BLD-Final | 9/18/2019 | 9/18/2019 | 9/18/2019 | P | DONE |
Tony Young
|
|
|
Chris Phone #: ###-####
|
DOC - Permit Finaled | 9/18/2019 | 9/18/2019 | 9/18/2019 | P | PASS |
Tony Young
|
|
|
done per letter from engineer
|
BLD-Conference | 9/16/2019 | 9/18/2019 | 9/18/2019 | A | PASS |
Tony Young
|
|
|
Chris Phone #: ###-####.. plan reviewer recieved engineer letter.. filed to records
|
Routing Walk-In (BLD) | 9/18/2019 | 9/18/2019 | 9/18/2019 | A | PASS |
Josh Bogle
|
|
|
RDP took in 310 form for JAB
|
Plan Reviewer's activity | | | 9/18/2019 | | DONE |
Rob Patrick
|
|
|
Engineers Special Inspection letter was delivered today and scanned into the documents for this BLD number.
|
BLD-Foundation | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | PEND |
Tony Young
|
|
|
Inspect helical pier foundation repair. Phone #: ###-#### Inspection requested via web by Christophe Jones,, all special inspection,, covered,, no one around,, no answer
|
OVERRIDE | | | 7/1/2019 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/1/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/1/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 6/21/2019 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 3/26/2019 | 3/26/2019 | 6/21/2019 | | PASS |
Josh Bogle
|
|
|
3/19 helical piers, paper - 1st done
|
Plan Reviewer's activity | | | 6/21/2019 | | DONE |
Josh Bogle
|
|
|
outside strucural review received, passed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/21/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy no
|
Inspection Record Card- Bld | | | 6/21/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/21/2019 | | DONE |
|
|
|
Called and left a message and emailed that permit is ready to pick up and the fees due.
|
Routing Walk-In (BLD) | 6/10/2019 | 6/10/2019 | 6/10/2019 | P | PASS |
Josh Bogle
|
|
|
took in spare set of plans and routed to outside structural review
|
Routing - Erosion and Sediment | 6/7/2019 | | 6/7/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified RP listed. Install BMPs and post ESC permit sign at start of construction.
|
Plan Reviewer's activity | | | 6/7/2019 | | DONE |
Josh Bogle
|
|
|
Called & e-mailed applicant asking for an extra set of plans (to send off for outside structural review) and for them to choose a Special Inspector from the Approved list - noticed no ESC review was done, took to ESC
|
Routing PW Grading-Hillside | 5/23/2019 | | 6/5/2019 | | PASS |
Melissa Jannusch
|
|
|
SPECIAL INSPECTION REQUIRED FOR PLACEMENT OF PEIRS.
|
Routing Walk-In (BLD) | 5/23/2019 | 5/23/2019 | 5/23/2019 | P | PASS |
Josh Bogle
|
|
|
took in resubmittal docs and routed
|
Routing Off Site - STRUCTURAL | 5/23/2019 | | 5/23/2019 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 3/26/2019 | | 3/26/2019 | | FAIL |
Josh Bogle
|
|
|
missing structural engineering, ES report, & form #310
|
1st review completed | | | 3/26/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing PW Grading-Hillside | 3/26/2019 | | 3/26/2019 | | FAIL |
Melissa Jannusch
|
|
|
Needs Structural Calc packet and detail sheet
|
Routing - PUBLIC WORKS | 3/26/2019 | | 3/26/2019 | | FAIL |
Angela Hardy
|
|
|
|
Routing Walk-In (Zoning) | 3/13/2019 | 3/13/2019 | 3/13/2019 | P | PASS |
Leon Letson
|
|
|
|
Application received | | 3/13/2019 | | | |
|
|
|
|
Routing - PLAN CHECK | 6/5/2019 | | | | |
Josh Bogle
|
|
|
|