Second Notice | | 11/8/2019 | 11/12/2019 | | DONE |
|
|
|
This permit finaled on the web by Scott Asin
|
First Notice | 9/13/2019 | 9/13/2019 | 10/29/2019 | | DONE |
Brandon Shaw
|
|
|
mailed 11-1
|
Permanent Occupancy | | | 9/16/2019 | | DONE |
|
|
|
|
BLD-Final | 9/13/2019 | 9/13/2019 | 9/13/2019 | P | PASS |
Brandon Shaw
|
|
|
Tod Phone #: ###-####
|
DOC - Permit Finaled | 9/13/2019 | 9/13/2019 | 9/13/2019 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 9/13/2019 | 9/13/2019 | 9/13/2019 | P | PASS |
Jim Page
|
|
|
Scope of work has been completed, no fire sprinklers, no fire alarms, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.
Tod Phone #: ###-####
|
DOC - Permit Finaled | 9/13/2019 | 9/13/2019 | 9/13/2019 | P | PASS |
Brandon Shaw
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/13/2019 | | DONE |
|
|
|
Per Brandon. this shouldn't have been final out.
|
Print Occupancy Form | | | 9/13/2019 | | DONE |
|
|
|
email 2nd inspection card to - royalcocktailco@gmail.com
|
BLD-Aging Inspection | 8/21/2019 | 8/21/2019 | 8/22/2019 | | PEND |
Tony Young
|
|
|
|
Temporary Occupancy | 6/24/2019 | 9/22/2019 | 6/24/2019 | | DONE |
Brittany Hill
|
|
|
|
Zoning Approval | 6/24/2019 | 6/24/2019 | 6/24/2019 | | DONE |
Ted Vanegas
|
|
|
|
BLD-Final | 6/21/2019 | 6/21/2019 | 6/21/2019 | P | PART |
Tony Young
|
|
|
Dale Phone #: ###-####,,temp occupancy ok,, needs final engineer letter,, full pass of trades, patio
|
Telephone call | | | 6/20/2019 | | DONE |
|
|
|
call came from GC-there is no PLM permit for the TI-PLM19-00866 is for the core & shell only-i told GC that he will need to get with Buss and get a permit pulled for both building permits before they can call in the building final
|
FIRE-Final Inspection | 6/18/2019 | 6/18/2019 | 6/18/2019 | P | PART |
Jim Page
|
|
|
Partial final for life fire safety inspection complete. No fire sprinklers, no fire alarms, fire exitnguishers are placed with a current inspection tags. A 90 day TCO is auhtorized for life fire safety inspection per conversation with Ron Johnson with Boise Fire contingent on the core and shell permit being finaled (BLD18-04579).
|
Issue PAID IN FULL permit | | | 4/12/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/12/2019 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 3/13/2019 | 3/13/2019 | 4/8/2019 | | PASS |
Joe Bruce
|
|
|
04/12 (2nd Rev) 04/04 (L3) Hyde Park Bar, ePlan (Plan)
|
Plan resubmittals received | | | 4/8/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 4/8/2019 | | 4/8/2019 | | PASS |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/8/2019 | | DONE |
|
|
|
Need GC
Need Rev cert of val
|
Route to Impact Fee Review | 4/4/2019 | 4/7/2019 | 4/5/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 4/4/2019 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 4/4/2019 | | DONE |
Joe Bruce
|
|
|
Emailed plan review report to Architect.
|
Routing - PLAN CHECK | 3/13/2019 | | 4/4/2019 | | FAIL |
Joe Bruce
|
|
|
|
Routing - FIRE | 3/13/2019 | 3/13/2019 | 4/3/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Review 04.03.2019.pdf uploaded.
|
Routing Off Site - C.D.H | 3/13/2019 | | 3/18/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing PW Environmental | 3/14/2019 | | 3/18/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 3/13/2019 | | 3/18/2019 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 3/13/2019 | | 3/15/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - Design Review | 3/13/2019 | | 3/15/2019 | | PASS |
Ted Vanegas
|
|
|
|
Routing - PUBLIC WORKS | 3/13/2019 | | 3/14/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 3/13/2019 | | 3/14/2019 | | PASS |
Michael Zawacki
|
|
|
TI, no ESC required. ESC plan provided.
|
Routing - PLANNING | 3/13/2019 | | 3/14/2019 | | PASS |
Nicolette Womack
|
|
|
|
Routing - PLUMBING | 3/13/2019 | | 3/13/2019 | | PASS |
Daryl Spivey
|
|
|
Install DCVA's on water service unless required drainage is installed to accomodate RPBP's.
|
Intake Approval | | | 3/8/2019 | | PASS |
|
|
|
|
Application received | | | 3/7/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 7 2019 11:04AM
|