Information based on query as of Wednesday, August 14, 2024.
Permit Information
Permit NumberBLD19-00723
StatusFinaled
Name FORTE CONSTRUCTION SERVICES LLC
Site Address 3510 E VIA ESTANCIA LN
Project NameReifschneider Residence
Customer Number 
ePlanReviewYes
Description
**PLAN MODIFICATION - updating drainage and redesigning front retaining wall - now double retaining wall. JJN 12-2-19** **HILLSIDE** **WUI VALLEY PERIMETER ZONE A REQUIREMENTS** **PASSES USING UA TRADE OFF** **310 SPECIAL INSPECTIONS** Permit for the construction of a new 3,320 sq. ft., two story (first story 2,945 sq. ft., below grade 375 sq. ft.) single family dwelling with 2 bedrooms, 2.5 bathrooms, approximately 53 sq. ft. of covered patio/porch and a 637 sq. ft. attached garage per the approved plans and any notations. R-1B zoning and setbacks per planning. JJN
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.



All disturbed slopes included in the construction of this project must be stabilized and approved by Public Works before a Final Occupancy Permit is granted. If weather conditions prohibit revegetation and stabilization activities, the contractor shall provide a bond/surety agreement or an irrevocable letter of credit in the amount of 110% of the cost estimated by the project engineer to enable stabilization of the site. Call 208-608-7168 for an inspection.
NO SPRINKLERS REQUIRED. LGM.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/30/20204/30/20204/30/2020PPASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Ken Johnson
DOC - Permit Finaled4/30/20204/30/20204/30/2020PPASS
DetailsBrandon Shaw
PubWorks Occupancy Approval4/30/20204/30/20204/30/2020 DONE
DetailsMelissa Jannusch
A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works. Photos of the landscaping and a video of the drainage connection has been received by Public Works Final occupancy may be approved by the building department. Melissa Jannusch ###-####.

CHANGE STATUS TO (ISS)  4/20/2020 DONE
Per Brandon S, didn't mean to final
BLD-Conference4/17/20204/17/20204/17/2020PPASS
DetailsBrandon Shaw
Consult for final before Hillside is completre Phone #: ###-#### Inspection requested via web by Ken Johnson
DOC - Permit Finaled4/17/20204/17/20204/17/2020PPASS
DetailsBrandon Shaw
BLD-Foundation3/5/20203/5/20203/5/2020PPASS
DetailsBrandon Shaw
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
BLD-Footing2/24/20202/24/20202/24/2020PPASS
DetailsBrandon Shaw
Work in progress...
BLD-Foundation12/18/201912/19/201912/19/2019APASS
DetailsBrandon Shaw
wall // Wes Phone #: ###-####
CHANGE STATUS TO (ISS)  12/18/2019 DONE
PLAN MOD
OVERRIDE  12/6/2019  
Permit Ready to Issue  12/6/2019 DONE
DO NOT ISSUE- plan mod approved
Plan assigned to (J_N)10/28/201910/28/201912/5/2019 DONE
DetailsJenny Nelson
waiting for hillside. plan mod to grading plan, need new site plan
Routing PW Grading-Hillside12/5/2019 12/5/2019 PASS
DetailsMelissa Jannusch
PLAN MOD
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
BLD-Footing12/3/201912/3/201912/3/2019PPASS
DetailsBrandon Shaw
Wes Phone #: ###-####
Routing - PLAN CHECK12/2/2019 12/2/2019 PASS
DetailsJenny Nelson
Plan modification
BLD-Energy code compliance11/26/201911/26/201911/26/2019PPASS
DetailsBrandon Shaw
Ken - fire block inspection Phone #: ###-####
BLD-Energy code compliance11/22/201911/25/201911/25/2019PPASS
DetailsBrandon Shaw
Exterior walls only...
OK to cover exterior walls, cover one side of interior wall...
Routing - PLANNING11/5/2019 11/22/2019 PASS
DetailsJeff Lowe
pursuant to SOS19-00016
BLD-Framing/Rough-in11/20/201911/21/201911/21/2019APASS
DetailsBrandon Shaw
Ken Phone #: ###-####
Routing PW Grading-Hillside11/5/2019 11/19/2019 FAIL
DetailsMelissa Jannusch
PLAN mod fail. See changemarks in ePlan
Routing - PLAN CHECK10/28/2019 11/5/2019 FAIL
DetailsJenny Nelson
upload new site plan
Plan Modification Accepted  10/28/2019 DONE
Missy Jane of Babcock Design requested to start a plan mod to revise grading and elevation for driveway. Sheet AS101, and C1 to be uploaded.
BLD-Framing/Rough-in10/1/201910/2/201910/2/2019PPASS
DetailsBrandon Shaw
Wall bracing- Pending special Inspection, all of brace panel- OK
BLD-Concrete9/4/20199/5/20199/5/2019PPASS
DetailsBrandon Shaw
Inspection of reinforcing mesh in main part of house Phone #: ###-#### Inspection requested via web by Ken Johnson
BLD-Concrete9/4/20199/4/20199/4/2019PCANC
DetailsBrandon Shaw
Inspection of reinforcing mesh in main part of house >> Inspection requested via web by Ken Johnson Inspection cancelled from web by: Ken Johnson
BLD-Footing8/26/20198/27/20198/27/2019APASS
DetailsBrandon Shaw
Interior footing inspection Phone #: ###-#### Inspection requested via web by Ken Johnson
BLD-Foundation6/26/20196/26/20196/26/2019PPASS
DetailsBrandon Shaw
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
BLD-Footing6/12/20196/13/20196/13/2019APASS
DetailsBrandon Shaw
Work in progress...
PubWorks Subgrade Approval6/13/20196/13/20196/13/2019 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. A footing inspection may now be scheduled with the Building Department. Jason Taylor
Issue PAID IN FULL permit  5/8/2019 DONE
OVERRIDE  4/30/2019  
Routing - FIRE4/17/20194/17/20194/30/2019 PASS
DetailsLee G Meredith
04/23 Reifschneider residence LM Resubmittal. SUEZ fire flow report indicates adequate gpm to meet minimum requirements. Grading drawing indicates adequate dimensions and support for fire apparatus. No sprinklers required.
Plan assigned to (J_N)4/1/20194/1/20194/30/2019 DONE
DetailsJenny Nelson
04/08 sfd L2 ePlan. 2nd 4/19, structural calcs still 2012. 1st complete, spray foam esr, 310 special inspections, structural calcs code year
Routing - PLAN CHECK4/30/2019 4/30/2019 PASS
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  4/30/2019 DONE
DetailsJenny Nelson
Permit Ready to Issue  4/30/2019 DONE
Routing PW Grading-Hillside4/26/2019 4/26/2019 PASS
DetailsMelissa Jannusch

