BLD-Final | 5/5/2020 | 5/6/2020 | 5/6/2020 | A | PASS |
Mike Jordan
|
|
|
Thanks Mike. Have a great day! Phone #: ###-#### Inspection requested via web by Scott Zierler
|
DOC - Permit Finaled | 5/6/2020 | 5/6/2020 | 5/6/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 5/6/2020 | 5/6/2020 | 5/6/2020 | A | DONE |
Mike Jordan
|
|
|
3.5
|
BLD-Final | 4/30/2020 | 5/5/2020 | 5/5/2020 | A | NR |
Mike Jordan
|
|
|
Hey Mike. Please call with lead time so I can meet you there. Thanks Scott Phone #: ###-#### Inspection requested via web by Scott Zierler. Needs landings and stairs. Everything else ok.
|
BLD-Final | 4/27/2020 | 4/29/2020 | 4/28/2020 | A | CANC |
Mike Jordan
|
|
|
Hi Mike. Please give me some lead time so I can meet you onsite. Thanks Scott ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Zierler Inspection cancelled from web by: Scott Zierler
|
BLD-Final | 4/25/2020 | 4/28/2020 | 4/27/2020 | A | CANC |
Mike Jordan
|
|
|
Hi Mike. Please give me some lead time so I can meet you onsite. Thanks Scott ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Zierler Inspection cancelled from web by: Scott Zierler
|
BLD-Conference | 7/8/2019 | 7/11/2019 | 7/11/2019 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Zierler
|
BLD-Framing/Rough-in | 7/10/2019 | 7/10/2019 | 7/10/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Zierler
|
BLD-Framing/Rough-in | 7/2/2019 | 7/3/2019 | 7/3/2019 | A | FAIL |
Mike Jordan
|
|
|
Thanks. Phone #: ###-#### Inspection requested via web by Scott Zierler. All issues resolved except fot notched F3 truss at bearing.
|
BLD-Framing/Rough-in | 6/27/2019 | 6/28/2019 | 6/28/2019 | A | FAIL |
Mike Jordan
|
|
|
Plans will be at the fireplace! Thanks Mike! Scott Phone #: ###-#### Inspection requested via web by Scott Zierler. Install straps for portal frames. Complete fire blockingat fir downs in main hallway by front door, both sides. Justify notched truss at bearing. (F3 truss). Roll block F1,F2,and F3 trusses, both sides. Nail C3 triple ply truss per the engineering and add stud under bearing. Complete lateral bracing on A4, A4A, A5, A6, A7 trusses. Correction notice posted. ok to insulate.
|
BLD-Energy code compliance | 6/27/2019 | 6/28/2019 | 6/28/2019 | A | CANC |
Mike Jordan
|
|
|
Thank you! Phone #: ###-#### Inspection requested via web by Scott Zierler
|
BLD-Wall Bracing | 5/28/2019 | 5/31/2019 | 5/31/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
Elevation Cert Rec'd-Midconst | | | 5/3/2019 | | DONE |
|
|
|
|
Routing PW Flood Plain | 5/3/2019 | | 5/3/2019 | | PASS |
Jason C. Taylor
|
|
|
recieved EC#2. Ok to proceed with framing. JCT
|
BLD-Foundation | 4/23/2019 | 4/24/2019 | 4/24/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru
|
BLD-Footing | 4/22/2019 | 4/23/2019 | 4/23/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru
|
Issue PAID IN FULL permit | | | 4/8/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 4/5/2019 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/5/2019 | | DONE |
|
|
|
|
Telephone call | | | 4/5/2019 | | DONE |
|
|
|
Left a message for Scott informing him that this permit is ready and the fee amount due for issuance
|
Permit Ready to Issue | | | 4/5/2019 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 4/4/2019 | | 4/4/2019 | | PASS |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 4/4/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/4/2019 | | DONE |
Rob Patrick
|
|
|
|
Plan assigned to (RDP) | 3/14/2019 | | 4/4/2019 | | DONE |
Rob Patrick
|
|
|
04/02 sfd L2 PAPER...03/29 Failed; Wall Bracing Corrections Req'd...took to JCT
|
Plan Reviewer's activity | | | 4/3/2019 | | |
Rob Patrick
|
|
|
04/03 Delivered dwg package back to JCT for review.
|
Routing PW Flood Plain | 4/3/2019 | | 4/3/2019 | | PASS |
Jason C. Taylor
|
|
|
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to framing/occupancy approval. Jason Taylor ###-####
|
Elevation Cert Rec'd-Prelim | | | 4/3/2019 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 4/3/2019 | | 4/3/2019 | | PASS |
Angela Hardy
|
|
|
|
Plan resubmittals received | | | 4/2/2019 | | DONE |
|
|
|
Resubmittals recieved 2 each-wall bracing and sheets A-2-took to Rob P
|
1st review completed | | | 3/29/2019 | | FAIL |
Rob Patrick
|
|
|
Wall Bracing Corrections Req'd
|
Routing - PLAN CHECK | 3/25/2019 | | 3/29/2019 | | FAIL |
Rob Patrick
|
|
|
Wall Bracing Corrections Req'd
|
Routing - MECHANICAL | 3/20/2019 | | 3/25/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | | | 3/20/2019 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 3/19/2019 | | 3/20/2019 | | FAIL |
Angela Hardy
|
|
|
FLOODPLAIN
|
Plan resubmittals received | | | 3/20/2019 | | DONE |
|
|
|
Resubmittals received-1 elevation cert & 2 sheets of A-1-took to Rob P
|
Plan Reviewer's activity | | | 3/20/2019 | | |
|
|
|
Delivered New Flood Plain comment sheets and Elevation Cert. to JCT.
|
Routing PW Flood Plain | 3/18/2019 | | 3/19/2019 | | FAIL |
Jason C. Taylor
|
|
|
Need revised plans and elevation certificate. JCT
|
Route to Impact Fee Review | 3/14/2019 | 3/17/2019 | 3/15/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 3/14/2019 | | 3/15/2019 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/14/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/14/2019 | | DONE |
|
|
|
|
Intake Approval | | | 3/14/2019 | | PASS |
|
|
|
|
Application received | | 3/14/2019 | | | |
|
|
|
|