BLD-Final | 4/16/2020 | 4/17/2020 | 4/17/2020 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Final | 4/15/2020 | 4/16/2020 | 4/16/2020 | A | FAIL |
Mike Jordan
|
|
|
Call aheadKevin - requesting virtual inspection Phone #: ###-####. provide egress ladder in window well. Lower handrail on stairs to basement. Inspection conducted via google duo.
|
BLD-Energy code compliance | 11/20/2019 | 11/21/2019 | 11/21/2019 | A | PASS |
Mike Jordan
|
|
|
not ready until 10 am // Kevin Phone #: ###-####
|
BLD-Framing/Rough-in | 11/19/2019 | 11/20/2019 | 11/20/2019 | A | PASS |
Mike Jordan
|
|
|
Jose Phone #: ###-####. All issues resolved except for tempered glazing, windows on order. ok to insulate.
|
BLD-Framing/Rough-in | 11/15/2019 | 11/18/2019 | 11/18/2019 | A | FAIL |
Mike Jordan
|
|
|
Kevin Phone #: ###-####. Complete airseal. Complete fireblocking. repair all broken floor joist, justify holes drilled into beams. Tempered glazing required at window by tub upstairs, and by french doors. strap all cut double top plates.
|
BLD-Framing/Rough-in | 11/15/2019 | 11/15/2019 | 11/15/2019 | P | NR |
Mike Jordan
|
|
|
Kevin Phone #: ###-####. Needs to complete airseal first.
|
BLD-Wall Bracing | 9/25/2019 | 9/30/2019 | 9/30/2019 | A | PASS |
Mike Jordan
|
|
|
Jose Phone #: ###-####
|
BLD-Conference | 9/17/2019 | 9/18/2019 | 9/18/2019 | A | DONE |
Mike Jordan
|
|
|
Kevin Phone #: ###-####
|
BLD-Foundation | 7/31/2019 | 8/1/2019 | 8/1/2019 | P | PART |
Mike Jordan
|
|
|
Jerimy Phone #: ###-####
|
BLD-Foundation | 7/8/2019 | 7/9/2019 | 7/9/2019 | P | CANC |
Mike Jordan
|
|
|
rebar // Cody Phone #: ###-####
|
BLD-Footing | 7/9/2019 | 7/9/2019 | 7/9/2019 | P | PART |
Mike Jordan
|
|
|
rebar // Cody Phone #: ###-####. Basement footings .
|
OVERRIDE | | | 5/13/2019 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 5/13/2019 | 5/13/2019 | 5/13/2019 | | PASS |
Josh Bogle
|
|
|
|
Routing Walk-In (BLD) | 5/13/2019 | 5/13/2019 | 5/13/2019 | P | DONE |
Josh Bogle
|
|
|
plan resubmittal
|
Plan assigned to (JAB) Josh | 5/6/2019 | 5/6/2019 | 5/13/2019 | | PASS |
Josh Bogle
|
|
|
5/10 addtion, paper - 1st done
|
Routing - PLAN CHECK | 5/13/2019 | | 5/13/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 5/13/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 5/13/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/13/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 5/13/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/13/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/13/2019 | | DONE |
|
|
|
Josh requested pages redone, customer resubmitting. Bracing plans, alterations to page S2.0 and A2.0
|
Routing - PLAN CHECK | 5/6/2019 | | 5/9/2019 | | FAIL |
Josh Bogle
|
|
|
beams apear innadequate, roof plans doesn't match other drawings - see e-mial to Kevin
|
Routing Walk-In (BLD) | 5/7/2019 | 5/7/2019 | 5/7/2019 | A | FAIL |
Josh Bogle
|
|
|
chatted about engineering details - dropped off a 2nd set of plans
|
Routing Walk-In (BLD) | 5/6/2019 | 5/6/2019 | 5/6/2019 | P | PASS |
Josh Bogle
|
|
|
took in as a level two
|
Routing Walk-In (Zoning) | 4/19/2019 | 4/19/2019 | 4/19/2019 | A | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (BLD) | 4/19/2019 | 4/19/2019 | 4/19/2019 | A | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 4/19/2019 | | 4/19/2019 | | FAIL |
Josh Bogle
|
|
|
plans don't match the engineering calcs
|
1st review completed | | | 4/19/2019 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 3/8/2019 | | | |
|
|
|
|