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.



All disturbed slopes included in the construction of this project must be stabilized and approved by Public Works before a Final Occupancy Permit is granted. If weather conditions prohibit revegetation and stabilization activities, the contractor shall provide a bond/surety agreement or an irrevocable letter of credit in the amount of 110% of the cost estimated by the project engineer to enable stabilization of the site. Call ###-#### for an inspection.
Routing - PLAN CHECK4/19/2019 4/19/2019 FAIL
DetailsJenny Nelson
1st review completed  4/3/2019 FAIL
DetailsJenny Nelson
Routing - PLAN CHECK3/20/2019 4/3/2019 FAIL
DetailsJenny Nelson
Plan assigned to (BJM)3/20/20193/20/20194/1/2019 DEFR
DetailsBrian McGowan
04/08 (L2 sfd) ePlan
Routing PW Grading-Hillside3/20/2019 4/1/2019 FAIL
DetailsMelissa Jannusch
See changemarks in ePlan
Routing - MECHANICAL3/20/2019 3/25/2019 PASS
DetailsChad Schwendiman
No Manual J, engineered plans instead
Route to Impact Fee Review3/20/20193/23/20193/21/2019 PASS
DetailsShannon Cade
Initial residential review of new SFD permits requested for now.
Routing - FIRE3/20/20193/20/20193/21/2019 FAIL
DetailsLee G Meredith
04/03 Reifschneider Residence Residential
Fire flow reqport required. Access distance exceeds 150 ft.
Routing - PLANNING3/20/2019 3/21/2019 PASS
DetailsJeff Lowe
Routing - Addressing3/20/2019 3/20/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS3/20/2019 3/20/2019 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment3/20/2019 3/20/2019 PASS
DetailsMichael Zawacki
Foothills lot, site prep inspection required.
Plans ACCEPTED BY PLAN TECH  3/20/2019 DONE
Recd Pcfee & Taken To Pln CK  3/20/2019 DONE
Intake Approval  3/20/2019 PASS
Intake Approval  3/19/2019 FAIL

1.Foundation Plan needs to be stamped by an engineer.
2.Manual J
3. Treads and Risers on stair section.
4. Wall bracing (Please indicate with a legend which walls are the bracing walls if using another drawing)
Meeting  3/19/2019 DONE
Applicant came to talk about corrections. Went through checklist and inform them that if they resubmit we can route for review and the MEC review (Furance and AC cals on drawing done and stamped by Engineer) and BLD review can go over the code for the sheets provided.
Intake Approval  3/18/2019 FAIL
1.Foundation Plan needs to be stamped by an engineer.
2.Manual J
3. Treads and Risers on stair section.
4. Wall bracing
Application received  3/7/2019 DONE
Application submitted via PDS Online on Mar 7 2019 11:39AM