BLD-Final | 8/22/2019 | 8/23/2019 | 8/23/2019 | A | DONE |
Tony Young
|
|
|
Abe Phone #: ###-####,, recieved letter of acceptance from Tammarack Grove engineers , TGE19-12916, other c/n items made ok
|
DOC - Permit Finaled | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 7/22/2019 | 7/23/2019 | 7/23/2019 | A | FAIL |
Dave Hannah
|
|
|
Abe Phone #: ###-#### needs to hard wire smoke and co2 detectors and get cablegaurd rail final letter
|
BLD-Conference | 7/17/2019 | 7/18/2019 | 7/18/2019 | A | DONE |
Jim Storey
|
|
|
Abe Phone #: ###-####
|
BLD-Energy code compliance | 5/30/2019 | 5/30/2019 | 5/30/2019 | P | PASS |
Tony Young
|
|
|
Bobby Phone #: ###-####
|
BLD-Other | 5/23/2019 | 5/24/2019 | 5/24/2019 | A | PASS |
Dave Hannah
|
|
|
sofits- Addy Phone #: ###-####
|
BLD-Framing/Rough-in | 5/23/2019 | 5/24/2019 | 5/24/2019 | A | PASS |
Dave Hannah
|
|
|
Aby Phone #: ###-####
|
BLD-Wall Bracing | 5/16/2019 | 5/17/2019 | 5/17/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kristy Newkirk
|
BLD-Footing | 4/10/2019 | 4/11/2019 | 4/11/2019 | P | PART |
Tony Young
|
|
|
Will Phone #: ###-####,, deck footings ok
|
PubWorks Subgrade Approval | 4/11/2019 | 4/11/2019 | 4/11/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Foundation | 4/9/2019 | 4/10/2019 | 4/10/2019 | A | PART |
Tony Young
|
|
|
Will Phone #: ###-####,, foundation wall is work in progress,, ok to pour when ready
|
BLD-Foundation | 4/8/2019 | 4/9/2019 | 4/9/2019 | A | CANC |
Tony Young
|
|
|
Will Phone #: ###-####-Jared called to cancel inspection and he will call Tony to let him know
|
CHANGE STATUS TO (ISS) | | | 4/8/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 4/5/2019 | | |
|
|
|
|
Routing Walk-In (Zoning) | 4/5/2019 | 4/5/2019 | 4/5/2019 | P | PASS |
Sue Cummings
|
|
|
plan mod
|
Routing Walk-In (BLD) | 4/5/2019 | 4/5/2019 | 4/5/2019 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 4/5/2019 | | 4/5/2019 | | PASS |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 4/5/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/5/2019 | | DONE |
Josh Bogle
|
|
|
1/2 hr. Plan Review charge
|
Permit Ready to Issue | | | 4/5/2019 | | DONE |
|
|
|
Plan mod
|
Plan Modification Accepted | | | 4/5/2019 | | DONE |
|
|
|
Submitting more Struc. Calcs. for the beams and footings and making a few windows larger.
|
BLD-Footing | 4/3/2019 | 4/4/2019 | 4/4/2019 | A | PART |
Tony Young
|
|
|
Will Phone #: ###-####,, addition ok
|
PubWorks Subgrade Approval | 4/4/2019 | 4/4/2019 | 4/4/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Conference | 3/21/2019 | 3/25/2019 | 3/25/2019 | A | PART |
Tony Young
|
|
|
Will Phone #: ###-####,, general ?s,, soffit ?s,, foundation ?s,, existing soffits can be addressed by fire dept for anternatives
|
Issue PAID IN FULL permit | | | 3/21/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 3/20/2019 | | |
|
|
|
|
Telephone call | | | 3/20/2019 | | DONE |
|
|
|
Called Kristy to let know permit is ready and how much is owed-left message on her phone
|
Permit Ready to Issue | | | 3/20/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 3/13/2019 | 3/13/2019 | 3/19/2019 | | PASS |
Josh Bogle
|
|
|
3/19 addition, paper - Hillside
|
Routing - PLAN CHECK | 3/15/2019 | | 3/19/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 3/19/2019 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 3/19/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 3/19/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Routing - MECHANICAL | 3/13/2019 | | 3/15/2019 | | PASS |
Troy James
|
|
|
|
Routing PW Grading-Hillside | 3/15/2019 | | 3/15/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
|
Routing - PUBLIC WORKS | 3/13/2019 | | 3/15/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 3/13/2019 | | 3/15/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver request approved. Certified ESC Responsible Person provided. Site preparation inspection required.
|
Routing - PLANNING | 3/13/2019 | | 3/13/2019 | | PASS |
Colleen T Carroll
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/13/2019 | | DONE |
|
|
|
|
Intake Approval | | | 3/13/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/13/2019 | | DONE |
|
|
|
|
Application received | | 3/13/2019 | | | |
|
|
|
|