BLD-Final | 10/3/2019 | 10/3/2019 | 10/3/2019 | P | PASS |
Jim Storey
|
|
|
access is 9378 Phone #: ###-#### Inspection requested via web by jarrod nelson
|
DOC - Permit Finaled | 10/3/2019 | 10/3/2019 | 10/3/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Blower Door Test Results | 10/3/2019 | 10/3/2019 | 10/3/2019 | P | DONE |
Jim Storey
|
|
|
access is 9378 Phone #: ###-#### Inspection requested via web by jarrod nelson 4.9
|
BLD-Energy code compliance | 8/11/2019 | 8/12/2019 | 8/12/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by jarrod nelson
|
BLD-Framing/Rough-in | 8/11/2019 | 8/12/2019 | 8/12/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by jarrod nelson
|
BLD-Framing/Rough-in | 8/5/2019 | 8/5/2019 | 8/5/2019 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Jarrod Nelson c/n 3 p[ly needs nailling per engineering// ok to insulate
|
BLD-Wall Bracing | 7/24/2019 | 7/24/2019 | 7/24/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Jarrod Nelson
|
BLD-Footing | 5/7/2019 | 5/7/2019 | 5/7/2019 | P | PASS |
Jim Storey
|
|
|
Derek Phone #: ###-####
|
Inspection Record Card- Bld | | | 4/2/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/2/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 3/29/2019 | | |
|
|
|
|
Plan assigned to (BJM) | 3/15/2019 | 3/15/2019 | 3/29/2019 | | DONE |
Brian McGowan
|
|
|
04/03 - 1st Review Complete 03/28 (L1 sfd) ePlan
|
Routing - PLAN CHECK | 3/29/2019 | | 3/29/2019 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/29/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 3/29/2019 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 3/15/2019 | | 3/26/2019 | | FAIL |
Brian McGowan
|
|
|
Spread footings required
|
1st review completed | | | 3/26/2019 | | FAIL |
Brian McGowan
|
|
|
|
Route to Impact Fee Review | 3/15/2019 | 3/18/2019 | 3/18/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Intake Approval | | | 3/15/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/15/2019 | | DONE |
|
|
|
|
Routing - MECHANICAL | 3/15/2019 | | 3/15/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 3/15/2019 | | 3/15/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 3/15/2019 | | 3/15/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/15/2019 | | 3/15/2019 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 3/13/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 13 2019 12:11PM
|