BLD-Wall Bracing | 4/2/2020 | 4/6/2020 | 4/6/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Fink
|
BLD-Foundation | 3/2/2020 | 3/2/2020 | 3/2/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress... Column, back patio/deck...
|
BLD-Concrete | 2/27/2020 | 2/28/2020 | 3/2/2020 | P | NR |
Dave Hannah
|
|
|
Concrete wall rebar inspection. This is the last element of structural concrete on this project. Phone #: ###-#### Inspection requested via web by Bob Fink still working on rebar
|
BLD-Foundation | 1/7/2020 | 1/7/2020 | 1/7/2020 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Foundation | 1/6/2020 | 1/7/2020 | 1/7/2020 | A | CANC |
Brandon Shaw
|
|
|
Partial foundation inspection. Phone #: ###-#### Inspection requested via web by Bob Fink
|
BLD-Foundation | 12/20/2019 | 12/23/2019 | 12/23/2019 | P | CANC |
Brandon Shaw
|
|
|
BOB FINK CANCEL INSPECTION// Partial foundation inspection. Phone #: ###-#### >> Inspection requested via web by Bob Fink
|
BLD-Foundation | 12/15/2019 | 12/16/2019 | 12/16/2019 | P | PASS |
Brandon Shaw
|
|
|
Partial foundation inspection Work in progress... Frost protection is required...
|
BLD-Foundation | 12/13/2019 | 12/16/2019 | 12/15/2019 | A | CANC |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Bob Fink Inspection cancelled from web by: Bob Fink
|
BLD-Foundation | 11/22/2019 | 11/25/2019 | 11/25/2019 | P | PASS |
Brandon Shaw
|
|
|
Frost protection is required...
|
BLD-Footing | 10/21/2019 | 10/22/2019 | 10/22/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
PubWorks Subgrade Approval | 10/2/2019 | 10/2/2019 | 10/2/2019 | | DONE |
Melissa Jannusch
|
|
|
*FOOTINGS, RETAINING WALL, SLAB* A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 8/30/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/30/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 7/25/2019 | | |
|
|
|
|
Routing - FIRE | 7/25/2019 | 7/25/2019 | 7/25/2019 | | PASS |
Lee G Meredith
|
|
|
07/31-Rolph Residence resubmittal LGM
7/25/19 Revised index sheet states that an NFPA 13D sprinkler system will be provided.
|
Plan assigned to (BJM) | 3/15/2019 | 3/15/2019 | 7/25/2019 | | DONE |
Brian McGowan
|
|
|
2nd Review Complete - 04/03 (L2 sfd) ePlan
|
Routing - PLAN CHECK | 7/25/2019 | | 7/25/2019 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/25/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/25/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/20/2019 | | 5/20/2019 | | FAIL |
Brian McGowan
|
|
|
Must Pass FIRE. Need roofing specifications
|
Routing - MECHANICAL | 5/8/2019 | | 5/8/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - FIRE | 5/7/2019 | 5/7/2019 | 5/7/2019 | | FAIL |
Lee G Meredith
|
|
|
Document provided by SUEZ indicates that fire flow is inadequate. 2250 gpm is required but on 2000 gpm is available for a limited duration of 90 minutes. Resubmittal required.
|
Routing - PLANNING | 5/7/2019 | | 5/7/2019 | | PASS |
Nicolette Womack
|
|
|
|
1st review completed | | | 4/3/2019 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 3/15/2019 | | 4/3/2019 | | FAIL |
Brian McGowan
|
|
|
|
Routing PW Grading-Hillside | 3/15/2019 | | 3/25/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.
|
Route to Impact Fee Review | 3/15/2019 | 3/18/2019 | 3/18/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | 3/15/2019 | 3/15/2019 | 3/18/2019 | | FAIL |
Lee G Meredith
|
|
|
04/29 Rolph Residence Hillside.
SUEZ Fire Flow Availability report not provided. Access distance exceeds 150. Sprinklers may be required.
|
Routing - Erosion and Sediment | 3/15/2019 | | 3/18/2019 | | PASS |
Michael Zawacki
|
|
|
Foothills lot, site prep inspection required.
|
Routing - PLANNING | 3/15/2019 | | 3/18/2019 | | PASS |
Nicolette Womack
|
|
|
|
Routing - Addressing | 3/15/2019 | | 3/15/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/15/2019 | | 3/15/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 3/15/2019 | | 3/15/2019 | | FAIL |
Troy James
|
|
|
See eplan for corrections
|
Plans ACCEPTED BY PLAN TECH | | | 3/15/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/15/2019 | | DONE |
|
|
|
|
Intake Approval | | | 3/15/2019 | | PASS |
|
|
|
|
Intake Approval | | | 3/11/2019 | | FAIL |
|
|
|
1. Please label A/C and Furnace locations.
2. Please provide HVAC equipment schedule (example brand of furnace information)
3. Please upload the most recent civil set for grading and drainage plans (ABCO Engineering dated January 22, 2019) prior to acceptance for building permit review MMJ ###-####
|
Application received | | | 3/6/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 6 2019 2:14PM
|
Expiration Notice | 8/14/2019 | 9/5/2019 | | | |
|
|
|
|