Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD19-00771
StatusFinaled
Name KREIZENBECK CONSTRUCTORS
Site Address 1075 N CURTIS RD Unit: 101
Project NameSARMC Vascular Clinic Remodel
Customer Number 
ePlanReviewYes
Description
(SARMC VASCULAR CLINIC) Permit to remodel two existing tenant suites in the south half of the first floor into a single 4,945 sq ft tenant suite for a new vascular clinic in an existing medical office building. Work to include: interior demolition of non-bearing walls, doors, and plumbing; construction of new interior non-bearing walls, doors, cabinetry and millwork; suspended grid ceilings; mechanical, electrical, and plumbing work; and new interior finishes in compliance with Ch. 8 of the 2015 IBC. Approval is contingent upon adhering to the approved plans on file. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 12/6/201912/9/2019 DONE
This permit finaled on the web by Brandon Byington
First Notice 11/18/201911/26/2019 DONE
mailed 12-2-19
Permanent Occupancy  11/8/2019 DONE
FIRE-Final Inspection11/7/201911/7/201911/7/2019PPASS
DetailsTroy Cobbley
Life safety passed.

Cecil Phone #: ###-####
BLD-Final10/22/201910/22/201910/22/2019PPASS
DetailsMike Jordan
cISEL Phone #: ###-####. Ok for temp occ. Will be ok for perm occ. once fire signs perm.
FIRE-Final Inspection10/21/201910/22/201910/22/2019APART
DetailsTroy Cobbley
Temp for life safety until the project related fire alarm permit is finaled. eciso Phone #: ###-####
BLD-Ceiling Grid Inspection9/20/20199/23/20199/23/2019APASS
DetailsMike Jordan
Cycle Phone #: ###-####
BLD-Framing/Rough-in7/17/20197/18/20197/18/2019APASS
DetailsMike Jordan
Cesal Phone #: ###-####. Interior steel stud framed walls and hardlids only at this time.
Issue PAID IN FULL permit  6/6/2019 DONE
Print Occupancy Form  6/6/2019 DONE
Meeting  6/4/2019 DONE
sent an email to aurora that we still need the 302 and 306 forms from the GC (someone paid the 4th review fee) and when the rest of the fees are paid they will have to let us know since we will not get a second email
Plan resubmittals received  6/3/2019 DONE
addition of a ups equipment in the basement electrical room and the required air conditioning associated with it
CHANGE STATUS TO (FEE)  6/3/2019 DONE
plan mod/resubmittal should have been for a different permit
Permit Ready to Issue  6/3/2019 DONE
MET (AURORAR@LCARCH.COM)
NEED
GC FORM
REVISED VALUE
Plan assigned to (JAR)3/29/20193/29/20196/1/2019 DONE
DetailsJulie Romig
06/05 - 4th Rev - 1st Rev Comp - L3 SARMC Vascular Clinic
Routing - PLAN CHECK5/30/2019 6/1/2019 PASS
DetailsJulie Romig
4th Review
PLANS/APPL TAKEN TO FRONT DESK  6/1/2019 DONE
Routing - PLAN CHECK5/10/2019 5/15/2019 FAIL
DetailsJulie Romig
Routing - PLAN CHECK5/7/2019 5/10/2019 FAIL
DetailsJulie Romig
Routing - FIRE5/7/20195/7/20195/8/2019 PASS
DetailsMark Scharfen
Uploaded med gas email pdf into tidemark and epermit. No changes to report already uploaded.
Route to Impact Fee Review4/24/20194/27/20194/25/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Routing - FIRE3/29/20193/29/20194/23/2019 PASS
DetailsMark Scharfen
IFC Review 04.23.2019.pdf uploaded.
1st review completed  4/23/2019 FAIL
DetailsJulie Romig
Routing - PLAN CHECK3/29/2019 4/23/2019 FAIL
DetailsJulie Romig
Routing - MECHANICAL3/29/2019 4/9/2019 PASS
DetailsTroy James
Routing - PUBLIC WORKS3/29/2019 4/3/2019 PASS
DetailsAngela Hardy
Routing - PLUMBING3/29/2019 4/1/2019 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - Addressing3/29/2019 3/29/2019 PASS
DetailsDoug Chausow
Note: Combining 3 Suites to 1, calling it Suite 101
Plan Reviewer's activity  3/27/2019 DONE
DetailsJulie Romig
Prescreen approved
Intake Approval  3/27/2019 PASS
Application received  3/12/2019 DONE
Application submitted via PDS Online on Mar 12 2019 1:43PM