First Notice | | 6/15/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
BLD-Final | 6/4/2019 | 6/5/2019 | 6/5/2019 | A | PASS |
Dave Hannah
|
|
|
Larrin Phone #: ###-####
|
Permanent Occupancy | | | 6/5/2019 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/22/2019 | 5/22/2019 | 5/22/2019 | A | PASS |
Jim Page
|
|
|
No fire sprinkler modifications, fire alarm inspection is complete, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete.
|
FIRE-Final Inspection | 5/13/2019 | 5/14/2019 | 5/14/2019 | A | FAIL |
Jim Page
|
|
|
Fire alarm failed inspection, need all FIR permits associated with project to be finaled before life safety can be completed.
Laren Phone #: ###-####
|
BLD-Framing/Rough-in | 4/9/2019 | 4/9/2019 | 4/9/2019 | P | PASS |
Dave Hannah
|
|
|
Laren Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/8/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/8/2019 | | |
|
|
|
|
Plan assigned to (JG) | 3/15/2019 | 3/15/2019 | 3/29/2019 | | PASS |
Javier Guzman
|
|
|
2nd rev, 3/21 L1 Tumwater Wealth Management ePlan
|
Routing - PLAN CHECK | 3/28/2019 | | 3/29/2019 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/29/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/29/2019 | | DONE |
|
|
|
met
|
Route to Impact Fee Review | 3/19/2019 | 3/22/2019 | 3/20/2019 | | PASS |
Karina Myles
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 3/15/2019 | | 3/19/2019 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 3/19/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 3/15/2019 | | 3/15/2019 | | PASS |
Doug Chausow
|
|
|
Ste 1610
|
Routing - PUBLIC WORKS | 3/15/2019 | | 3/15/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 3/14/2019 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 3/8/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 8 2019 10:17AM
|