | | PASS |
Sue Cummings
|
|
|
|
Application received | | | 3/5/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 5 2019 7:38PM
|