Plan Reviewer's activity | | | 11/27/2019 | | DONE |
|
|
|
Paper drawings taken to Records
|
Third Notice | | 8/7/2019 | 9/19/2019 | | DONE |
|
|
|
mailed 9-20-19
|
Second Notice | | 7/20/2019 | 8/2/2019 | | DONE |
|
|
|
mailed 8/5/19
|
First Notice | 6/17/2019 | 6/17/2019 | 7/10/2019 | | DONE |
Mike Jordan
|
|
|
mailed 7-11
|
BLD-Final | 6/14/2019 | 6/17/2019 | 6/17/2019 | A | PASS |
Mike Jordan
|
|
|
Please call half hour before to meet // Ed Phone #: ###-####
|
DOC - Permit Finaled | 6/17/2019 | 6/17/2019 | 6/17/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 4/26/2019 | 4/26/2019 | 4/26/2019 | P | PASS |
Mike Jordan
|
|
|
Call on the way, wants to meet you there // Ed Phone #: ###-####. Interior steel stud framed walls ok.
|
Plan assigned to (CJW) | | | 4/24/2019 | | PASS |
Carl Westfall
|
|
|
* 04/17/19 (L-2 - 7 days) (paper - 3 sheets) Aero Specialties
|
Routing - PLAN CHECK | 4/9/2019 | | 4/24/2019 | | PASS |
Carl Westfall
|
|
|
|
1st review completed | | | 4/24/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/24/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/24/2019 | | DONE |
|
|
|
need GC
need rev cert of val
|
Inspection Record Card- Bld | | | 4/24/2019 | | DONE |
|
|
|
|
Telephone call | | | 4/24/2019 | | DONE |
|
|
|
Left voicemail for David to inform him the permit is ready and that we need the GC to fill out the GC Form and revised value.
|
Issue PAID IN FULL permit | | | 4/24/2019 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/9/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/9/2019 | | DONE |
|
|
|
|
Intake Approval | | | 4/9/2019 | | PASS |
|
|
|
|
Intake Approval | | | 3/15/2019 | | FAIL |
|
|
|
Need a completed application
|
Application received | | 3/15/2019 | | | |
|
|
|
|